MIRA RESIDENCY

by MIRA DEVELOPERS · Mamdapur, Raigarh

Possession: MIRA RESIDENCY is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000080229. Status: Completed. Its completion date is now September 2026, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about MIRA RESIDENCY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of MIRA RESIDENCY has moved

  1. 29 May 2026

    Completion date given when the project was registered

  2. 29 September 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: MIRA RESIDENCY’s extension records on MahaRERA (P52000080229), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MIRA RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000080229
Status
Completed
Builder
MIRA DEVELOPERS
Location
Mamdapur, Raigarh · 410101
Project type
Others
Registered on
9 May 2025
Completion date at registration
May 2026
Latest completion date
September 2026
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
29
Sold or booked
63%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of MIRA RESIDENCY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MIRA RESIDENCY100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • MIRA RESIDENCY: covers Ground + 8 Floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MIRA RESIDENCY every month.

MIRA RESIDENCY: buildings, flats and land, as filed on MahaRERA

  • Buildings: MIRA RESIDENCY (9 floors, 32 units)
  • Car parking: 6 covered, 3 open
  • Land: 507 sq m (about 0.1 acres) · sanctioned built-up 1,136 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of MIRA RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MIRA RESIDENCY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MIRA RESIDENCY

What is the possession date of MIRA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MIRA RESIDENCY in Mamdapur, Raigarh is 29 September 2026, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for MIRA RESIDENCY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MIRA RESIDENCY's builder has filed on MahaRERA, the official one, is 29 September 2026, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of MIRA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MIRA RESIDENCY in Mamdapur, Raigarh is P52000080229.

Is MIRA RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MIRA RESIDENCY is registered as P52000080229 and its status is "Completed".

What is the construction status of MIRA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), MIRA RESIDENCY's status on MahaRERA is "Completed". As filed by the builder, slab work on MIRA RESIDENCY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does MIRA RESIDENCY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is MIRA RESIDENCY safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), MIRA RESIDENCY is registered on MahaRERA as P52000080229, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if MIRA RESIDENCY's possession date changes?

The latest dates are on MIRA RESIDENCY's MahaRERA page (P52000080229). GharKundli's Kundli Watch sends a free WhatsApp update on MIRA RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MIRA RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated October 2026), MIRA RESIDENCY has one building filed: MIRA RESIDENCY with 9 floors and 32 units.

How much parking does MIRA RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 6 covered and 3 open car parking spaces for MIRA RESIDENCY.

How big is the land of MIRA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), MIRA RESIDENCY stands on 507 sq m of land (about 0.1 acres), with 1,136 sq m of sanctioned built-up area.

Where can I read reviews of MIRA RESIDENCY?

Google Maps has reviews of MIRA RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MIRA RESIDENCY?

MIRA RESIDENCY by MIRA DEVELOPERS is in Mamdapur, Raigarh (pincode 410101), Maharashtra, and is registered on MahaRERA as P52000080229, per GharKundli's check of MahaRERA records.

How many homes are in MIRA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), MIRA RESIDENCY has 29 homes in 1 tower registered on MahaRERA, and 63% of them are sold or booked.

When was MIRA RESIDENCY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MIRA RESIDENCY was registered on MahaRERA on 9 May 2025. GharKundli did not find a title report on the land on file there.

Are there court cases on MIRA RESIDENCY?

No court cases are listed for MIRA RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of MIRA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MIRA DEVELOPERS.

Other projects in Mamdapur

All 362 projects in Neral (410101) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.