Dattatray Residency
by Sana Homes Private Limited · Kumbharmath, SindhudurgAlso near Malvan
Possession date of Dattatray Residency: 31 May 2028, moved from 30 September 2019 (104 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52900007388, and currently active. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Dattatray Residency?
How the possession date of Dattatray Residency has moved
30 September 2019
Completion date given when the project was registered
29 September 2020
Extended at the builder's request (MahaRERA application EXT52900003722)
Reason the builder gave MahaRERA:
“Delay in getting height permission from 12 mtr to 15 mtr .(Application dated 01/06/2017 and permission received on 30/08/2019), Sand not available due to non opening of tender by Sindhudurga Collector from September 2017 to February 2018. H…” Read the full reason
“Delay in getting height permission from 12 mtr to 15 mtr .(Application dated 01/06/2017 and permission received on 30/08/2019), Sand not available due to non opening of tender by Sindhudurga Collector from September 2017 to February 2018. Heavy rain and flood in the monsoon for the period June 2018 to August 2018 and June, 2019 to October, 2019. Malvan in Sindhudurga is 516 km away from Mumbai and due to weather problem difficulty in arrangement of labour etc.”31 December 2022
Extended at the builder's request (MahaRERA application EXT52900008596)
Reason the builder gave MahaRERA: “Pandemic COVID 19 and non availability of labour and material, Heavy Rain. detailed letter attached”
31 December 2024
Extended at the builder's request (MahaRERA application EXT52900016633)
Reason the builder gave MahaRERA:
“COVID-19 pandemic, shortage of skilled labour, change in material credit policies in the market, extended rain till October, 22. Due to first festival after COVID-19 out of state resumed the work by February-March 2023. Also unseasonal Mons…” Read the full reason
“COVID-19 pandemic, shortage of skilled labour, change in material credit policies in the market, extended rain till October, 22. Due to first festival after COVID-19 out of state resumed the work by February-March 2023. Also unseasonal Monsoon in the month of March and April 2023 finishing, waterproofing work affected. Coming heavy monsoon in Konkan region will also delay the finishing work. Commercial building work not yet started. OC procedure of four buildings will take time. so need extension.”31 May 2026
Extended at the builder's request (MahaRERA application EXT52900025838)
Reason the builder gave MahaRERA:
“Since COVID-19 pandemic we are facing shortage of skilled labour and change in credit policies in the market, which affect construction work a lot. Our project is in the rural area therefore we face lots of transportation and other problems…” Read the full reason
“Since COVID-19 pandemic we are facing shortage of skilled labour and change in credit policies in the market, which affect construction work a lot. Our project is in the rural area therefore we face lots of transportation and other problems. In the year 2024 we were unable to speed up work as there was a heavy rain from June, 2024 till September, 2024 and unexpected rainfall in Konkan region due to cyclone in south India in the month of October, 2024 and November, 2024. Due to festivals like Holi and Gudi Padawa out of state labour did not resume the work in February and March 2024. Our wat…”31 May 2028
Extended at the builder's request (MahaRERA application EA27052621120)
Reason the builder gave MahaRERA:
“Till date we have completed 100% work of Building No. 1, 80% work of Building No. 2 and 70% work of Building No. 3. All are residential buildings. We have not yet started work of Commercial-cum-residential Building. As we are planning to co…” Read the full reason
“Till date we have completed 100% work of Building No. 1, 80% work of Building No. 2 and 70% work of Building No. 3. All are residential buildings. We have not yet started work of Commercial-cum-residential Building. As we are planning to complete the work of residential buildings first; we have not sold a single unit in commercial-cum-residential building. Since COVID-19 pandemic we are facing shortage of skilled labour and change in credit policies in the market, which affect construction work a lot. Our project is in the rural area therefore we face lots of transportation and other proble…”
Source: Dattatray Residency’s extension records on MahaRERA (P52900007388), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Dattatray Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the May 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52900007388
- Status
- Registered and active
- Builder
- Sana Homes Private Limited
- Location
- Kumbharmath, Sindhudurg · 416606
- Project type
- Others
- Registered on
- 17 Aug 2017
- Completion date at registration
- September 2019
- Latest completion date
- May 2028
- Delay so far
- 104 months
- Towers
- 4
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Appeals at the tribunal
- 2
- Title report on file
- Not found
Construction progress of Dattatray Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Blossom Wing A,B,C | 100% | 100% | 90% | 90% |
| Daffodil Wing D,E | 100% | 100% | 80% | 40% |
| Orchid Wing F,G,H | 100% | 100% | 80% | 20% |
| Sana Pride | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Dattatray Residency every month.
