HOLIDAY MAIYAAN KARJAT

by B QUBES · Chaudhar Wadi, Raigarh

Possession date of HOLIDAY MAIYAAN KARJAT: 30 April 2029, moved from 30 April 2019 (116 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000000477, and currently active. Its completion date has moved from April 2019 to April 2029: 116 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about HOLIDAY MAIYAAN KARJAT?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of HOLIDAY MAIYAAN KARJAT has moved

  1. 30 April 2019

    Completion date given when the project was registered

  2. 29 April 2020

    Extended at the builder's request (MahaRERA application EXT52000001913)

    Reason the builder gave MahaRERA:
    “To The Hon. Chairman, Maharashtra Real Estate Regulatory Authority, Mumbai Subject : Request for Project Extension for Holiday Maiyaan Karjat, MahaRERA Registration No. P52000000477) situated at Sr. No. 185/1 to 185/6, Vil Dhamani, Tal Karj…” Read the full reason“To The Hon. Chairman, Maharashtra Real Estate Regulatory Authority, Mumbai Subject : Request for Project Extension for Holiday Maiyaan Karjat, MahaRERA Registration No. P52000000477) situated at Sr. No. 185/1 to 185/6, Vil Dhamani, Tal Karjat, Dist. Raigarh Respected Hon. Chairman, MahaRERA, This is in reference to our above mentioned project Holiday Maiyaan Karjat (phase 1) which is registered with the MAHARERA authority under the number: P52000000477 We would like to state that the construction on site is almost 85% completed including RCC superstructure and major finishing works like pai…”
  3. 30 April 2026

    Extended at the builder's request (MahaRERA application EXT52000017024)

    Reason the builder gave MahaRERA:
    “To, The Hon. Chairman, Maharashtra Real Estate Regulatory Authority, Mumbai Subject: Request for project extension for Holiday Maiyaan Karjat Phase 2, MahaRERA Registration NO. P52000000477, Situated at Sr. No. 185/1 to 185/6, Vil. Dhamni,…” Read the full reason“To, The Hon. Chairman, Maharashtra Real Estate Regulatory Authority, Mumbai Subject: Request for project extension for Holiday Maiyaan Karjat Phase 2, MahaRERA Registration NO. P52000000477, Situated at Sr. No. 185/1 to 185/6, Vil. Dhamni, Taluka Karjat, Dist Raigarh Respected Honourable Chairman, MahaRERA, This is in reference to our above mentioned project Holiday Maiyaan Karjat which is registered with the MahaRERA authority under the number: P52000000477 By an email received from MahaRERA authority on 11/04/23, and further our reply on 12th May 2023, We were informed and further instruc…”
  4. 31 December 2028

    Extended at the builder's request (MahaRERA application EA23052621070)

    Reason the builder gave MahaRERA:
    “a) The project site’s remote location—approximately 25 kilometres from Karjat station—poses logistical challenges in material delivery and labour/staff mobilization, further affecting the construction timeline. b) Despite these hurdles, we…” Read the full reason“a) The project site’s remote location—approximately 25 kilometres from Karjat station—poses logistical challenges in material delivery and labour/staff mobilization, further affecting the construction timeline. b) Despite these hurdles, we have continued to make consistent efforts to ensure quality development and timely delivery. We remained committed in completing the work in the feasible timeline, without compromising on the standards. We have obtained completion certificate from Group Grampanchayat Mograj dated 10/11/2020. However, occupancy certificate from Town and Country Planning De…”
  5. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: HOLIDAY MAIYAAN KARJAT’s extension records on MahaRERA (P52000000477), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on HOLIDAY MAIYAAN KARJAT

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52000000477
Status
Registered and active
Builder
B QUBES
Location
Chaudhar Wadi, Raigarh · 410201
Project type
Others
Registered on
18 Jul 2017
Completion date at registration
April 2019
Latest completion date
April 2029
Delay so far
116 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
132
Sold or booked
99%
Towers
4
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of HOLIDAY MAIYAAN KARJAT, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
D1100%100%100%100%
D2100%100%100%100%
A2100%100%100%100%
A3100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • D1: covers 3 floors
  • D2: covers 3 floors
  • A2: covers 3 floors
  • A3: covers 3 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on HOLIDAY MAIYAAN KARJAT every month.

HOLIDAY MAIYAAN KARJAT: buildings, flats and land, as filed on MahaRERA

  • Buildings: D1 (3 floors, 24 units) · D2 (3 floors, 12 units) · A2 (3 floors, 48 units) · A3 (3 floors, 48 units)
  • Car parking: 12 open
  • Land: 11,580 sq m (about 2.9 acres) · sanctioned built-up 5,824 sq m · recreational space 1,088 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

B Qubes has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 3 past the promised date (typically 62 months late). 6 complaints on MahaRERA across 2 projects.

Read Google reviews of HOLIDAY MAIYAAN KARJAT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

HOLIDAY MAIYAAN KARJAT: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about HOLIDAY MAIYAAN KARJAT

What is the possession date of HOLIDAY MAIYAAN KARJAT?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for HOLIDAY MAIYAAN KARJAT in Chaudhar Wadi, Raigarh is 30 April 2029 — 116 months later than 30 April 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for HOLIDAY MAIYAAN KARJAT?

Builders and listing sites often quote an earlier "target" date for handover. The completion date HOLIDAY MAIYAAN KARJAT's builder has filed on MahaRERA, the official one, is 30 April 2029, already 116 months later than the 30 April 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of HOLIDAY MAIYAAN KARJAT extended?

