MANGALSIDDHI ARCADE
by MANGALA AND ASSOCIATES · Ganesh Nagar, SindhudurgAlso near Jamsande
Possession date of MANGALSIDDHI ARCADE: 30 March 2027, moved from 12 August 2023 (39 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52900032540, and currently active. Its completion date has moved from August 2023 to March 2027: 39 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about MANGALSIDDHI ARCADE?
How the possession date of MANGALSIDDHI ARCADE has moved
12 August 2023
Completion date given when the project was registered
30 November 2026
Extended at the builder's request (MahaRERA application EA25082622379)
Reason the builder gave MahaRERA: “POST FACTO EXTENSION”
30 March 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: MANGALSIDDHI ARCADE’s extension records on MahaRERA (P52900032540), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on MANGALSIDDHI ARCADE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52900032540
- Status
- Registered and active
- Builder
- MANGALA AND ASSOCIATES
- Location
- Ganesh Nagar, Sindhudurg · 416612
- Project type
- Others
- Registered on
- 10 Jan 2022
- Completion date at registration
- August 2023
- Latest completion date
- March 2027
- Delay so far
- 39 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 26
- Sold or booked
- 69%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of MANGALSIDDHI ARCADE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MANGALSIDDHI ARCADE | 100% | 100% | 1001% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- MANGALSIDDHI ARCADE: covers 6 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MANGALSIDDHI ARCADE every month.
MANGALSIDDHI ARCADE: buildings, flats and land, as filed on MahaRERA
- Buildings: MANGALSIDDHI ARCADE (6 floors, 35 units)
- Car parking: 15 covered
- Land: 1,300 sq m (about 0.3 acres) · sanctioned built-up 2,634 sq m
- Boundaries filed include: Devgad Nipani state highway
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Mangala AND Associates (a group of 2 linked companies) has 3 projects on MahaRERA since 2022, this one included. Of the 3 GharKundli has checked: 3 still being built, 1 past the promised date (typically 35 months late). No complaints on MahaRERA.
Read Google reviews of MANGALSIDDHI ARCADE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MANGALSIDDHI ARCADE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MANGALSIDDHI ARCADE
What is the possession date of MANGALSIDDHI ARCADE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MANGALSIDDHI ARCADE in Ganesh Nagar, Sindhudurg is 30 March 2027 — 39 months later than 12 August 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for MANGALSIDDHI ARCADE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MANGALSIDDHI ARCADE's builder has filed on MahaRERA, the official one, is 30 March 2027, already 39 months later than the 12 August 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of MANGALSIDDHI ARCADE extended?
According to GharKundli's check of MahaRERA records (updated October 2026), MANGALSIDDHI ARCADE's builder applied to MahaRERA to extend the completion date once: to 30 November 2026, giving the reason "POST FACTO EXTENSION". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of MANGALSIDDHI ARCADE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MANGALSIDDHI ARCADE in Ganesh Nagar, Sindhudurg is P52900032540.
Is MANGALSIDDHI ARCADE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MANGALSIDDHI ARCADE is registered as P52900032540 and its status is "Registered and active".
What is the construction status of MANGALSIDDHI ARCADE?
According to GharKundli's check of MahaRERA records (updated October 2026), MANGALSIDDHI ARCADE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MANGALSIDDHI ARCADE is 100% done and internal work 1001%. GharKundli's full report compares construction progress with the deadline.
Does MANGALSIDDHI ARCADE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is MANGALSIDDHI ARCADE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), MANGALSIDDHI ARCADE is registered on MahaRERA as P52900032540, its completion date has moved 39 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if MANGALSIDDHI ARCADE's possession date changes?
The latest dates are on MANGALSIDDHI ARCADE's MahaRERA page (P52900032540). GharKundli's Kundli Watch sends a free WhatsApp update on MANGALSIDDHI ARCADE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MANGALSIDDHI ARCADE have?
According to GharKundli's check of MahaRERA records (updated October 2026), MANGALSIDDHI ARCADE has one building filed: MANGALSIDDHI ARCADE with 6 floors and 35 units.
How much parking does MANGALSIDDHI ARCADE have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 15 covered car parking spaces for MANGALSIDDHI ARCADE.
How big is the land of MANGALSIDDHI ARCADE?
According to GharKundli's check of MahaRERA records (updated October 2026), MANGALSIDDHI ARCADE stands on 1,300 sq m of land (about 0.3 acres), with 2,634 sq m of sanctioned built-up area.
What is the track record of MANGALSIDDHI ARCADE's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Mangala AND Associates (a group of 2 linked companies) has 3 projects on MahaRERA since 2022, this one included. Of the 3 GharKundli has checked: 3 still being built, 1 past the promised date (typically 35 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of MANGALSIDDHI ARCADE?
Google Maps has reviews of MANGALSIDDHI ARCADE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MANGALSIDDHI ARCADE?
MANGALSIDDHI ARCADE by MANGALA AND ASSOCIATES is in Ganesh Nagar, Sindhudurg (pincode 416612), near Jamsande, Maharashtra, and is registered on MahaRERA as P52900032540, per GharKundli's check of MahaRERA records. Its boundaries filed there include Devgad Nipani state highway.
How many homes are in MANGALSIDDHI ARCADE?
According to GharKundli's check of MahaRERA records (updated October 2026), MANGALSIDDHI ARCADE has 26 homes in 1 tower registered on MahaRERA, and 69% of them are sold or booked.
When was MANGALSIDDHI ARCADE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MANGALSIDDHI ARCADE was registered on MahaRERA on 10 January 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on MANGALSIDDHI ARCADE?
No court cases are listed for MANGALSIDDHI ARCADE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of MANGALSIDDHI ARCADE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MANGALA AND ASSOCIATES, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of MANGALSIDDHI ARCADE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Sindhudurg →
Other projects in Devgad
- RA URBANIA
- Sushila
- AMAR GALAXY PHASE - I
- Omkar Complex Phase 2
- KRUPASINDHU
- RAMESHWAR COMPLEX
- PMAY EWS 240 tenement at Devgad jamsande
- DEVDURG ELITES
Other projects by MANGALA AND ASSOCIATES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.