SAI KAUSTUBH RESIDENCY
by KAUSTUBH CONSTRUCTION COMPANY · Tal Khalapur, RaigarhAlso near Khalapur
Registered on MahaRERA under P52000018233. Status: Lapsed (registration period ended). Its completion date has moved from January 2021 to July 2023, 30 months later.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (July 2023) has passed.
GharKundli’s full report on SAI KAUSTUBH RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000018233
- Status
- Lapsed (registration period ended)
- Builder
- KAUSTUBH CONSTRUCTION COMPANY
- Location
- Tal Khalapur, Raigarh · 410202
- Project type
- Residential / Group Housing
- Registered on
- 16 Oct 2018
- Completion date at registration
- January 2021
- Latest completion date
- July 2023
- Delay so far
- 30 months
- Homes
- 12
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Kundli Watch
SAI KAUSTUBH RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SAI KAUSTUBH RESIDENCY
Is SAI KAUSTUBH RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI KAUSTUBH RESIDENCY is registered as P52000018233 and its status is "Lapsed (registration period ended)".
Where is SAI KAUSTUBH RESIDENCY?
SAI KAUSTUBH RESIDENCY by KAUSTUBH CONSTRUCTION COMPANY is in Tal Khalapur, Raigarh (pincode 410202), near Khalapur, Maharashtra, and is registered on MahaRERA as P52000018233, per GharKundli's check of MahaRERA records.
When is possession of SAI KAUSTUBH RESIDENCY due?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SAI KAUSTUBH RESIDENCY in Tal Khalapur, Raigarh is 30 July 2023 — 30 months later than 31 January 2021, the date given at registration. That date has already passed.
Does SAI KAUSTUBH RESIDENCY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
How many homes are in SAI KAUSTUBH RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI KAUSTUBH RESIDENCY has 12 homes in 1 tower registered on MahaRERA.
When was SAI KAUSTUBH RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI KAUSTUBH RESIDENCY was registered on MahaRERA on 16 October 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on SAI KAUSTUBH RESIDENCY?
No court cases are listed for SAI KAUSTUBH RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SAI KAUSTUBH RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is KAUSTUBH CONSTRUCTION COMPANY.
Other projects in pincode 410202
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.