HOLIDAY MAIYAAN KARJAT PHASE III
by B QUBES · chaudhar wadi, Raigarh
Possession date of HOLIDAY MAIYAAN KARJAT PHASE III: 30 August 2028, moved from 30 April 2022 (72 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000000505, and currently active. Its completion date has moved from April 2022 to August 2028: 72 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about HOLIDAY MAIYAAN KARJAT PHASE III?
How the possession date of HOLIDAY MAIYAAN KARJAT PHASE III has moved
30 April 2022
Completion date given when the project was registered
30 April 2023
Extended at the builder's request (MahaRERA application EXT52000012057)
Reason the builder gave MahaRERA:
“To, The Hon. Chairman, Maharashtra Real Estate Regulatory Authority, Mumbai Subject: Request for project extension for Holiday Maiyaan Karjat Phase 2, MahaRERA Registration NO. P52000000505, Situated at Sr. No. 185/1 to 185/6, Vil. Dhamni,…” Read the full reason
“To, The Hon. Chairman, Maharashtra Real Estate Regulatory Authority, Mumbai Subject: Request for project extension for Holiday Maiyaan Karjat Phase 2, MahaRERA Registration NO. P52000000505, Situated at Sr. No. 185/1 to 185/6, Vil. Dhamni, Taluka Karjat, Dist Raigarh Respected Honourable Chairman, MahaRERA, This is in reference to our above mentioned project Holiday Maiyaan Karjat (Phase 3) which is registered with the MahaRERA authority under the number: P52000000505 We would like to mention that there are total 2 number of buildings in the said Phase, namely B and F. We would also like to…”30 April 2028
Extended at the builder's request (MahaRERA application EXT52000015371)
Reason the builder gave MahaRERA:
“To, The Hon. Chairman, Maharashtra Real Estate Regulatory Authority, Mumbai Subject: Request for project extension for Holiday Maiyaan Karjat Phase 2, MahaRERA Registration NO. P52000000505, Situated at Sr. No. 185/1 to 185/6, Vil. Dhamni,…” Read the full reason
“To, The Hon. Chairman, Maharashtra Real Estate Regulatory Authority, Mumbai Subject: Request for project extension for Holiday Maiyaan Karjat Phase 2, MahaRERA Registration NO. P52000000505, Situated at Sr. No. 185/1 to 185/6, Vil. Dhamni, Taluka Karjat, Dist Raigarh Respected Honourable Chairman, MahaRERA, This is in reference to our above mentioned project Holiday Maiyaan Karjat (Phase 3) which is registered with the MahaRERA authority under the number: P52000000505 We would like to mention that there are total 2 number of buildings in the said Phase, namely B and F. We would also like to…”30 August 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: HOLIDAY MAIYAAN KARJAT PHASE III’s extension records on MahaRERA (P52000000505), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on HOLIDAY MAIYAAN KARJAT PHASE III
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints and 1 court case, and how it ended
- Construction pace against the August 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- HOLIDAY MAIYAAN KARJATP52000000477 · possession 30 Apr 2029
- HOLIDAY MAIYAAN KARJAT PHASE IIP52000000479 · possession 30 Apr 2029
- MahaRERA registration
- P52000000505
- Status
- Registered and active
- Builder
- B QUBES
- Location
- chaudhar wadi, Raigarh · 410201
- Project type
- Others
- Registered on
- 18 Jul 2017
- Completion date at registration
- April 2022
- Latest completion date
- August 2028
- Delay so far
- 72 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 111
- Sold or booked
- 87%
- Towers
- 2
- Complaints on MahaRERA
- 3
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of HOLIDAY MAIYAAN KARJAT PHASE III, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| B | 100% | 68% | 19% | 15% |
| F | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- B: covers 3 floors
- F: covers 3 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on HOLIDAY MAIYAAN KARJAT PHASE III every month.
HOLIDAY MAIYAAN KARJAT PHASE III: buildings, flats and land, as filed on MahaRERA
- Buildings: B (3 floors, 111 units) · F (3 floors, 1 units)
- Car parking: 15 open
- Land: 11,966 sq m (about 3.0 acres) · sanctioned built-up 5,567 sq m · recreational space 1,124 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
B Qubes has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 3 past the promised date (typically 62 months late). 6 complaints on MahaRERA across 2 projects.
Read Google reviews of HOLIDAY MAIYAAN KARJAT PHASE III →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
HOLIDAY MAIYAAN KARJAT PHASE III: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about HOLIDAY MAIYAAN KARJAT PHASE III
What is the possession date of HOLIDAY MAIYAAN KARJAT PHASE III?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for HOLIDAY MAIYAAN KARJAT PHASE III in chaudhar wadi, Raigarh is 30 August 2028 — 72 months later than 30 April 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for HOLIDAY MAIYAAN KARJAT PHASE III?
Builders and listing sites often quote an earlier "target" date for handover. The completion date HOLIDAY MAIYAAN KARJAT PHASE III's builder has filed on MahaRERA, the official one, is 30 August 2028, already 72 months later than the 30 April 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of HOLIDAY MAIYAAN KARJAT PHASE III extended?
