Shiv Srushti Park Complex - Phase II

by Jai Parmamaa Developers · Karjat, Raigarh

Registered on MahaRERA under P52000016272, and currently active. Its completion date has moved from December 2023 to December 2030, 84 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on Shiv Srushti Park Complex - Phase II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000016272
Status
Registered and active
Builder
Jai Parmamaa Developers
Location
Karjat, Raigarh · 410101
Project type
Residential / Group Housing
Registered on
2 May 2018
Completion date at registration
December 2023
Latest completion date
December 2030
Delay so far
84 months
Homes
222
Sold or booked
31%
Towers
19
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Kundli Watch

Shiv Srushti Park Complex - Phase II: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about Shiv Srushti Park Complex - Phase II

Is Shiv Srushti Park Complex - Phase II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shiv Srushti Park Complex - Phase II is registered as P52000016272 and its status is "Registered and active".

Where is Shiv Srushti Park Complex - Phase II?

Shiv Srushti Park Complex - Phase II by Jai Parmamaa Developers is in Karjat, Raigarh (pincode 410101), Maharashtra, and is registered on MahaRERA as P52000016272, per GharKundli's check of MahaRERA records.

When is possession of Shiv Srushti Park Complex - Phase II due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shiv Srushti Park Complex - Phase II in Karjat, Raigarh is 31 December 2030 — 84 months later than 1 December 2023, the date given at registration.

Does Shiv Srushti Park Complex - Phase II have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of Shiv Srushti Park Complex - Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Jai Parmamaa Developers.

Other projects in pincode 410101

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.