Skip to content
GharKundli

Menlo Delicia

by MENLO PROPERTIES LLP · Mundhwa, Pune 411036

What’s in the report? →

Possession date of Menlo Delicia (MahaRERA P52100032791): 30 October 2027, moved from 31 December 2025 (18 months later). It has 32 homes, 31% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100032791, and currently active. Its completion date has moved from December 2025 to October 2027: 18 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P52100032791, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Menlo Delicia?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Menlo Delicia has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 30 June 2027

    Extended at the builder's request (MahaRERA application EA20082622248)

    Reason the builder gave MahaRERA:
    “In view of market demand, we plan to construct additional floors and have applied for revised sanctioned plans. Consequently, the overall construction timeline will be extended. It is important to note that the promoter has transparently co…” Read the full reason“In view of market demand, we plan to construct additional floors and have applied for revised sanctioned plans. Consequently, the overall construction timeline will be extended. It is important to note that the promoter has transparently communicated this matter to all allottees, majority of the allottees have agreed to provide their consent for the extension. In anticipation of your understanding and cooperation, I would like to express my gratitude. We are committed to completing the project within the extended timeframe and ensuring compliance with all regulatory requirements.”
  3. 30 October 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Menlo Delicia’s extension records on MahaRERA (P52100032791), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Menlo Delicia

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100032791
Status
Registered and active
Builder
MENLO PROPERTIES LLP
Location
Mundhwa, Pune · 411036
Project type
Residential / Group Housing
Registered on
29 Jan 2022
Completion date at registration
December 2025
Latest completion date
October 2027
Delay so far
18 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
32
Sold or booked
31%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Menlo Delicia, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Delicia100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Delicia: covers P+7

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Menlo Delicia every 1–2 months.

Menlo Delicia: buildings, flats and land, as filed on MahaRERA

  • Buildings: Delicia (8 floors, 32 units)
  • Land: 1,520 sq m (about 0.4 acres) · sanctioned built-up 2,665 sq m
  • Land, as filed: S NO 92 HISSA 8 AND 92 HISSA 9
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Menlo Delicia →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Menlo Delicia: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Menlo Delicia

What is the possession date of Menlo Delicia?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Menlo Delicia in Mundhwa, Pune is 30 October 2027 — 18 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 18 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Menlo Delicia?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Menlo Delicia's builder has filed on MahaRERA, the official one, is 30 October 2027, already 18 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Menlo Delicia extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Menlo Delicia's builder applied to MahaRERA to extend the completion date once: to 30 June 2027, giving the reason "In view of market demand, we plan to construct additional floors and have applied for revised sanctioned plans. Consequently, the overall construction timeline will be extended. It is important to note that the promoter has transparently communicated this matter to all allottees, majority of the allottees have agreed to provide their consent for the extension. In anticipation of your understanding and cooperation, I would like to express my gratitude. We are committed to completing the project within the extended timeframe and ensuring compliance with all regulatory requirements.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Menlo Delicia?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Menlo Delicia in Mundhwa, Pune is P52100032791.

Is Menlo Delicia registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Menlo Delicia is registered as P52100032791 and its status is "Registered and active".

What is the current construction status of Menlo Delicia? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Menlo Delicia's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Delicia is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Menlo Delicia have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Menlo Delicia safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Menlo Delicia is registered on MahaRERA as P52100032791, its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Menlo Delicia?

Menlo Delicia is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Menlo Delicia?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Menlo Delicia: gharkundli.com/tools/property-cost-calculator

Has Menlo Delicia received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Menlo Delicia is still under construction, with 30 October 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Menlo Delicia uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Menlo Delicia was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Menlo Delicia's possession date changes?

The latest dates are on Menlo Delicia's MahaRERA page (P52100032791). GharKundli's Kundli Watch sends a free WhatsApp update on Menlo Delicia every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Menlo Delicia have?

According to GharKundli's check of MahaRERA records (updated October 2026), Menlo Delicia has one building filed: Delicia with 8 floors and 32 units.

How big is the land of Menlo Delicia?

According to GharKundli's check of MahaRERA records (updated October 2026), Menlo Delicia stands on 1,520 sq m of land (about 0.4 acres), with 2,665 sq m of sanctioned built-up area.

What are the reviews of Menlo Delicia?

Google Maps has reviews of Menlo Delicia written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Menlo Delicia?

Menlo Delicia by MENLO PROPERTIES LLP is in Mundhwa, Pune, pincode 411036, Maharashtra, and is registered on MahaRERA as P52100032791, per GharKundli's check of MahaRERA records. Its land is filed as S NO 92 HISSA 8 AND 92 HISSA 9. GharKundli lists all 241 MahaRERA projects in Mundhwa (411036).

How many flats are in Menlo Delicia, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Menlo Delicia has 32 homes in 1 tower registered on MahaRERA, and 31% of them are sold or booked.

When was Menlo Delicia registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Menlo Delicia was registered on MahaRERA on 29 January 2022. GharKundli did not find a title report on the land on file there.

Does Menlo Delicia have any legal issues or court cases?

No court cases are listed for Menlo Delicia on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Menlo Delicia?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MENLO PROPERTIES LLP.

All projects with possession due in 2027 in Pune →

Other projects in Mundhwa (411036)

All 241 projects in Mundhwa (411036) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.