Skip to content
GharKundli

Airawat

by SHUBHASHREEDEVELOPERS · Sangli Miraj Kupwad (M Corp.), Sangli

Possession date of Airawat: 31 July 2027, moved from 9 April 2026 (11 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P53100054007, and currently active. Its completion date has moved from April 2026 to July 2027: 11 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Airawat?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Airawat has moved

  1. 9 April 2026

    Completion date given when the project was registered

  2. 31 March 2027

    Extended at the builder's request (MahaRERA application EA30032620441)

    Reason the builder gave MahaRERA:
    “1. The project stands at 85% completion. 2. The consent of 63.64% of allottees has been uploaded in support of this extension application. 3. Form B uploaded. 4. PERT for the remaining completion work is uploaded in the Application. 5. The…” Read the full reason“1. The project stands at 85% completion. 2. The consent of 63.64% of allottees has been uploaded in support of this extension application. 3. Form B uploaded. 4. PERT for the remaining completion work is uploaded in the Application. 5. The Project got delayed due to following reasons: a) Financial Constraints: Intermittent funding issues and cash flow disruptions affected procurement and continuity of construction work. b) Shortage of Labour & Materials: Limited availability of skilled labour and delays in material supply impacted progress, though the situation has now stabilised. c) Increa…”
  3. 31 July 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Airawat’s extension records on MahaRERA (P53100054007), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Airawat

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P53100054007
Status
Registered and active
Builder
SHUBHASHREEDEVELOPERS
Location
Sangli Miraj Kupwad (M Corp.), Sangli · 416416
Project type
Others
Registered on
19 Dec 2023
Completion date at registration
April 2026
Latest completion date
July 2027
Delay so far
11 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
25
Sold or booked
58%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Airawat, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Airawat100%100%80%30%

Commencement certificate (CC), as filed on MahaRERA

  • Airawat: covers 10 floors

Latest CC order on MahaRERA: dated 09/06/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Airawat every month.

Airawat: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Airawat →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Airawat: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Airawat

What is the possession date of Airawat?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Airawat in Sangli Miraj Kupwad (M Corp.), Sangli is 31 July 2027 — 11 months later than 9 April 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Airawat?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Airawat's builder has filed on MahaRERA, the official one, is 31 July 2027, already 11 months later than the 9 April 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Airawat extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Airawat's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "1. The project stands at 85% completion. 2. The consent of 63.64% of allottees has been uploaded in support of this extension application. 3. Form B uploaded. 4. PERT for the remaining completion work is uploaded in the Application. 5. The Project got delayed due to following reasons: a) Financial Constraints: Intermittent funding issues and cash flow disruptions affected procurement and continuity of construction work. b) Shortage of Labour & Materials: Limited availability of skilled labour and delays in material supply impacted progress, though the situation has now stabilised. c) Increa…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Airawat?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Airawat in Sangli Miraj Kupwad (M Corp.), Sangli is P53100054007.

Is Airawat registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Airawat is registered as P53100054007 and its status is "Registered and active".

What is the construction status of Airawat?

According to GharKundli's check of MahaRERA records (updated October 2026), Airawat's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Airawat is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does Airawat have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Airawat safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Airawat is registered on MahaRERA as P53100054007, its completion date has moved 11 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Airawat's possession date changes?

The latest dates are on Airawat's MahaRERA page (P53100054007). GharKundli's Kundli Watch sends a free WhatsApp update on Airawat every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Airawat have?

According to GharKundli's check of MahaRERA records (updated October 2026), Airawat has one building filed: Airawat with 10 floors and 51 units.

How much parking does Airawat have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 16 covered car parking spaces for Airawat.

How big is the land of Airawat?

According to GharKundli's check of MahaRERA records (updated October 2026), Airawat stands on 1,033 sq m of land (about 0.3 acres), with 4,389 sq m of sanctioned built-up area.

Where can I read reviews of Airawat?

Google Maps has reviews of Airawat written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Airawat?

Airawat by SHUBHASHREEDEVELOPERS is in Sangli Miraj Kupwad (M Corp.), Sangli (pincode 416416), Maharashtra, and is registered on MahaRERA as P53100054007, per GharKundli's check of MahaRERA records.

How many homes are in Airawat?

According to GharKundli's check of MahaRERA records (updated October 2026), Airawat has 25 homes in 1 tower registered on MahaRERA, and 58% of them are sold or booked.

When was Airawat registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Airawat was registered on MahaRERA on 19 December 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Airawat?

No court cases are listed for Airawat on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Airawat?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHUBHASHREEDEVELOPERS, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2027 in Sangli →

Other projects in pincode 416416

All 100 projects in Sangli (416416) →

Other projects by SHUBHASHREEDEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.