Ashtavinayak Complex

by Ashtavinayak Enterprises · Neral, Raigarh

Registered on MahaRERA under PM1270002501104, and currently active. Its completion date has moved from December 2029 to April 2030, 4 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on Ashtavinayak Complex

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PM1270002501104
Status
Registered and active
Builder
Ashtavinayak Enterprises
Location
Neral, Raigarh · 410101
Project type
Mixed
Registered on
7 Oct 2025
Completion date at registration
December 2029
Latest completion date
April 2030
Delay so far
4 months
Homes
143
Sold or booked
8%
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
6

Kundli Watch

Ashtavinayak Complex: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about Ashtavinayak Complex

Is Ashtavinayak Complex registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashtavinayak Complex is registered as PM1270002501104 and its status is "Registered and active".

Where is Ashtavinayak Complex?

Ashtavinayak Complex by Ashtavinayak Enterprises is in Neral, Raigarh (pincode 410101), Maharashtra, and is registered on MahaRERA as PM1270002501104, per GharKundli's check of MahaRERA records.

When is possession of Ashtavinayak Complex due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ashtavinayak Complex in Neral, Raigarh is 30 April 2030 — 4 months later than 31 December 2029, the date given at registration.

Does Ashtavinayak Complex have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of Ashtavinayak Complex?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Ashtavinayak Enterprises, which has 6 other projects registered on MahaRERA.

Other projects in pincode 410101

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.