Integrated IRS II
by Integrated Spaces Limited · Panvel, Raigarh
Registered on MahaRERA under P52000005863. Status: Completed. Its completion date has moved from March 2019 to September 2023, 54 months later.
Source: GharKundli’s check of MahaRERA records, November 2026.
GharKundli’s full report on Integrated IRS II
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000005863
- Status
- Completed
- Builder
- Integrated Spaces Limited
- Location
- Panvel, Raigarh · 410206
- Project type
- Residential / Group Housing
- Registered on
- 14 Aug 2017
- Completion date at registration
- March 2019
- Latest completion date
- September 2023
- Delay so far
- 54 months
- Homes
- 36
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Kundli Watch
Integrated IRS II: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about Integrated IRS II
Is Integrated IRS II registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Integrated IRS II is registered as P52000005863 and its status is "Completed".
Where is Integrated IRS II?
Integrated IRS II by Integrated Spaces Limited is in Panvel, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000005863, per GharKundli's check of MahaRERA records.
When is possession of Integrated IRS II due?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Integrated IRS II in Panvel, Raigarh is 30 September 2023 — 54 months later than 31 March 2019, the date given at registration.
Does Integrated IRS II have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
How many homes are in Integrated IRS II?
According to GharKundli's check of MahaRERA records (updated November 2026), Integrated IRS II has 36 homes in 1 tower registered on MahaRERA.
When was Integrated IRS II registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Integrated IRS II was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Integrated IRS II?
1 court case is listed for Integrated IRS II on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Integrated IRS II?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Integrated Spaces Limited, which has 5 other projects registered on MahaRERA.
Other projects in pincode 410206
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.