VITTHAL KRUPA
by KAIZEN INDIA REALTY · Adai, RaigarhAlso near Panvel
Registered on MahaRERA under P52000018144. Status: Completed. Its completion date has moved from November 2020 to May 2022, 18 months later.
Source: GharKundli’s check of MahaRERA records, November 2026.
GharKundli’s full report on VITTHAL KRUPA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000018144
- Status
- Completed
- Builder
- KAIZEN INDIA REALTY
- Location
- Adai, Raigarh · 410206
- Project type
- Others
- Registered on
- 11 Oct 2018
- Completion date at registration
- November 2020
- Latest completion date
- May 2022
- Delay so far
- 18 months
- Homes
- 19
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Kundli Watch
VITTHAL KRUPA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about VITTHAL KRUPA
Is VITTHAL KRUPA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), VITTHAL KRUPA is registered as P52000018144 and its status is "Completed".
Where is VITTHAL KRUPA?
VITTHAL KRUPA by KAIZEN INDIA REALTY is in Adai, Raigarh (pincode 410206), near Panvel, Maharashtra, and is registered on MahaRERA as P52000018144, per GharKundli's check of MahaRERA records.
When is possession of VITTHAL KRUPA due?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for VITTHAL KRUPA in Adai, Raigarh is 21 May 2022 — 18 months later than 21 November 2020, the date given at registration.
Does VITTHAL KRUPA have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
How many homes are in VITTHAL KRUPA?
According to GharKundli's check of MahaRERA records (updated November 2026), VITTHAL KRUPA has 19 homes in 1 tower registered on MahaRERA.
When was VITTHAL KRUPA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), VITTHAL KRUPA was registered on MahaRERA on 11 October 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on VITTHAL KRUPA?
No court cases are listed for VITTHAL KRUPA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of VITTHAL KRUPA?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is KAIZEN INDIA REALTY.
Other projects in pincode 410206
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.