VRUKSHAVALLI B2
by VIJAY GANGARAM NAIK · Malgaon, SindhudurgAlso near Sawantwadi
Possession date of VRUKSHAVALLI B2: 29 March 2024, moved from 30 March 2023 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52900018490. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (March 2024) has passed.
What do you want to know about VRUKSHAVALLI B2?
How the possession date of VRUKSHAVALLI B2 has moved
30 March 2023
Completion date given when the project was registered
29 March 2024
Extended at the builder's request (MahaRERA application EXT52900015288)
Reason the builder gave MahaRERA: “DUE TO FINANCIAL CONSTRAINT AND COVID, PROJECT WAS STUCK. WE HAVE ONCE AGAIN REINFUSED CAPITAL AND STARTED PROJECT, EXPECTED TO COMPLETE BEFORE PROPOSED DATE 29/03/2024”
Source: VRUKSHAVALLI B2’s extension records on MahaRERA (P52900018490), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on VRUKSHAVALLI B2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- VRUKSHAVALLI B-4P52900046973 · possession 30 Apr 2027
- MahaRERA registration
- P52900018490
- Status
- Lapsed (registration period ended)
- Builder
- VIJAY GANGARAM NAIK
- Location
- Malgaon, Sindhudurg · 416510
- Project type
- Residential / Group Housing
- Registered on
- 12 Nov 2018
- Completion date at registration
- March 2023
- Latest completion date
- March 2024
- Delay so far
- 12 months
- Homes
- 45
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of VRUKSHAVALLI B2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| VRUKSHAVALLI B2 | 100% | 100% | 100% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on VRUKSHAVALLI B2 every month.
VRUKSHAVALLI B2: buildings, flats and land, as filed on MahaRERA
- Buildings: VRUKSHAVALLI B2 (4 floors)
- Land: 2,000 sq m (about 0.5 acres) · sanctioned built-up 1,949 sq m
The builder’s record and reviews
Vijay Gangaram Naik has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 6 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of VRUKSHAVALLI B2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
VRUKSHAVALLI B2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about VRUKSHAVALLI B2
What is the possession date of VRUKSHAVALLI B2?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for VRUKSHAVALLI B2 in Malgaon, Sindhudurg is 29 March 2024 — 12 months later than 30 March 2023, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for VRUKSHAVALLI B2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date VRUKSHAVALLI B2's builder has filed on MahaRERA, the official one, is 29 March 2024, already 12 months later than the 30 March 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of VRUKSHAVALLI B2 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), VRUKSHAVALLI B2's builder applied to MahaRERA to extend the completion date once: to 29 March 2024, giving the reason "DUE TO FINANCIAL CONSTRAINT AND COVID, PROJECT WAS STUCK. WE HAVE ONCE AGAIN REINFUSED CAPITAL AND STARTED PROJECT, EXPECTED TO COMPLETE BEFORE PROPOSED DATE 29/03/2024".
What is the RERA number of VRUKSHAVALLI B2?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of VRUKSHAVALLI B2 in Malgaon, Sindhudurg is P52900018490.
Is VRUKSHAVALLI B2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), VRUKSHAVALLI B2 is registered as P52900018490 and its status is "Lapsed (registration period ended)".
What is the construction status of VRUKSHAVALLI B2?
According to GharKundli's check of MahaRERA records (updated November 2026), VRUKSHAVALLI B2's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on VRUKSHAVALLI B2 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does VRUKSHAVALLI B2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is VRUKSHAVALLI B2 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), VRUKSHAVALLI B2 is registered on MahaRERA as P52900018490, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does VRUKSHAVALLI B2 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: VRUKSHAVALLI B-4 (P52900046973, possession 30 Apr 2027). Check that your agreement names the registration of your own wing.
How can I get updates if VRUKSHAVALLI B2's possession date changes?
The latest dates are on VRUKSHAVALLI B2's MahaRERA page (P52900018490). GharKundli's Kundli Watch sends a free WhatsApp update on VRUKSHAVALLI B2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does VRUKSHAVALLI B2 have?
According to GharKundli's check of MahaRERA records (updated November 2026), VRUKSHAVALLI B2 has one building filed: VRUKSHAVALLI B2 with 4 floors.
How big is the land of VRUKSHAVALLI B2?
According to GharKundli's check of MahaRERA records (updated November 2026), VRUKSHAVALLI B2 stands on 2,000 sq m of land (about 0.5 acres), with 1,949 sq m of sanctioned built-up area.
What is the track record of VRUKSHAVALLI B2's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Vijay Gangaram Naik has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 6 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of VRUKSHAVALLI B2?
Google Maps has reviews of VRUKSHAVALLI B2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is VRUKSHAVALLI B2?
VRUKSHAVALLI B2 by VIJAY GANGARAM NAIK is in Malgaon, Sindhudurg (pincode 416510), near Sawantwadi, Maharashtra, and is registered on MahaRERA as P52900018490, per GharKundli's check of MahaRERA records.
How many homes are in VRUKSHAVALLI B2?
According to GharKundli's check of MahaRERA records (updated November 2026), VRUKSHAVALLI B2 has 45 homes in 1 tower registered on MahaRERA.
When was VRUKSHAVALLI B2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), VRUKSHAVALLI B2 was registered on MahaRERA on 12 November 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on VRUKSHAVALLI B2?
No court cases are listed for VRUKSHAVALLI B2 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of VRUKSHAVALLI B2?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VIJAY GANGARAM NAIK, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of VRUKSHAVALLI B2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 416510
- HERITAGE HOMES
- SAWANTWADI ENCLAVE
- VRUKSHAVALLI B-4
- ANAADIH SHRI DATTA
- GOBIND SRUSHTI
- Unnati Heights
- HNS Valley
- Marlin Plots
Other projects by VIJAY GANGARAM NAIK
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.