21 ENCLAVE
by Pushpam Infra LLP · Kashele, Raigarh
Possession date of 21 ENCLAVE: 30 October 2027, moved from 31 December 2025 (18 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000045327, and currently active. Its completion date has moved from December 2025 to October 2027: 18 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about 21 ENCLAVE?
How the possession date of 21 ENCLAVE has moved
31 December 2025
Completion date given when the project was registered
30 June 2026
Extended at the builder's request (MahaRERA application EXT52000028405)
Reason the builder gave MahaRERA: “Plan revised”
30 June 2027
Extended at the builder's request (MahaRERA application EA10062621300)
Reason the builder gave MahaRERA: “Shortage of labour”
30 October 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: 21 ENCLAVE’s extension records on MahaRERA (P52000045327), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on 21 ENCLAVE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- 21 EnclaveP52000035127 · possession 31 May 2024
- MahaRERA registration
- P52000045327
- Status
- Registered and active
- Builder
- Pushpam Infra LLP
- Location
- Kashele, Raigarh · 410201
- Project type
- Residential / Group Housing
- Registered on
- 12 May 2022
- Completion date at registration
- December 2025
- Latest completion date
- October 2027
- Delay so far
- 18 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 21
- Sold or booked
- 24%
- Towers
- 4
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 9
Construction progress of 21 ENCLAVE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| E | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- E: covers 2 floors
- B: covers 2 floors
- C: covers 2 floors
- D: covers 2 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on 21 ENCLAVE every month.
21 ENCLAVE: buildings, flats and land, as filed on MahaRERA
- Buildings: E (2 floors, 3 units) · B (2 floors, 8 units) · C (2 floors, 3 units) · D (2 floors, 7 units)
- Land: 4,804 sq m (about 1.2 acres) · sanctioned built-up 2,871 sq m
- Boundaries filed include: Karjat Murbad Road
The builder’s record and reviews
Pushpam Infra (a group of 4 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 40 months); 7 still being built, 4 past the promised date (typically 14 months late); 1 lapsed. 2 complaints on MahaRERA across 2 projects.
Read Google reviews of 21 ENCLAVE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
21 ENCLAVE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about 21 ENCLAVE
What is the possession date of 21 ENCLAVE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for 21 ENCLAVE in Kashele, Raigarh is 30 October 2027 — 18 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for 21 ENCLAVE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date 21 ENCLAVE's builder has filed on MahaRERA, the official one, is 30 October 2027, already 18 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of 21 ENCLAVE extended?
According to GharKundli's check of MahaRERA records (updated October 2026), 21 ENCLAVE's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2026, giving the reason "Plan revised"; to 30 June 2027, giving the reason "Shortage of labour". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of 21 ENCLAVE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of 21 ENCLAVE in Kashele, Raigarh is P52000045327.
Is 21 ENCLAVE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), 21 ENCLAVE is registered as P52000045327 and its status is "Registered and active".
What is the construction status of 21 ENCLAVE?
According to GharKundli's check of MahaRERA records (updated October 2026), 21 ENCLAVE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on E is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does 21 ENCLAVE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is 21 ENCLAVE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), 21 ENCLAVE is registered on MahaRERA as P52000045327, its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does 21 ENCLAVE have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: 21 Enclave (P52000035127, possession 31 May 2024). Check that your agreement names the registration of your own wing.
How can I get updates if 21 ENCLAVE's possession date changes?
The latest dates are on 21 ENCLAVE's MahaRERA page (P52000045327). GharKundli's Kundli Watch sends a free WhatsApp update on 21 ENCLAVE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does 21 ENCLAVE have?
According to GharKundli's check of MahaRERA records (updated October 2026), 21 ENCLAVE has 4 buildings filed: E with 2 floors and 3 units; B with 2 floors and 8 units; C with 2 floors and 3 units; D with 2 floors and 7 units.
How big is the land of 21 ENCLAVE?
According to GharKundli's check of MahaRERA records (updated October 2026), 21 ENCLAVE stands on 4,804 sq m of land (about 1.2 acres), with 2,871 sq m of sanctioned built-up area.
What is the track record of 21 ENCLAVE's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Pushpam Infra (a group of 4 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 40 months); 7 still being built, 4 past the promised date (typically 14 months late); 1 lapsed. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of 21 ENCLAVE?
Google Maps has reviews of 21 ENCLAVE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is 21 ENCLAVE?
21 ENCLAVE by Pushpam Infra LLP is in Kashele, Raigarh (pincode 410201), Maharashtra, and is registered on MahaRERA as P52000045327, per GharKundli's check of MahaRERA records. Its boundaries filed there include Karjat Murbad Road.
How many homes are in 21 ENCLAVE?
According to GharKundli's check of MahaRERA records (updated October 2026), 21 ENCLAVE has 21 homes in 4 towers registered on MahaRERA, and 24% of them are sold or booked.
When was 21 ENCLAVE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), 21 ENCLAVE was registered on MahaRERA on 12 May 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on 21 ENCLAVE?
No court cases are listed for 21 ENCLAVE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of 21 ENCLAVE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Pushpam Infra LLP, which has 9 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of 21 ENCLAVE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Raigad →
Other projects in pincode 410201
- HOLIDAY MAIYAAN KARJAT
- RIVA RYTHM -I, J,K,L WING
- SARTH APARTMENT BUILDING NO 2 PHASE I
- Krishna Valley Phase I
- Gajvakra Heights
- MUDRA AVENUE
- Hill Top Residency
- Ratnamisha Villas
Other projects by Pushpam Infra LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.