According to GharKundli's check of MahaRERA records (updated October 2026), HOLIDAY MAIYAAN KARJAT PHASE III's builder applied to MahaRERA to extend the completion date 2 times: to 30 April 2023, giving the reason "To, The Hon. Chairman, Maharashtra Real Estate Regulatory Authority, Mumbai Subject: Request for project extension for Holiday Maiyaan Karjat Phase 2, MahaRERA Registration NO. P52000000505, Situated at Sr. No. 185/1 to 185/6, Vil. Dhamni, Taluka Karjat, Dist Raigarh Respected Honourable Chairman, MahaRERA, This is in reference to our above mentioned project Holiday Maiyaan Karjat (Phase 3) which is registered with the MahaRERA authority under the number: P52000000505 We would like to mention that there are total 2 number of buildings in the said Phase, namely B and F. We would also like to…"; to 30 April 2028, giving the reason "To, The Hon. Chairman, Maharashtra Real Estate Regulatory Authority, Mumbai Subject: Request for project extension for Holiday Maiyaan Karjat Phase 2, MahaRERA Registration NO. P52000000505, Situated at Sr. No. 185/1 to 185/6, Vil. Dhamni, Taluka Karjat, Dist Raigarh Respected Honourable Chairman, MahaRERA, This is in reference to our above mentioned project Holiday Maiyaan Karjat (Phase 3) which is registered with the MahaRERA authority under the number: P52000000505 We would like to mention that there are total 2 number of buildings in the said Phase, namely B and F. We would also like to…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of HOLIDAY MAIYAAN KARJAT PHASE III?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of HOLIDAY MAIYAAN KARJAT PHASE III in chaudhar wadi, Raigarh is P52000000505.
Is HOLIDAY MAIYAAN KARJAT PHASE III registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), HOLIDAY MAIYAAN KARJAT PHASE III is registered as P52000000505 and its status is "Registered and active".
What is the construction status of HOLIDAY MAIYAAN KARJAT PHASE III?
According to GharKundli's check of MahaRERA records (updated October 2026), HOLIDAY MAIYAAN KARJAT PHASE III's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 68% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does HOLIDAY MAIYAAN KARJAT PHASE III have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is HOLIDAY MAIYAAN KARJAT PHASE III safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), HOLIDAY MAIYAAN KARJAT PHASE III is registered on MahaRERA as P52000000505, its completion date has moved 72 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does HOLIDAY MAIYAAN KARJAT PHASE III have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: HOLIDAY MAIYAAN KARJAT (P52000000477, possession 30 Apr 2029); HOLIDAY MAIYAAN KARJAT PHASE II (P52000000479, possession 30 Apr 2029). Check that your agreement names the registration of your own wing.
How can I get updates if HOLIDAY MAIYAAN KARJAT PHASE III's possession date changes?
The latest dates are on HOLIDAY MAIYAAN KARJAT PHASE III's MahaRERA page (P52000000505). GharKundli's Kundli Watch sends a free WhatsApp update on HOLIDAY MAIYAAN KARJAT PHASE III every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does HOLIDAY MAIYAAN KARJAT PHASE III have?
According to GharKundli's check of MahaRERA records (updated October 2026), HOLIDAY MAIYAAN KARJAT PHASE III has 2 buildings filed: B with 3 floors and 111 units; F with 3 floors and 1 units.
How much parking does HOLIDAY MAIYAAN KARJAT PHASE III have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 15 open car parking spaces for HOLIDAY MAIYAAN KARJAT PHASE III.
How big is the land of HOLIDAY MAIYAAN KARJAT PHASE III?
According to GharKundli's check of MahaRERA records (updated October 2026), HOLIDAY MAIYAAN KARJAT PHASE III stands on 11,966 sq m of land (about 3.0 acres), with 5,567 sq m of sanctioned built-up area and 1,124 sq m of recreational open space.
What is the track record of HOLIDAY MAIYAAN KARJAT PHASE III's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), B Qubes has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 3 past the promised date (typically 62 months late). 6 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of HOLIDAY MAIYAAN KARJAT PHASE III?
Google Maps has reviews of HOLIDAY MAIYAAN KARJAT PHASE III written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is HOLIDAY MAIYAAN KARJAT PHASE III?
HOLIDAY MAIYAAN KARJAT PHASE III by B QUBES is in chaudhar wadi, Raigarh (pincode 410201), Maharashtra, and is registered on MahaRERA as P52000000505, per GharKundli's check of MahaRERA records.
How many homes are in HOLIDAY MAIYAAN KARJAT PHASE III?
According to GharKundli's check of MahaRERA records (updated October 2026), HOLIDAY MAIYAAN KARJAT PHASE III has 111 homes in 2 towers registered on MahaRERA, and 87% of them are sold or booked.
When was HOLIDAY MAIYAAN KARJAT PHASE III registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), HOLIDAY MAIYAAN KARJAT PHASE III was registered on MahaRERA on 18 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on HOLIDAY MAIYAAN KARJAT PHASE III?
1 court case is listed for HOLIDAY MAIYAAN KARJAT PHASE III on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of HOLIDAY MAIYAAN KARJAT PHASE III?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is B QUBES, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of HOLIDAY MAIYAAN KARJAT PHASE III
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Raigad →
Other projects in Karjat
- HOLIDAY MAIYAAN KARJAT PHASE II
- SWAMI AASHRAY
- Ratnamisha Villas
- 21 ENCLAVE
- Krishna Valley Phase I
- MUDRA AVENUE
- Hill Top Residency
- Gajvakra Heights
Other projects by B QUBES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.