Possession due in 2027 · Sangli
According to GharKundli's check of MahaRERA records, 11 housing projects in Sangli have a MahaRERA completion date in 2027, out of 38 Sangli projects GharKundli has read in detail so far.
The date is the latest completion date the builder has filed on MahaRERA, including MahaRERA’s automatic 4-month extension of August 2026 where it applies. “First promised” is the date given at registration. Completed projects are not listed. Open a project for its full MahaRERA record.
| Project | Where | Possession due (MahaRERA) | First promised | Complaints |
|---|---|---|---|---|
| MEGH MALHAR RESIDENCY MALHAR BUILDCON | Kupwad | 31 Mar 2027 | 31 Mar 2026 | 0 |
| MALHAR PLAZA SHINTRE SHETE DEVLOPERS | Opp Mahasoba Gate | 30 Apr 2027 | 15 Jun 2025 | 0 |
| NAGMANI AJAY BHAUSO JADHAV | Shirala | 30 Apr 2027 | 12 Mar 2025 | 0 |
| UNITY HARMONY UNITY CONTRACTORS | near bapat colony | 30 Apr 2027 | 31 Dec 2025 | 0 |
| VEDANT DEWELLS YOGIVALLABH BUILDERS AND DEVELOPERS | Old Kupwad Road | 30 Apr 2027 | 31 Dec 2025 | 0 |
| VISHNU HARI REGENCY AVANEESH BUILDCON LLP | Opp Ghanshyam Nagar | 30 Apr 2027 | 31 Dec 2025 | 0 |
| Airawat SHUBHASHREEDEVELOPERS | Sangli Miraj Kupwad (M Corp.) | 31 Jul 2027 | 9 Apr 2026 | 0 |
| Avantika Residency UTTAM LAHU MOHITE | Samarth Nagar | 31 Jul 2027 | 31 Dec 2024 | 0 |
| SHREE RAJLAXMI MALL SHREE RAJLAXMI CONSTRUCTIONS AND BUILDERS | S S K Sakharale | 30 Sep 2027 | 30 Jul 2024 | 0 |
| SAICHARAN HEIGHTS ASHTANG DEVELOPERS | Waranali, Sangli | 30 Oct 2027 | 30 Jun 2026 | 0 |
| PRUTHVI PLAZA MAHADEV SADASHIV PATIL | Sangli Road | 30 Nov 2027 | 28 Nov 2021 | 0 |
Other years in Sangli: 2026 (3) · 2028 (5) · 2029 (3) · 2030 (4) · 2031 (1)
Source: GharKundli’s check of MahaRERA records. More projects appear as GharKundli reads them.