UTSAV CITY PHASE II

by TODAY MICRON DEVELOPERS · Panvel, Raigarh

Registered on MahaRERA under P52000018102. Status: Completed. Its completion date has moved from June 2021 to December 2022, 18 months later.

Source: GharKundli’s check of MahaRERA records, November 2026.

GharKundli’s full report on UTSAV CITY PHASE II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000018102
Status
Completed
Builder
TODAY MICRON DEVELOPERS
Location
Panvel, Raigarh · 410206
Project type
Residential / Group Housing
Registered on
10 Oct 2018
Completion date at registration
June 2021
Latest completion date
December 2022
Delay so far
18 months
Homes
24
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Kundli Watch

UTSAV CITY PHASE II: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about UTSAV CITY PHASE II

Is UTSAV CITY PHASE II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), UTSAV CITY PHASE II is registered as P52000018102 and its status is "Completed".

Where is UTSAV CITY PHASE II?

UTSAV CITY PHASE II by TODAY MICRON DEVELOPERS is in Panvel, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000018102, per GharKundli's check of MahaRERA records.

When is possession of UTSAV CITY PHASE II due?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for UTSAV CITY PHASE II in Panvel, Raigarh is 30 December 2022 — 18 months later than 30 June 2021, the date given at registration.

Does UTSAV CITY PHASE II have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

How many homes are in UTSAV CITY PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), UTSAV CITY PHASE II has 24 homes in 1 tower registered on MahaRERA.

When was UTSAV CITY PHASE II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), UTSAV CITY PHASE II was registered on MahaRERA on 10 October 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on UTSAV CITY PHASE II?

No court cases are listed for UTSAV CITY PHASE II on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of UTSAV CITY PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is TODAY MICRON DEVELOPERS, which has 2 other projects registered on MahaRERA.

Other projects in pincode 410206

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.