Emerald Bay Building 10

by Pune Projects LLP · Mundhva AV, Pune

Registered on MahaRERA under P52100026110, and currently active. Its completion date has moved from June 2025 to April 2030: 54 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. MahaRERA has issued a regulatory order on this project.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on Emerald Bay Building 10

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100026110
Status
Registered and active
Builder
Pune Projects LLP
Location
Mundhva AV, Pune · 411036
Project type
Residential / Group Housing
Registered on
19 Aug 2020
Completion date at registration
June 2025
Latest completion date
April 2030
Delay so far
54 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
219
Towers
1
Complaints on MahaRERA
0
Court cases listed
5
MahaRERA regulatory orders
1
Title report on file
Not found
Builder's other MahaRERA projects
10

Kundli Watch

Emerald Bay Building 10: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about Emerald Bay Building 10

Is Emerald Bay Building 10 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Emerald Bay Building 10 is registered as P52100026110 and its status is "Registered and active".

Where is Emerald Bay Building 10?

Emerald Bay Building 10 by Pune Projects LLP is in Mundhva AV, Pune (pincode 411036), Maharashtra, and is registered on MahaRERA as P52100026110, per GharKundli's check of MahaRERA records.

When is possession of Emerald Bay Building 10 due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Emerald Bay Building 10 in Mundhva AV, Pune is 30 April 2030 — 54 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Does Emerald Bay Building 10 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of Emerald Bay Building 10?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Pune Projects LLP, which has 10 other projects registered on MahaRERA.

All projects with possession due in 2030 in Pune →

Other projects in pincode 411036

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.