NAGMANI
by AJAY BHAUSO JADHAV · Shirala, Sangli
Registered on MahaRERA under P53100077343, and currently active. Its completion date has moved from March 2025 to April 2027: 21 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on NAGMANI
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P53100077343
- Status
- Registered and active
- Builder
- AJAY BHAUSO JADHAV
- Location
- Shirala, Sangli · 415408
- Project type
- Others
- Registered on
- 9 Aug 2024
- Completion date at registration
- March 2025
- Latest completion date
- April 2027
- Delay so far
- 21 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 32
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Kundli Watch
NAGMANI: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about NAGMANI
Is NAGMANI registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), NAGMANI is registered as P53100077343 and its status is "Registered and active".
Where is NAGMANI?
NAGMANI by AJAY BHAUSO JADHAV is in Shirala, Sangli (pincode 415408), Maharashtra, and is registered on MahaRERA as P53100077343, per GharKundli's check of MahaRERA records.
When is possession of NAGMANI due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for NAGMANI in Shirala, Sangli is 30 April 2027 — 21 months later than 12 March 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Does NAGMANI have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
How many homes are in NAGMANI?
According to GharKundli's check of MahaRERA records (updated October 2026), NAGMANI has 32 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was NAGMANI registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), NAGMANI was registered on MahaRERA on 9 August 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on NAGMANI?
No court cases are listed for NAGMANI on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of NAGMANI?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AJAY BHAUSO JADHAV.
All projects with possession due in 2027 in Sangli →
Other projects in pincode 415408
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.