Synergy Satvam Hills A6
by SYNERGY PROPERTIES · Jamgaon, Pune 412108Registered on MahaRERA as “Satvam Hills A6”
What’s in the report? →Possession date of Synergy Satvam Hills A6 (MahaRERA P52100054456): 30 October 2027, moved from 30 June 2025 (24 months later). No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100054456, and currently active. Its completion date has moved from June 2025 to October 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P52100054456, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Synergy Satvam Hills A6?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Synergy Satvam Hills A6 has moved
30 June 2025
Completion date given when the project was registered
30 June 2026
Extended at the builder's request (MahaRERA application EA30062501874)
Reason the builder gave MahaRERA:
“1. We unable to work on site as it is in Mulshi, which receives one of the heaviest rainfalls in the country leading to disruption of work, for around 4 months. 2. since the site is very far (40 kms) away from the main city, there is shorta…” Read the full reason
“1. We unable to work on site as it is in Mulshi, which receives one of the heaviest rainfalls in the country leading to disruption of work, for around 4 months. 2. since the site is very far (40 kms) away from the main city, there is shortage of labour and availability of less transport. 3. Scarcity of construction material like stone, murum, crush sand etc. also causes delayed in work. 4. Due to rain falls N.A. Demarcation got delayed and subsequently all other revenues formalities got delayed which are needed for application of completion. 5. Load shading of erratic electricity supply ham…”30 June 2027
Extended at the builder's request (MahaRERA application EA25062621536)
Reason the builder gave MahaRERA:
“We are applying for Extension of our Project Completion Date with MahaRERA Authority under Section – 7(3) of the Act. We would like to inform the Authority that the development on site is under process and is expected to be completed in nex…” Read the full reason
“We are applying for Extension of our Project Completion Date with MahaRERA Authority under Section – 7(3) of the Act. We would like to inform the Authority that the development on site is under process and is expected to be completed in next 9 to 10 months and then will require another 2 months to fulfil Sanction Authorities formalities and receive the completion certificate for the project. After conveying the same to the allottees, it was mutually decided to apply for an extension with the Authority. Hence, we request you to extend proposed date of completion for the Project from 30/06/20…”30 October 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Synergy Satvam Hills A6’s extension records on MahaRERA (P52100054456), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Synergy Satvam Hills A6
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Satvam Hills A4P52100052106 · possession 30 Apr 2027
- SATVAM HILLS A5P52100052048 · possession 24 Feb 2026
- Satvam Hills B7P52100053964 · possession 31 Dec 2026
- SATVAM HILLS C1P52100080889 · possession 31 Mar 2027
- Satvam Hills C4P52100055512 · possession 30 Apr 2027
- Satvam Hills C5PP1260002601969 · possession 31 Aug 2029
- MahaRERA registration
- P52100054456
- Status
- Registered and active
- Builder
- SYNERGY PROPERTIES
- Location
- Jamgaon, Pune · 412108
- Project type
- Plotted
- Registered on
- 25 Jan 2024
- Completion date at registration
- June 2025
- Latest completion date
- October 2027
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 10
Synergy Satvam Hills A6: buildings, flats and land, as filed on MahaRERA
- Land: 14,207 sq m (about 3.5 acres) · recreational space 2,563 sq m
- Land, as filed: 319part 321 part 322 part 323A 323 B part
- Map: Get directions
The builder’s record and reviews
Synergy Properties (a group of 3 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 14 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 5 months); 8 still being built, 6 past the promised date (typically 11 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Synergy Satvam Hills A6 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Synergy Satvam Hills A6: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Synergy Satvam Hills A6
What is the possession date of Synergy Satvam Hills A6?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Synergy Satvam Hills A6 in Jamgaon, Pune is 30 October 2027 — 24 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Synergy Satvam Hills A6?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Synergy Satvam Hills A6's builder has filed on MahaRERA, the official one, is 30 October 2027, already 24 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Synergy Satvam Hills A6 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Synergy Satvam Hills A6's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2026, giving the reason "1. We unable to work on site as it is in Mulshi, which receives one of the heaviest rainfalls in the country leading to disruption of work, for around 4 months. 2. since the site is very far (40 kms) away from the main city, there is shortage of labour and availability of less transport. 3. Scarcity of construction material like stone, murum, crush sand etc. also causes delayed in work. 4. Due to rain falls N.A. Demarcation got delayed and subsequently all other revenues formalities got delayed which are needed for application of completion. 5. Load shading of erratic electricity supply ham…"; to 30 June 2027, giving the reason "We are applying for Extension of our Project Completion Date with MahaRERA Authority under Section – 7(3) of the Act. We would like to inform the Authority that the development on site is under process and is expected to be completed in next 9 to 10 months and then will require another 2 months to fulfil Sanction Authorities formalities and receive the completion certificate for the project. After conveying the same to the allottees, it was mutually decided to apply for an extension with the Authority. Hence, we request you to extend proposed date of completion for the Project from 30/06/20…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Synergy Satvam Hills A6?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Synergy Satvam Hills A6 in Jamgaon, Pune is P52100054456.
