Krishna Valley Phase I

by NANDKISHORE LIFESPACES PVT LTD · Sirsai Mandir, Raigarh

Possession date of Krishna Valley Phase I: 15 December 2026, moved from 31 December 2023 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000030001, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Krishna Valley Phase I?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Krishna Valley Phase I has moved

  1. 31 December 2023

    Completion date given when the project was registered

  2. 30 December 2024

    Extended at the builder's request (MahaRERA application EXT52000018069)

    Reason the builder gave MahaRERA: “DUE TO COVID 19 NOT ABLE TO COMPLETE PROJECT PLEASE GRNAT US EXTENSION TILL 30/12/2024”
  3. 30 August 2025

    Extended at the builder's request (MahaRERA application EXT52000025883)

    Reason the builder gave MahaRERA:
    “With reference to the above mentioned subject our project KRISHNA VALLEY is located at Plot No 16/6 Village Shine Taluka Karjat, Dist Raigad the said project was scheduled to be completed on 30.12.2024 However due to unseen and unavoidable…” Read the full reason“With reference to the above mentioned subject our project KRISHNA VALLEY is located at Plot No 16/6 Village Shine Taluka Karjat, Dist Raigad the said project was scheduled to be completed on 30.12.2024 However due to unseen and unavoidable circumstances we have till date been able to complete 90% of the Project and just a few items in finishing is pending along with lift and MSEB connection pending which will soon be done after which we would apply for OC and hand over the possession to the buyers. Sor the entire process may not take more than 3 mouthis but taking into consideration and mar…”
  4. 15 December 2026

    Extended at the builder's request (MahaRERA application EA20082622255)

    Reason the builder gave MahaRERA: “OC Recived”

Source: Krishna Valley Phase I’s extension records on MahaRERA (P52000030001), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Krishna Valley Phase I

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000030001
Status
Registered and active
Builder
NANDKISHORE LIFESPACES PVT LTD
Location
Sirsai Mandir, Raigarh · 410201
Project type
Residential / Group Housing
Registered on
20 Jul 2021
Completion date at registration
December 2023
Latest completion date
December 2026
Delay so far
36 months
Homes
114
Sold or booked
49%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Krishna Valley Phase I, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
01100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • 01: covers plinth/ with FSI) / 7 Habitable / Floors.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Krishna Valley Phase I every month.

Krishna Valley Phase I: buildings, flats and land, as filed on MahaRERA

  • Buildings: 01 (9 floors, 114 units)
  • Land: 2,160 sq m (about 0.5 acres) · sanctioned built-up 4,577 sq m · recreational space 216 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Krishna Valley Phase I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Krishna Valley Phase I: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Krishna Valley Phase I

What is the possession date of Krishna Valley Phase I?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Krishna Valley Phase I in Sirsai Mandir, Raigarh is 15 December 2026 — 36 months later than 31 December 2023, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Krishna Valley Phase I?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Krishna Valley Phase I's builder has filed on MahaRERA, the official one, is 15 December 2026, already 36 months later than the 31 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Krishna Valley Phase I extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Valley Phase I's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2024, giving the reason "DUE TO COVID 19 NOT ABLE TO COMPLETE PROJECT PLEASE GRNAT US EXTENSION TILL 30/12/2024"; to 30 August 2025, giving the reason "With reference to the above mentioned subject our project KRISHNA VALLEY is located at Plot No 16/6 Village Shine Taluka Karjat, Dist Raigad the said project was scheduled to be completed on 30.12.2024 However due to unseen and unavoidable circumstances we have till date been able to complete 90% of the Project and just a few items in finishing is pending along with lift and MSEB connection pending which will soon be done after which we would apply for OC and hand over the possession to the buyers. Sor the entire process may not take more than 3 mouthis but taking into consideration and mar…"; to 15 December 2026, giving the reason "OC Recived".

What is the RERA number of Krishna Valley Phase I?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Krishna Valley Phase I in Sirsai Mandir, Raigarh is P52000030001.

Is Krishna Valley Phase I registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Valley Phase I is registered as P52000030001 and its status is "Registered and active".

What is the construction status of Krishna Valley Phase I?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Valley Phase I's status on MahaRERA is "Registered and active". As filed by the builder, slab work on 01 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Krishna Valley Phase I have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Krishna Valley Phase I safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Valley Phase I is registered on MahaRERA as P52000030001, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Krishna Valley Phase I's possession date changes?

The latest dates are on Krishna Valley Phase I's MahaRERA page (P52000030001). GharKundli's Kundli Watch sends a free WhatsApp update on Krishna Valley Phase I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Krishna Valley Phase I have?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Valley Phase I has one building filed: 01 with 9 floors and 114 units.

How big is the land of Krishna Valley Phase I?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Valley Phase I stands on 2,160 sq m of land (about 0.5 acres), with 4,577 sq m of sanctioned built-up area and 216 sq m of recreational open space.

Where can I read reviews of Krishna Valley Phase I?

Google Maps has reviews of Krishna Valley Phase I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Krishna Valley Phase I?

Krishna Valley Phase I by NANDKISHORE LIFESPACES PVT LTD is in Sirsai Mandir, Raigarh (pincode 410201), Maharashtra, and is registered on MahaRERA as P52000030001, per GharKundli's check of MahaRERA records.

How many homes are in Krishna Valley Phase I?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Valley Phase I has 114 homes in 1 tower registered on MahaRERA, and 49% of them are sold or booked.

When was Krishna Valley Phase I registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Valley Phase I was registered on MahaRERA on 20 July 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on Krishna Valley Phase I?

No court cases are listed for Krishna Valley Phase I on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Krishna Valley Phase I?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NANDKISHORE LIFESPACES PVT LTD.

All projects with possession due in 2026 in Raigad →

Other projects in Karjat

All 311 projects in Karjat (410201) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.