According to GharKundli's check of MahaRERA records (updated October 2026), HOLIDAY MAIYAAN KARJAT's builder applied to MahaRERA to extend the completion date 3 times: to 29 April 2020, giving the reason "To The Hon. Chairman, Maharashtra Real Estate Regulatory Authority, Mumbai Subject : Request for Project Extension for Holiday Maiyaan Karjat, MahaRERA Registration No. P52000000477) situated at Sr. No. 185/1 to 185/6, Vil Dhamani, Tal Karjat, Dist. Raigarh Respected Hon. Chairman, MahaRERA, This is in reference to our above mentioned project Holiday Maiyaan Karjat (phase 1) which is registered with the MAHARERA authority under the number: P52000000477 We would like to state that the construction on site is almost 85% completed including RCC superstructure and major finishing works like pai…"; to 30 April 2026, giving the reason "To, The Hon. Chairman, Maharashtra Real Estate Regulatory Authority, Mumbai Subject: Request for project extension for Holiday Maiyaan Karjat Phase 2, MahaRERA Registration NO. P52000000477, Situated at Sr. No. 185/1 to 185/6, Vil. Dhamni, Taluka Karjat, Dist Raigarh Respected Honourable Chairman, MahaRERA, This is in reference to our above mentioned project Holiday Maiyaan Karjat which is registered with the MahaRERA authority under the number: P52000000477 By an email received from MahaRERA authority on 11/04/23, and further our reply on 12th May 2023, We were informed and further instruc…"; to 31 December 2028, giving the reason "a) The project site’s remote location—approximately 25 kilometres from Karjat station—poses logistical challenges in material delivery and labour/staff mobilization, further affecting the construction timeline. b) Despite these hurdles, we have continued to make consistent efforts to ensure quality development and timely delivery. We remained committed in completing the work in the feasible timeline, without compromising on the standards. We have obtained completion certificate from Group Grampanchayat Mograj dated 10/11/2020. However, occupancy certificate from Town and Country Planning De…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of HOLIDAY MAIYAAN KARJAT?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of HOLIDAY MAIYAAN KARJAT in Chaudhar Wadi, Raigarh is P52000000477.

Is HOLIDAY MAIYAAN KARJAT registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), HOLIDAY MAIYAAN KARJAT is registered as P52000000477 and its status is "Registered and active".

What is the construction status of HOLIDAY MAIYAAN KARJAT?

According to GharKundli's check of MahaRERA records (updated October 2026), HOLIDAY MAIYAAN KARJAT's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does HOLIDAY MAIYAAN KARJAT have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is HOLIDAY MAIYAAN KARJAT safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), HOLIDAY MAIYAAN KARJAT is registered on MahaRERA as P52000000477, its completion date has moved 116 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does HOLIDAY MAIYAAN KARJAT have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: HOLIDAY MAIYAAN KARJAT PHASE II (P52000000479, possession 30 Apr 2029); HOLIDAY MAIYAAN KARJAT PHASE III (P52000000505, possession 30 Aug 2028). Check that your agreement names the registration of your own wing.

How can I get updates if HOLIDAY MAIYAAN KARJAT's possession date changes?

The latest dates are on HOLIDAY MAIYAAN KARJAT's MahaRERA page (P52000000477). GharKundli's Kundli Watch sends a free WhatsApp update on HOLIDAY MAIYAAN KARJAT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does HOLIDAY MAIYAAN KARJAT have?

According to GharKundli's check of MahaRERA records (updated October 2026), HOLIDAY MAIYAAN KARJAT has 4 buildings filed: D1 with 3 floors and 24 units; D2 with 3 floors and 12 units; A2 with 3 floors and 48 units; A3 with 3 floors and 48 units.

How much parking does HOLIDAY MAIYAAN KARJAT have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 12 open car parking spaces for HOLIDAY MAIYAAN KARJAT.

How big is the land of HOLIDAY MAIYAAN KARJAT?

According to GharKundli's check of MahaRERA records (updated October 2026), HOLIDAY MAIYAAN KARJAT stands on 11,580 sq m of land (about 2.9 acres), with 5,824 sq m of sanctioned built-up area and 1,088 sq m of recreational open space.

What is the track record of HOLIDAY MAIYAAN KARJAT's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), B Qubes has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 3 past the promised date (typically 62 months late). 6 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of HOLIDAY MAIYAAN KARJAT?

Google Maps has reviews of HOLIDAY MAIYAAN KARJAT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is HOLIDAY MAIYAAN KARJAT?

HOLIDAY MAIYAAN KARJAT by B QUBES is in Chaudhar Wadi, Raigarh (pincode 410201), Maharashtra, and is registered on MahaRERA as P52000000477, per GharKundli's check of MahaRERA records.

How many homes are in HOLIDAY MAIYAAN KARJAT?

According to GharKundli's check of MahaRERA records (updated October 2026), HOLIDAY MAIYAAN KARJAT has 132 homes in 4 towers registered on MahaRERA, and 99% of them are sold or booked.

When was HOLIDAY MAIYAAN KARJAT registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), HOLIDAY MAIYAAN KARJAT was registered on MahaRERA on 18 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on HOLIDAY MAIYAAN KARJAT?

1 court case is listed for HOLIDAY MAIYAAN KARJAT on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of HOLIDAY MAIYAAN KARJAT?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is B QUBES, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2029 in Raigad →

Other projects in Karjat

All 311 projects in Karjat (410201) →

Other projects by B QUBES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.