SARTH APARTMENT BUILDING NO 2 PHASE I
by YADNESHWAR SHANTARAM PATIL · Karjat, Raigarh
Possession date of SARTH APARTMENT BUILDING NO 2 PHASE I: 31 December 2028, moved from 31 December 2018 (120 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000015029, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SARTH APARTMENT BUILDING NO 2 PHASE I?
How the possession date of SARTH APARTMENT BUILDING NO 2 PHASE I has moved
31 December 2018
Completion date given when the project was registered
30 December 2022
Extended at the builder's request (MahaRERA application EXT52000000836)
Reason the builder gave MahaRERA: “Due to the market issue the booking of the properties no done as we expected. Therefore we don't have enough fund to complete the project as we mentioned at the time of registration.”
30 December 2022
Extended at the builder's request (MahaRERA application EXT52000005231)
Reason the builder gave MahaRERA: “Major inventory is Unsold.”
31 December 2025
Extended at the builder's request (MahaRERA application EXT52000018029)
Reason the builder gave MahaRERA:
“Project was delayed because of slow market transaction and consumer expectation about their home/house/flat, also there is competition in market about construction works. Also, there is problem occurring in finance and labour availability.…” Read the full reason
“Project was delayed because of slow market transaction and consumer expectation about their home/house/flat, also there is competition in market about construction works. Also, there is problem occurring in finance and labour availability. Total No. of Flats - 91 Total No. of Flats Sold - 29”31 December 2028
Extended at the builder's request (MahaRERA application EA18122518754)
Reason the builder gave MahaRERA:
“• Financial and Material/Labour Shortages: Ongoing challenges with rising material costs and a shortage of skilled labour have made it difficult to meet the original construction deadlines. These supply chain issues, which are beyond our co…” Read the full reason
“• Financial and Material/Labour Shortages: Ongoing challenges with rising material costs and a shortage of skilled labour have made it difficult to meet the original construction deadlines. These supply chain issues, which are beyond our control, have significantly affected the project’s progress. • Weather-Related Delays: Unseasonal rains and adverse weather conditions during the past year further contributed to delays, particularly in outdoor construction activities, including foundation work, external façade construction, and road access improvements. • Ensuring Completion of All Constru…”
Source: SARTH APARTMENT BUILDING NO 2 PHASE I’s extension records on MahaRERA (P52000015029), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SARTH APARTMENT BUILDING NO 2 PHASE I
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000015029
- Status
- Registered and active
- Builder
- YADNESHWAR SHANTARAM PATIL
- Location
- Karjat, Raigarh · 410201
- Project type
- Residential / Group Housing
- Registered on
- 22 Jan 2018
- Completion date at registration
- December 2018
- Latest completion date
- December 2028
- Delay so far
- 120 months
- Homes
- 91
- Sold or booked
- 49%
- Towers
- 4
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SARTH APARTMENT BUILDING NO 2 PHASE I, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A WING | 100% | 100% | 100% | 60% |
| B WING | 100% | 100% | 80% | 60% |
| C WING | 100% | 100% | 80% | 60% |
| D WING | 100% | 100% | 80% | 60% |
Commencement certificate (CC), as filed on MahaRERA
- A WING: covers 4 floors
- B WING: covers 4 floors
- C WING: covers 4 floors
- D WING: covers 4 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SARTH APARTMENT BUILDING NO 2 PHASE I every month.
SARTH APARTMENT BUILDING NO 2 PHASE I: buildings, flats and land, as filed on MahaRERA
- Buildings: A WING (8 floors, 18 units) · B WING (9 floors, 28 units) · C WING (8 floors, 28 units) · D WING (8 floors, 17 units)
- Car parking: 8 covered, 40 open
- Land: 2,665 sq m (about 0.7 acres) · sanctioned built-up 2,666 sq m · recreational space 10,470 sq m
- Boundaries filed include: GRAMMAPANCHAYAT ROAD
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SARTH APARTMENT BUILDING NO 2 PHASE I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SARTH APARTMENT BUILDING NO 2 PHASE I: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SARTH APARTMENT BUILDING NO 2 PHASE I
What is the possession date of SARTH APARTMENT BUILDING NO 2 PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SARTH APARTMENT BUILDING NO 2 PHASE I in Karjat, Raigarh is 31 December 2028 — 120 months later than 31 December 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SARTH APARTMENT BUILDING NO 2 PHASE I?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SARTH APARTMENT BUILDING NO 2 PHASE I's builder has filed on MahaRERA, the official one, is 31 December 2028, already 120 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SARTH APARTMENT BUILDING NO 2 PHASE I extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SARTH APARTMENT BUILDING NO 2 PHASE I's builder applied to MahaRERA to extend the completion date 4 times: to 30 December 2022, giving the reason "Due to the market issue the booking of the properties no done as we expected. Therefore we don't have enough fund to complete the project as we mentioned at the time of registration."; to 30 December 2022, giving the reason "Major inventory is Unsold."; to 31 December 2025, giving the reason "Project was delayed because of slow market transaction and consumer expectation about their home/house/flat, also there is competition in market about construction works. Also, there is problem occurring in finance and labour availability. Total No. of Flats - 91 Total No. of Flats Sold - 29"; to 31 December 2028, giving the reason "• Financial and Material/Labour Shortages: Ongoing challenges with rising material costs and a shortage of skilled labour have made it difficult to meet the original construction deadlines. These supply chain issues, which are beyond our control, have significantly affected the project’s progress. • Weather-Related Delays: Unseasonal rains and adverse weather conditions during the past year further contributed to delays, particularly in outdoor construction activities, including foundation work, external façade construction, and road access improvements. • Ensuring Completion of All Constru…".
