Synergy Paloma Azure
by SYNERGY PROPERTIES · Adhale Bk, Pune 410506Also near Talegaon DabhadeRegistered on MahaRERA as “PALOMA AZURE”
What’s in the report? →Possession date of Synergy Paloma Azure (MahaRERA P52100078832): 31 December 2026, moved from 31 January 2026 (11 months later). No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100078832, and currently active.
Source: MahaRERA website — records for P52100078832, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Synergy Paloma Azure?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Synergy Paloma Azure has moved
31 January 2026
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA24082622370)
Reason the builder gave MahaRERA:
“We are applying for Post Facto Extension (i.e. Extension after receiving Completion Certificate) for our Project Completion Date with MahaRERA Authority, to extend proposed date of Completion for the Project from 31-01-2026 to Revised Compl…” Read the full reason
“We are applying for Post Facto Extension (i.e. Extension after receiving Completion Certificate) for our Project Completion Date with MahaRERA Authority, to extend proposed date of Completion for the Project from 31-01-2026 to Revised Completion Date of 31-12-2026. We have received Final Layout Sanction on 05-10-2025 and have got Tahsildar Inward for project completion on 20-02-2026 we need to update a few details as per the Final Layout Santion, hence this declaration.”
Source: Synergy Paloma Azure’s extension records on MahaRERA (P52100078832), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Synergy Paloma Azure
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100078832
- Status
- Registered and active
- Builder
- SYNERGY PROPERTIES
- Location
- Adhale Bk, Pune · 410506
- Project type
- Plotted
- Registered on
- 13 Jan 2025
- Completion date at registration
- January 2026
- Latest completion date
- December 2026
- Delay so far
- 11 months
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 10
Construction progress of Synergy Paloma Azure, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
Commencement certificate (CC), as filed on MahaRERA
Latest CC order on MahaRERA: dated 15/10/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Synergy Paloma Azure every 1–2 months.
Synergy Paloma Azure: buildings, flats and land, as filed on MahaRERA
- Land: 2,603 sq m (about 0.6 acres) · recreational space 396 sq m
- Land, as filed: GAT NO 271
- Map: Get directions
The builder’s record and reviews
Synergy Properties (a group of 3 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 14 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 5 months); 8 still being built, 6 past the promised date (typically 11 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Synergy Paloma Azure →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Synergy Paloma Azure: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Synergy Paloma Azure
What is the possession date of Synergy Paloma Azure?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Synergy Paloma Azure in Adhale Bk, Pune is 31 December 2026 — 11 months later than 31 January 2026, the date given at registration.
The date has already moved 11 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Synergy Paloma Azure?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Synergy Paloma Azure's builder has filed on MahaRERA, the official one, is 31 December 2026, already 11 months later than the 31 January 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Synergy Paloma Azure extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Synergy Paloma Azure's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "We are applying for Post Facto Extension (i.e. Extension after receiving Completion Certificate) for our Project Completion Date with MahaRERA Authority, to extend proposed date of Completion for the Project from 31-01-2026 to Revised Completion Date of 31-12-2026. We have received Final Layout Sanction on 05-10-2025 and have got Tahsildar Inward for project completion on 20-02-2026 we need to update a few details as per the Final Layout Santion, hence this declaration.".
What is the RERA number of Synergy Paloma Azure?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Synergy Paloma Azure in Adhale Bk, Pune is P52100078832.
Is Synergy Paloma Azure registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Synergy Paloma Azure is registered as P52100078832 and its status is "Registered and active".
What is the current construction status of Synergy Paloma Azure? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Synergy Paloma Azure's status on MahaRERA is "Registered and active". GharKundli's full report compares construction progress with the deadline.
Does Synergy Paloma Azure have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Synergy Paloma Azure safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Synergy Paloma Azure is registered on MahaRERA as P52100078832, its completion date has moved 11 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Synergy Paloma Azure?
Synergy Paloma Azure is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Synergy Paloma Azure?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Synergy Paloma Azure: gharkundli.com/tools/property-cost-calculator
Has Synergy Paloma Azure received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Synergy Paloma Azure is still under construction, with 31 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Synergy Paloma Azure uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Synergy Paloma Azure was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Synergy Paloma Azure's possession date changes?
The latest dates are on Synergy Paloma Azure's MahaRERA page (P52100078832). GharKundli's Kundli Watch sends a free WhatsApp update on Synergy Paloma Azure every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How big is the land of Synergy Paloma Azure?
According to GharKundli's check of MahaRERA records (updated October 2026), Synergy Paloma Azure stands on 2,603 sq m of land (about 0.6 acres) and 396 sq m of recreational open space.
What is the track record of Synergy Paloma Azure's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Synergy Properties (a group of 3 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 14 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 5 months); 8 still being built, 6 past the promised date (typically 11 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Synergy Paloma Azure?
Google Maps has reviews of Synergy Paloma Azure written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Synergy Paloma Azure?
Synergy Paloma Azure by SYNERGY PROPERTIES is in Adhale Bk, Pune, pincode 410506 (near Talegaon Dabhade), Maharashtra, and is registered on MahaRERA as P52100078832, per GharKundli's check of MahaRERA records. Its land is filed as GAT NO 271. GharKundli lists all 226 MahaRERA projects in Talegaon Dabhade (410506).
When was Synergy Paloma Azure registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Synergy Paloma Azure was registered on MahaRERA on 13 January 2025. GharKundli did not find a title report on the land on file there.
Does Synergy Paloma Azure have any legal issues or court cases?
No court cases are listed for Synergy Paloma Azure on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Synergy Paloma Azure?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SYNERGY PROPERTIES, which has 10 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Synergy Paloma Azure
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Pune →
Other projects in Talegaon Dabhade (410506)
- Belmont Reserve Phase 3
- Belmont Reserve Phase 5
- Belmont Reserve Phase 2
- Nakshatraban
- Abhimaan Homes Phase 3
- Yash Evana
- Kulswamini Park
- Aria A and B
Other projects by SYNERGY PROPERTIES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.