Gajvakra Heights

by Gajvakra Realty Private Limited · Mauje Mudre Budruk ,Karjat, Raigarh

Possession date of Gajvakra Heights: 30 April 2027, moved from 31 December 2024 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000034563, and currently active. Its completion date has moved from December 2024 to April 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Gajvakra Heights?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Gajvakra Heights has moved

  1. 31 December 2024

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT52000027167)

    Reason the builder gave MahaRERA:
    “We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these…” Read the full reason“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 31-12-2026 to complete the project and fulfil all regulatory requirements.”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Gajvakra Heights’s extension records on MahaRERA (P52000034563), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Gajvakra Heights

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000034563
Status
Registered and active
Builder
Gajvakra Realty Private Limited
Location
Mauje Mudre Budruk ,Karjat, Raigarh · 410201
Project type
Others
Registered on
11 Apr 2022
Completion date at registration
December 2024
Latest completion date
April 2027
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
68
Sold or booked
30%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Gajvakra Heights, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Gajvakra Heights100%100%90%25%

Commencement certificate (CC), as filed on MahaRERA

  • Gajvakra Heights: covers 9 (Ground + 8 Upper Floors)

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Gajvakra Heights every month.

Gajvakra Heights: buildings, flats and land, as filed on MahaRERA

  • Buildings: Gajvakra Heights (10 floors, 84 units)
  • Land: 2,150 sq m (about 0.5 acres) · sanctioned built-up 5,539 sq m

The builder’s record and reviews

Gajvakra Realty has 3 projects on MahaRERA since 2021, this one included. Of the 3 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 12 months); 1 still being built, 1 past the promised date (typically 18 months late). No complaints on MahaRERA.

Read Google reviews of Gajvakra Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Gajvakra Heights: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Gajvakra Heights

What is the possession date of Gajvakra Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Gajvakra Heights in Mauje Mudre Budruk ,Karjat, Raigarh is 30 April 2027 — 24 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Gajvakra Heights?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Gajvakra Heights's builder has filed on MahaRERA, the official one, is 30 April 2027, already 24 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Gajvakra Heights extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Gajvakra Heights's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 31-12-2026 to complete the project and fulfil all regulatory requirements.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Gajvakra Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Gajvakra Heights in Mauje Mudre Budruk ,Karjat, Raigarh is P52000034563.

Is Gajvakra Heights registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Gajvakra Heights is registered as P52000034563 and its status is "Registered and active".

What is the construction status of Gajvakra Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Gajvakra Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Gajvakra Heights is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does Gajvakra Heights have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Gajvakra Heights safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Gajvakra Heights is registered on MahaRERA as P52000034563, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Gajvakra Heights's possession date changes?

The latest dates are on Gajvakra Heights's MahaRERA page (P52000034563). GharKundli's Kundli Watch sends a free WhatsApp update on Gajvakra Heights every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Gajvakra Heights have?

According to GharKundli's check of MahaRERA records (updated October 2026), Gajvakra Heights has one building filed: Gajvakra Heights with 10 floors and 84 units.

How big is the land of Gajvakra Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Gajvakra Heights stands on 2,150 sq m of land (about 0.5 acres), with 5,539 sq m of sanctioned built-up area.

What is the track record of Gajvakra Heights's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Gajvakra Realty has 3 projects on MahaRERA since 2021, this one included. Of the 3 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 12 months); 1 still being built, 1 past the promised date (typically 18 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Gajvakra Heights?

Google Maps has reviews of Gajvakra Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Gajvakra Heights?

Gajvakra Heights by Gajvakra Realty Private Limited is in Mauje Mudre Budruk ,Karjat, Raigarh (pincode 410201), Maharashtra, and is registered on MahaRERA as P52000034563, per GharKundli's check of MahaRERA records.

How many homes are in Gajvakra Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Gajvakra Heights has 68 homes in 1 tower registered on MahaRERA, and 30% of them are sold or booked.

When was Gajvakra Heights registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Gajvakra Heights was registered on MahaRERA on 11 April 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on Gajvakra Heights?

No court cases are listed for Gajvakra Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Gajvakra Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Gajvakra Realty Private Limited, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2027 in Raigad →

Other projects in Karjat

All 311 projects in Karjat (410201) →

Other projects by Gajvakra Realty Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.