AYAANS AMBARY

by Suman Developers · Malvan, Sindhudurg

Possession date of AYAANS AMBARY: 30 October 2027, moved from 30 June 2026 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52900053470, and currently active. Its completion date has moved from June 2026 to October 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about AYAANS AMBARY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of AYAANS AMBARY has moved

  1. 30 June 2026

    Completion date given when the project was registered

  2. 30 June 2027

    Extended at the builder's request (MahaRERA application EA09092502540)

    Reason the builder gave MahaRERA:
    “The extension is essential to maintain the validity of the project registration, without the extension, the registration will lapse, which will: Halt ongoing construction work. Stall disbursement of home loans by banks / financial instituti…” Read the full reason“The extension is essential to maintain the validity of the project registration, without the extension, the registration will lapse, which will: Halt ongoing construction work. Stall disbursement of home loans by banks / financial institutions. Prevent registration of new agreements for sale. Result in severe cash flow disruption, adversely affecting allottees. The project has been delayed due to circumstances beyond the control of the Promoter, such as: Shortage of labour and demand slump triggered by market volatility. Unavailability of skilled labour and labour migration issues, leading…”
  3. 30 October 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: AYAANS AMBARY’s extension records on MahaRERA (P52900053470), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on AYAANS AMBARY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52900053470
Status
Registered and active
Builder
Suman Developers
Location
Malvan, Sindhudurg · 416606
Project type
Others
Registered on
6 Nov 2023
Completion date at registration
June 2026
Latest completion date
October 2027
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
42
Sold or booked
23%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of AYAANS AMBARY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AYAANS AMBARY100%100%70%0%

Commencement certificate (CC), as filed on MahaRERA

  • AYAANS AMBARY: covers Ground+7 Floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on AYAANS AMBARY every month.

AYAANS AMBARY: buildings, flats and land, as filed on MahaRERA

  • Buildings: AYAANS AMBARY (8 floors, 57 units)
  • Land: 940 sq m (about 0.2 acres) · sanctioned built-up 3,266 sq m
  • Boundaries filed include: Muncipal Road

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of AYAANS AMBARY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

AYAANS AMBARY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about AYAANS AMBARY

What is the possession date of AYAANS AMBARY?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AYAANS AMBARY in Malvan, Sindhudurg is 30 October 2027 — 12 months later than 30 June 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for AYAANS AMBARY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date AYAANS AMBARY's builder has filed on MahaRERA, the official one, is 30 October 2027, already 12 months later than the 30 June 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of AYAANS AMBARY extended?

According to GharKundli's check of MahaRERA records (updated October 2026), AYAANS AMBARY's builder applied to MahaRERA to extend the completion date once: to 30 June 2027, giving the reason "The extension is essential to maintain the validity of the project registration, without the extension, the registration will lapse, which will: Halt ongoing construction work. Stall disbursement of home loans by banks / financial institutions. Prevent registration of new agreements for sale. Result in severe cash flow disruption, adversely affecting allottees. The project has been delayed due to circumstances beyond the control of the Promoter, such as: Shortage of labour and demand slump triggered by market volatility. Unavailability of skilled labour and labour migration issues, leading…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of AYAANS AMBARY?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AYAANS AMBARY in Malvan, Sindhudurg is P52900053470.

Is AYAANS AMBARY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AYAANS AMBARY is registered as P52900053470 and its status is "Registered and active".

What is the construction status of AYAANS AMBARY?

According to GharKundli's check of MahaRERA records (updated October 2026), AYAANS AMBARY's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AYAANS AMBARY is 100% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.

Does AYAANS AMBARY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is AYAANS AMBARY safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), AYAANS AMBARY is registered on MahaRERA as P52900053470, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if AYAANS AMBARY's possession date changes?

The latest dates are on AYAANS AMBARY's MahaRERA page (P52900053470). GharKundli's Kundli Watch sends a free WhatsApp update on AYAANS AMBARY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does AYAANS AMBARY have?

According to GharKundli's check of MahaRERA records (updated October 2026), AYAANS AMBARY has one building filed: AYAANS AMBARY with 8 floors and 57 units.

How big is the land of AYAANS AMBARY?

According to GharKundli's check of MahaRERA records (updated October 2026), AYAANS AMBARY stands on 940 sq m of land (about 0.2 acres), with 3,266 sq m of sanctioned built-up area.

Where can I read reviews of AYAANS AMBARY?

Google Maps has reviews of AYAANS AMBARY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is AYAANS AMBARY?

AYAANS AMBARY by Suman Developers is in Malvan, Sindhudurg (pincode 416606), Maharashtra, and is registered on MahaRERA as P52900053470, per GharKundli's check of MahaRERA records. Its boundaries filed there include Muncipal Road.

How many homes are in AYAANS AMBARY?

According to GharKundli's check of MahaRERA records (updated October 2026), AYAANS AMBARY has 42 homes in 1 tower registered on MahaRERA, and 23% of them are sold or booked.

When was AYAANS AMBARY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AYAANS AMBARY was registered on MahaRERA on 6 November 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on AYAANS AMBARY?

No court cases are listed for AYAANS AMBARY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of AYAANS AMBARY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Suman Developers.

All projects with possession due in 2027 in Sindhudurg →

Other projects in pincode 416606

All 21 projects in Malvan (416606) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.