VAADI LAKE MULSHI
by CAPRICORN DEVELOPERS AND HOMES PRIVATE LIMITED · Shirvali, Pune
Registered on MahaRERA under P52100048722, and currently active. Its completion date has moved from December 2027 to April 2028, 4 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on VAADI LAKE MULSHI
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100048722
- Status
- Registered and active
- Builder
- CAPRICORN DEVELOPERS AND HOMES PRIVATE LIMITED
- Location
- Shirvali, Pune · 412108
- Project type
- Others
- Registered on
- 17 Jan 2023
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- Delay so far
- 4 months
- Homes
- 7
- Sold or booked
- 29%
- Towers
- 7
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Kundli Watch
VAADI LAKE MULSHI: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about VAADI LAKE MULSHI
Is VAADI LAKE MULSHI registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VAADI LAKE MULSHI is registered as P52100048722 and its status is "Registered and active".
Where is VAADI LAKE MULSHI?
VAADI LAKE MULSHI by CAPRICORN DEVELOPERS AND HOMES PRIVATE LIMITED is in Shirvali, Pune (pincode 412108), Maharashtra, and is registered on MahaRERA as P52100048722, per GharKundli's check of MahaRERA records.
When is possession of VAADI LAKE MULSHI due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VAADI LAKE MULSHI in Shirvali, Pune is 30 April 2028 — 4 months later than 31 December 2027, the date given at registration.
Does VAADI LAKE MULSHI have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of VAADI LAKE MULSHI?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is CAPRICORN DEVELOPERS AND HOMES PRIVATE LIMITED.
Other projects in pincode 412108
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.