Skip to content
GharKundli

IRISH ORISON

by CHAITANYA CONSTRUCTIONS · Shivaji Stadium Corner, SangliAlso near North Shivajinagar, North Shivaji Nagar, Yadiki

Possession date of IRISH ORISON: 30 April 2033. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under PM1290002500893, and currently active. Its completion date is now April 2033, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about IRISH ORISON?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of IRISH ORISON has moved

  1. 31 December 2032

    Completion date given when the project was registered

  2. 30 April 2033

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: IRISH ORISON’s extension records on MahaRERA (PM1290002500893), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on IRISH ORISON

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2033 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PM1290002500893
Status
Registered and active
Builder
CHAITANYA CONSTRUCTIONS
Location
Shivaji Stadium Corner, Sangli · 416416
Project type
Mixed
Registered on
22 Sep 2025
Completion date at registration
December 2032
Latest completion date
April 2033
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
28
Sold or booked
1%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of IRISH ORISON, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
IRISH ORISON0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • IRISH ORISON: covers 14 floors

Latest CC order on MahaRERA: dated 11/07/2026.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on IRISH ORISON every month.

IRISH ORISON: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of IRISH ORISON →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

IRISH ORISON: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about IRISH ORISON

What is the possession date of IRISH ORISON?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for IRISH ORISON in Shivaji Stadium Corner, Sangli is 30 April 2033, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for IRISH ORISON?

Builders and listing sites often quote an earlier "target" date for handover. The completion date IRISH ORISON's builder has filed on MahaRERA, the official one, is 30 April 2033, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of IRISH ORISON?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of IRISH ORISON in Shivaji Stadium Corner, Sangli is PM1290002500893.

Is IRISH ORISON registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), IRISH ORISON is registered as PM1290002500893 and its status is "Registered and active".

What is the construction status of IRISH ORISON?

According to GharKundli's check of MahaRERA records (updated October 2026), IRISH ORISON's status on MahaRERA is "Registered and active". As filed by the builder, slab work on IRISH ORISON is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does IRISH ORISON have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is IRISH ORISON safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), IRISH ORISON is registered on MahaRERA as PM1290002500893, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if IRISH ORISON's possession date changes?

The latest dates are on IRISH ORISON's MahaRERA page (PM1290002500893). GharKundli's Kundli Watch sends a free WhatsApp update on IRISH ORISON every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does IRISH ORISON have?

According to GharKundli's check of MahaRERA records (updated October 2026), IRISH ORISON has one building filed: IRISH ORISON with 14 floors and 113 units.

How much parking does IRISH ORISON have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 60 covered and 1 open car parking spaces for IRISH ORISON.

How big is the land of IRISH ORISON?

According to GharKundli's check of MahaRERA records (updated October 2026), IRISH ORISON stands on 2,294 sq m of land (about 0.6 acres), with 9,929 sq m of sanctioned built-up area.

Where can I read reviews of IRISH ORISON?

Google Maps has reviews of IRISH ORISON written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is IRISH ORISON?

IRISH ORISON by CHAITANYA CONSTRUCTIONS is in Shivaji Stadium Corner, Sangli (pincode 416416), near North Shivajinagar, North Shivaji Nagar, Yadiki, Maharashtra, and is registered on MahaRERA as PM1290002500893, per GharKundli's check of MahaRERA records.

How many homes are in IRISH ORISON?

According to GharKundli's check of MahaRERA records (updated October 2026), IRISH ORISON has 28 homes in 1 tower registered on MahaRERA, and 1% of them are sold or booked.

When was IRISH ORISON registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), IRISH ORISON was registered on MahaRERA on 22 September 2025. GharKundli did not find a title report on the land on file there.

Are there court cases on IRISH ORISON?

No court cases are listed for IRISH ORISON on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of IRISH ORISON?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is CHAITANYA CONSTRUCTIONS, which has 1 other project registered on MahaRERA.

Other projects in Miraj

All 149 projects in Sangli (416416) →

Other projects by CHAITANYA CONSTRUCTIONS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.