Dattatray Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: Blossom Wing A,B,C (6 floors) · Daffodil Wing D,E (5 floors) · Orchid Wing F,G,H (5 floors) · Sana Pride (4 floors)
- Car parking: 54 open
- Land: 9,250 sq m (about 2.3 acres) · sanctioned built-up 7,031 sq m · recreational space 925 sq m
- Boundaries filed include: Malvan-Kasal Road
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Dattatray Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Dattatray Residency: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Dattatray Residency
What is the possession date of Dattatray Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Dattatray Residency in Kumbharmath, Sindhudurg is 31 May 2028 — 104 months later than 30 September 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Dattatray Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Dattatray Residency's builder has filed on MahaRERA, the official one, is 31 May 2028, already 104 months later than the 30 September 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Dattatray Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Dattatray Residency's builder applied to MahaRERA to extend the completion date 5 times: to 29 September 2020, giving the reason "Delay in getting height permission from 12 mtr to 15 mtr .(Application dated 01/06/2017 and permission received on 30/08/2019), Sand not available due to non opening of tender by Sindhudurga Collector from September 2017 to February 2018. Heavy rain and flood in the monsoon for the period June 2018 to August 2018 and June, 2019 to October, 2019. Malvan in Sindhudurga is 516 km away from Mumbai and due to weather problem difficulty in arrangement of labour etc."; to 31 December 2022, giving the reason "Pandemic COVID 19 and non availability of labour and material, Heavy Rain. detailed letter attached"; to 31 December 2024, giving the reason "COVID-19 pandemic, shortage of skilled labour, change in material credit policies in the market, extended rain till October, 22. Due to first festival after COVID-19 out of state resumed the work by February-March 2023. Also unseasonal Monsoon in the month of March and April 2023 finishing, waterproofing work affected. Coming heavy monsoon in Konkan region will also delay the finishing work. Commercial building work not yet started. OC procedure of four buildings will take time. so need extension."; to 31 May 2026, giving the reason "Since COVID-19 pandemic we are facing shortage of skilled labour and change in credit policies in the market, which affect construction work a lot. Our project is in the rural area therefore we face lots of transportation and other problems. In the year 2024 we were unable to speed up work as there was a heavy rain from June, 2024 till September, 2024 and unexpected rainfall in Konkan region due to cyclone in south India in the month of October, 2024 and November, 2024. Due to festivals like Holi and Gudi Padawa out of state labour did not resume the work in February and March 2024. Our wat…"; to 31 May 2028, giving the reason "Till date we have completed 100% work of Building No. 1, 80% work of Building No. 2 and 70% work of Building No. 3. All are residential buildings. We have not yet started work of Commercial-cum-residential Building. As we are planning to complete the work of residential buildings first; we have not sold a single unit in commercial-cum-residential building. Since COVID-19 pandemic we are facing shortage of skilled labour and change in credit policies in the market, which affect construction work a lot. Our project is in the rural area therefore we face lots of transportation and other proble…".
What is the RERA number of Dattatray Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Dattatray Residency in Kumbharmath, Sindhudurg is P52900007388.
Is Dattatray Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Dattatray Residency is registered as P52900007388 and its status is "Registered and active".
What is the construction status of Dattatray Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Dattatray Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does Dattatray Residency have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Dattatray Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Dattatray Residency is registered on MahaRERA as P52900007388, its completion date has moved 104 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Dattatray Residency's possession date changes?
The latest dates are on Dattatray Residency's MahaRERA page (P52900007388). GharKundli's Kundli Watch sends a free WhatsApp update on Dattatray Residency every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Dattatray Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Dattatray Residency has 4 buildings filed: Blossom Wing A,B,C with 6 floors; Daffodil Wing D,E with 5 floors; Orchid Wing F,G,H with 5 floors; Sana Pride with 4 floors.
How much parking does Dattatray Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 54 open car parking spaces for Dattatray Residency.
How big is the land of Dattatray Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Dattatray Residency stands on 9,250 sq m of land (about 2.3 acres), with 7,031 sq m of sanctioned built-up area and 925 sq m of recreational open space.
Where can I read reviews of Dattatray Residency?
Google Maps has reviews of Dattatray Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Dattatray Residency?
Dattatray Residency by Sana Homes Private Limited is in Kumbharmath, Sindhudurg (pincode 416606), near Malvan, Maharashtra, and is registered on MahaRERA as P52900007388, per GharKundli's check of MahaRERA records. Its boundaries filed there include Malvan-Kasal Road.
When was Dattatray Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Dattatray Residency was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Dattatray Residency?
No court cases are listed for Dattatray Residency on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Dattatray Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sana Homes Private Limited.
Check it yourself on MahaRERA
- How to check the possession date of Dattatray Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Sindhudurg →
Other projects in Malwan
- SHIVSRUSHTI
- AYAANS AMBARY
- Horizon Grande Wing K
- Athang Ganga
- Sunsmit Vedic Village
- ATHANG LAXMI
- SEA MERIDIAN
- MAITRI RESIDENCY
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.