What is the RERA number of SARTH APARTMENT BUILDING NO 2 PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SARTH APARTMENT BUILDING NO 2 PHASE I in Karjat, Raigarh is P52000015029.
Is SARTH APARTMENT BUILDING NO 2 PHASE I registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SARTH APARTMENT BUILDING NO 2 PHASE I is registered as P52000015029 and its status is "Registered and active".
What is the construction status of SARTH APARTMENT BUILDING NO 2 PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), SARTH APARTMENT BUILDING NO 2 PHASE I's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does SARTH APARTMENT BUILDING NO 2 PHASE I have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is SARTH APARTMENT BUILDING NO 2 PHASE I safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SARTH APARTMENT BUILDING NO 2 PHASE I is registered on MahaRERA as P52000015029, its completion date has moved 120 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SARTH APARTMENT BUILDING NO 2 PHASE I's possession date changes?
The latest dates are on SARTH APARTMENT BUILDING NO 2 PHASE I's MahaRERA page (P52000015029). GharKundli's Kundli Watch sends a free WhatsApp update on SARTH APARTMENT BUILDING NO 2 PHASE I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SARTH APARTMENT BUILDING NO 2 PHASE I have?
According to GharKundli's check of MahaRERA records (updated October 2026), SARTH APARTMENT BUILDING NO 2 PHASE I has 4 buildings filed: A WING with 8 floors and 18 units; B WING with 9 floors and 28 units; C WING with 8 floors and 28 units; D WING with 8 floors and 17 units.
How much parking does SARTH APARTMENT BUILDING NO 2 PHASE I have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 8 covered and 40 open car parking spaces for SARTH APARTMENT BUILDING NO 2 PHASE I.
How big is the land of SARTH APARTMENT BUILDING NO 2 PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), SARTH APARTMENT BUILDING NO 2 PHASE I stands on 2,665 sq m of land (about 0.7 acres), with 2,666 sq m of sanctioned built-up area and 10,470 sq m of recreational open space.
Where can I read reviews of SARTH APARTMENT BUILDING NO 2 PHASE I?
Google Maps has reviews of SARTH APARTMENT BUILDING NO 2 PHASE I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SARTH APARTMENT BUILDING NO 2 PHASE I?
SARTH APARTMENT BUILDING NO 2 PHASE I by YADNESHWAR SHANTARAM PATIL is in Karjat, Raigarh (pincode 410201), Maharashtra, and is registered on MahaRERA as P52000015029, per GharKundli's check of MahaRERA records. Its boundaries filed there include GRAMMAPANCHAYAT ROAD.
How many homes are in SARTH APARTMENT BUILDING NO 2 PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), SARTH APARTMENT BUILDING NO 2 PHASE I has 91 homes in 4 towers registered on MahaRERA, and 49% of them are sold or booked.
When was SARTH APARTMENT BUILDING NO 2 PHASE I registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SARTH APARTMENT BUILDING NO 2 PHASE I was registered on MahaRERA on 22 January 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on SARTH APARTMENT BUILDING NO 2 PHASE I?
No court cases are listed for SARTH APARTMENT BUILDING NO 2 PHASE I on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SARTH APARTMENT BUILDING NO 2 PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is YADNESHWAR SHANTARAM PATIL.
Check it yourself on MahaRERA
- How to check the possession date of SARTH APARTMENT BUILDING NO 2 PHASE I
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Raigad →
Other projects in pincode 410201
- HOLIDAY MAIYAAN KARJAT
- RIVA RYTHM -I, J,K,L WING
- Krishna Valley Phase I
- Gajvakra Heights
- 21 ENCLAVE
- MUDRA AVENUE
- Hill Top Residency
- Ratnamisha Villas
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.