Skip to content
GharKundli

HARI OM PUSHPA

by PILLARS INDIA CONSTRUCTIONS · Panvel, Raigarh

Registered on MahaRERA under P52000021433. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

GharKundli’s full report on HARI OM PUSHPA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000021433
Status
Completed
Builder
PILLARS INDIA CONSTRUCTIONS
Location
Panvel, Raigarh · 410206
Project type
Others
Registered on
28 Jun 2019
Completion date at registration
December 2021
Latest completion date
December 2021
Homes
20
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Kundli Watch

HARI OM PUSHPA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about HARI OM PUSHPA

Is HARI OM PUSHPA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), HARI OM PUSHPA is registered as P52000021433 and its status is "Completed".

Where is HARI OM PUSHPA?

HARI OM PUSHPA by PILLARS INDIA CONSTRUCTIONS is in Panvel, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000021433, per GharKundli's check of MahaRERA records.

When is possession of HARI OM PUSHPA due?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for HARI OM PUSHPA in Panvel, Raigarh is 30 December 2021.

Does HARI OM PUSHPA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

How many homes are in HARI OM PUSHPA?

According to GharKundli's check of MahaRERA records (updated November 2026), HARI OM PUSHPA has 20 homes in 1 tower registered on MahaRERA.

When was HARI OM PUSHPA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), HARI OM PUSHPA was registered on MahaRERA on 28 June 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on HARI OM PUSHPA?

No court cases are listed for HARI OM PUSHPA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of HARI OM PUSHPA?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PILLARS INDIA CONSTRUCTIONS, which has 3 other projects registered on MahaRERA.

Other projects in pincode 410206

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.