APEX LOVE
by APEX GROUP · Kharghar, Raigarh
Registered on MahaRERA under P52000010576. Status: Completed. Its completion date has moved from June 2019 to December 2020, 18 months later.
Source: GharKundli’s check of MahaRERA records, November 2026.
GharKundli’s full report on APEX LOVE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000010576
- Status
- Completed
- Builder
- APEX GROUP
- Location
- Kharghar, Raigarh · 410206
- Project type
- Residential / Group Housing
- Registered on
- 31 Aug 2017
- Completion date at registration
- June 2019
- Latest completion date
- December 2020
- Delay so far
- 18 months
- Homes
- 31
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Kundli Watch
APEX LOVE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about APEX LOVE
Is APEX LOVE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), APEX LOVE is registered as P52000010576 and its status is "Completed".
Where is APEX LOVE?
APEX LOVE by APEX GROUP is in Kharghar, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000010576, per GharKundli's check of MahaRERA records.
When is possession of APEX LOVE due?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for APEX LOVE in Kharghar, Raigarh is 29 December 2020 — 18 months later than 30 June 2019, the date given at registration.
Does APEX LOVE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
How many homes are in APEX LOVE?
According to GharKundli's check of MahaRERA records (updated November 2026), APEX LOVE has 31 homes in 1 tower registered on MahaRERA.
When was APEX LOVE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), APEX LOVE was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on APEX LOVE?
No court cases are listed for APEX LOVE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of APEX LOVE?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is APEX GROUP, which has 2 other projects registered on MahaRERA.
Other projects in pincode 410206
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.