VANSH HEIGHTS
by NAVKAR DEVELOPERS · Ganganagar, Raigarh
Possession date of VANSH HEIGHTS: 31 July 2028, moved from 9 January 2026 (26 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000049810, and currently active. Its completion date has moved from January 2026 to July 2028: 26 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about VANSH HEIGHTS?
How the possession date of VANSH HEIGHTS has moved
9 January 2026
Completion date given when the project was registered
31 March 2028
Extended at the builder's request (MahaRERA application EA16072621777)
Reason the builder gave MahaRERA:
“Dear Sir, I, Mr. Piyush P. Oswal (Partner), hereby request you to grant extension of completion date for project " VANSH HEIGHTS ". situated at Plot Bearing 380/3 380/4 at Neral, Karjat, Raigarh, 410101, registered with "The Maharashtra Rea…” Read the full reason
“Dear Sir, I, Mr. Piyush P. Oswal (Partner), hereby request you to grant extension of completion date for project " VANSH HEIGHTS ". situated at Plot Bearing 380/3 380/4 at Neral, Karjat, Raigarh, 410101, registered with "The Maharashtra Real Estate Regulatory Authority" vide project registration certificate bearing no. "P52000049810" for a further period of 27 months from 10th January 2026 to 31st March 2028. I respectfully submit that the extension for a period of 27 months is necessitated due to a combination of regulatory, financial and market factors that affected our ability to continu…”31 July 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: VANSH HEIGHTS’s extension records on MahaRERA (P52000049810), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on VANSH HEIGHTS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000049810
- Status
- Registered and active
- Builder
- NAVKAR DEVELOPERS
- Location
- Ganganagar, Raigarh · 410101
- Project type
- Residential / Group Housing
- Registered on
- 24 Feb 2023
- Completion date at registration
- January 2026
- Latest completion date
- July 2028
- Delay so far
- 26 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 45
- Sold or booked
- 18%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 10
Construction progress of VANSH HEIGHTS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| VANSH HEIGHTS | 100% | 100% | 95% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- VANSH HEIGHTS: covers 7 floors
Latest CC order on MahaRERA: dated 18/08/2021.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on VANSH HEIGHTS every month.
VANSH HEIGHTS: buildings, flats and land, as filed on MahaRERA
- Buildings: VANSH HEIGHTS (7 floors, 51 units)
- Car parking: 8 covered
- Land: 993 sq m (about 0.2 acres) · sanctioned built-up 2,233 sq m
- Boundaries filed include: CENTRAL RAILWAY LINE
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of VANSH HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
VANSH HEIGHTS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about VANSH HEIGHTS
What is the possession date of VANSH HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VANSH HEIGHTS in Ganganagar, Raigarh is 31 July 2028 — 26 months later than 9 January 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for VANSH HEIGHTS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date VANSH HEIGHTS's builder has filed on MahaRERA, the official one, is 31 July 2028, already 26 months later than the 9 January 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of VANSH HEIGHTS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), VANSH HEIGHTS's builder applied to MahaRERA to extend the completion date once: to 31 March 2028, giving the reason "Dear Sir, I, Mr. Piyush P. Oswal (Partner), hereby request you to grant extension of completion date for project " VANSH HEIGHTS ". situated at Plot Bearing 380/3 380/4 at Neral, Karjat, Raigarh, 410101, registered with "The Maharashtra Real Estate Regulatory Authority" vide project registration certificate bearing no. "P52000049810" for a further period of 27 months from 10th January 2026 to 31st March 2028. I respectfully submit that the extension for a period of 27 months is necessitated due to a combination of regulatory, financial and market factors that affected our ability to continu…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of VANSH HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VANSH HEIGHTS in Ganganagar, Raigarh is P52000049810.
Is VANSH HEIGHTS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VANSH HEIGHTS is registered as P52000049810 and its status is "Registered and active".
What is the construction status of VANSH HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), VANSH HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on VANSH HEIGHTS is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does VANSH HEIGHTS have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is VANSH HEIGHTS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), VANSH HEIGHTS is registered on MahaRERA as P52000049810, its completion date has moved 26 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if VANSH HEIGHTS's possession date changes?
The latest dates are on VANSH HEIGHTS's MahaRERA page (P52000049810). GharKundli's Kundli Watch sends a free WhatsApp update on VANSH HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does VANSH HEIGHTS have?
According to GharKundli's check of MahaRERA records (updated October 2026), VANSH HEIGHTS has one building filed: VANSH HEIGHTS with 7 floors and 51 units.
How much parking does VANSH HEIGHTS have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 8 covered car parking spaces for VANSH HEIGHTS.
How big is the land of VANSH HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), VANSH HEIGHTS stands on 993 sq m of land (about 0.2 acres), with 2,233 sq m of sanctioned built-up area.
Where can I read reviews of VANSH HEIGHTS?
Google Maps has reviews of VANSH HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is VANSH HEIGHTS?
VANSH HEIGHTS by NAVKAR DEVELOPERS is in Ganganagar, Raigarh (pincode 410101), Maharashtra, and is registered on MahaRERA as P52000049810, per GharKundli's check of MahaRERA records. Its boundaries filed there include CENTRAL RAILWAY LINE.
How many homes are in VANSH HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), VANSH HEIGHTS has 45 homes in 1 tower registered on MahaRERA, and 18% of them are sold or booked.
When was VANSH HEIGHTS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VANSH HEIGHTS was registered on MahaRERA on 24 February 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on VANSH HEIGHTS?
No court cases are listed for VANSH HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of VANSH HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NAVKAR DEVELOPERS, which has 10 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of VANSH HEIGHTS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Raigad →
Other projects in Karjat
- SWAMI AASHRAY
- Ratnamisha Villas
- 21 ENCLAVE
- Krishna Valley Phase I
- MUDRA AVENUE
- Hill Top Residency
- Gajvakra Heights
- MIRA RESIDENCY
Other projects by NAVKAR DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.