Is Synergy Satvam Hills A6 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Synergy Satvam Hills A6 is registered as P52100054456 and its status is "Registered and active".
What is the current construction status of Synergy Satvam Hills A6? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Synergy Satvam Hills A6's status on MahaRERA is "Registered and active". GharKundli's full report compares construction progress with the deadline.
Does Synergy Satvam Hills A6 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Synergy Satvam Hills A6 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Synergy Satvam Hills A6 is registered on MahaRERA as P52100054456, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Synergy Satvam Hills A6?
Synergy Satvam Hills A6 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Synergy Satvam Hills A6?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Synergy Satvam Hills A6: gharkundli.com/tools/property-cost-calculator
Has Synergy Satvam Hills A6 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Synergy Satvam Hills A6 is still under construction, with 30 October 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Synergy Satvam Hills A6 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Synergy Satvam Hills A6 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
Does Synergy Satvam Hills A6 have other wings or phases?
Yes. MahaRERA lists 6 other registrations of the same project, each with its own possession date: Satvam Hills A4 (P52100052106, possession 30 Apr 2027); SATVAM HILLS A5 (P52100052048, possession 24 Feb 2026); Satvam Hills B7 (P52100053964, possession 31 Dec 2026); SATVAM HILLS C1 (P52100080889, possession 31 Mar 2027); Satvam Hills C4 (P52100055512, possession 30 Apr 2027); Satvam Hills C5 (PP1260002601969, possession 31 Aug 2029). Check that your agreement names the registration of your own wing.
How can I get updates if Synergy Satvam Hills A6's possession date changes?
The latest dates are on Synergy Satvam Hills A6's MahaRERA page (P52100054456). GharKundli's Kundli Watch sends a free WhatsApp update on Synergy Satvam Hills A6 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How big is the land of Synergy Satvam Hills A6?
According to GharKundli's check of MahaRERA records (updated October 2026), Synergy Satvam Hills A6 stands on 14,207 sq m of land (about 3.5 acres) and 2,563 sq m of recreational open space.
What is the track record of Synergy Satvam Hills A6's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Synergy Properties (a group of 3 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 14 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 5 months); 8 still being built, 6 past the promised date (typically 11 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Synergy Satvam Hills A6?
Google Maps has reviews of Synergy Satvam Hills A6 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Synergy Satvam Hills A6?
Synergy Satvam Hills A6 by SYNERGY PROPERTIES is in Jamgaon, Pune, pincode 412108, Maharashtra, and is registered on MahaRERA as P52100054456, per GharKundli's check of MahaRERA records. Its land is filed as 319part 321 part 322 part 323A 323 B part. GharKundli lists all 73 MahaRERA projects in Paud (412108).
When was Synergy Satvam Hills A6 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Synergy Satvam Hills A6 was registered on MahaRERA on 25 January 2024. GharKundli did not find a title report on the land on file there.
Does Synergy Satvam Hills A6 have any legal issues or court cases?
No court cases are listed for Synergy Satvam Hills A6 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Synergy Satvam Hills A6?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SYNERGY PROPERTIES, which has 10 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Synergy Satvam Hills A6
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Pune →
Other projects in Mulshi
- Satvam Hills C4
- Signature Park Phase - I
- Nirman Serenopolis
- Lotus Crest
- Goodland Phase-III
- Kohinoor Uptown Avenue
- Westgate Business Park
- West World
Other projects by SYNERGY PROPERTIES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.