by VISHAL VILAS KALEKAR · Mascernes Colony II, Pune 410506

What’s in the report? →

Possession date of Kulswamini Park (MahaRERA P52100031977): 30 April 2028, moved from 31 December 2025 (24 months later). It has 48 homes, 31% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100031977, and currently active. Its completion date has moved from December 2025 to April 2028: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P52100031977, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Kulswamini Park?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Kulswamini Park has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 31 December 2027

    Extended at the builder's request (MahaRERA application EA09082622066)

    Reason the builder gave MahaRERA:
    “The project work has been 100% completed at site, including all necessary development and construction works. There is no pending physical work in the project. However, the Revised/Updated Sanctioned Plan is required to be updated on the Ma…” Read the full reason“The project work has been 100% completed at site, including all necessary development and construction works. There is no pending physical work in the project. However, the Revised/Updated Sanctioned Plan is required to be updated on the MahaRERA portal, along with certain corrections in the project details as per the latest approved plan and actual completed status of the project. We therefore request the Hon’ble Authority to kindly grant the required extension of the project registration period to enable us to complete the necessary portal corrections and update the revised plan. We hereb…”
  3. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Kulswamini Park’s extension records on MahaRERA (P52100031977), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Kulswamini Park

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100031977
Status
Registered and active
Builder
VISHAL VILAS KALEKAR
Location
Mascernes Colony II, Pune · 410506
Project type
Residential / Group Housing
Registered on
29 Nov 2021
Completion date at registration
December 2025
Latest completion date
April 2028
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
48
Sold or booked
31%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Kulswamini Park, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
KULSWAMINI PARK100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • KULSWAMINI PARK: covers 7 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kulswamini Park every 1–2 months.

Kulswamini Park: buildings, flats and land, as filed on MahaRERA

  • Buildings: KULSWAMINI PARK (7 floors, 53 units)
  • Car parking: 13 covered
  • Land: 1,000 sq m (about 0.2 acres) · sanctioned built-up 2,663 sq m · recreational space 400 sq m
  • Land, as filed: 386/2/1
  • Map: Get directions

The builder’s record and reviews

Vishal Vilas Kalekar has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 6 months late). No complaints on MahaRERA.

Read Google reviews of Kulswamini Park →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Kulswamini Park: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Kulswamini Park

What is the possession date of Kulswamini Park?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kulswamini Park in Mascernes Colony II, Pune is 30 April 2028 — 24 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 24 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Kulswamini Park?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Kulswamini Park's builder has filed on MahaRERA, the official one, is 30 April 2028, already 24 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Kulswamini Park extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Kulswamini Park's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "The project work has been 100% completed at site, including all necessary development and construction works. There is no pending physical work in the project. However, the Revised/Updated Sanctioned Plan is required to be updated on the MahaRERA portal, along with certain corrections in the project details as per the latest approved plan and actual completed status of the project. We therefore request the Hon’ble Authority to kindly grant the required extension of the project registration period to enable us to complete the necessary portal corrections and update the revised plan. We hereb…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Kulswamini Park?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Kulswamini Park in Mascernes Colony II, Pune is P52100031977.

Is Kulswamini Park registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Kulswamini Park is registered as P52100031977 and its status is "Registered and active".

What is the current construction status of Kulswamini Park? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Kulswamini Park's status on MahaRERA is "Registered and active". As filed by the builder, slab work on KULSWAMINI PARK is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Kulswamini Park have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Kulswamini Park safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Kulswamini Park is registered on MahaRERA as P52100031977, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Kulswamini Park?

Kulswamini Park is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Kulswamini Park?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Kulswamini Park: gharkundli.com/tools/property-cost-calculator

Has Kulswamini Park received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Kulswamini Park is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Kulswamini Park uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Kulswamini Park was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Kulswamini Park's possession date changes?

The latest dates are on Kulswamini Park's MahaRERA page (P52100031977). GharKundli's Kundli Watch sends a free WhatsApp update on Kulswamini Park every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Kulswamini Park have?

According to GharKundli's check of MahaRERA records (updated October 2026), Kulswamini Park has one building filed: KULSWAMINI PARK with 7 floors and 53 units.

How much parking does Kulswamini Park have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 13 covered car parking spaces for Kulswamini Park.

How big is the land of Kulswamini Park?

According to GharKundli's check of MahaRERA records (updated October 2026), Kulswamini Park stands on 1,000 sq m of land (about 0.2 acres), with 2,663 sq m of sanctioned built-up area and 400 sq m of recreational open space.

What is the track record of Kulswamini Park's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Vishal Vilas Kalekar has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 6 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Kulswamini Park?

Google Maps has reviews of Kulswamini Park written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Kulswamini Park?

Kulswamini Park by VISHAL VILAS KALEKAR is in Mascernes Colony II, Pune, pincode 410506, Maharashtra, and is registered on MahaRERA as P52100031977, per GharKundli's check of MahaRERA records. Its land is filed as 386/2/1. GharKundli lists all 226 MahaRERA projects in Talegaon Dabhade (410506).

How many flats are in Kulswamini Park, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Kulswamini Park has 48 homes in 1 tower registered on MahaRERA, and 31% of them are sold or booked.

When was Kulswamini Park registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Kulswamini Park was registered on MahaRERA on 29 November 2021. GharKundli did not find a title report on the land on file there.

Does Kulswamini Park have any legal issues or court cases?

No court cases are listed for Kulswamini Park on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Kulswamini Park?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VISHAL VILAS KALEKAR.

All projects with possession due in 2028 in Pune →

Other projects in Mawal

All 226 projects in Talegaon Dabhade (410506) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.