by SYMPHONY LANDMARKS LLP · Paud, Pune 412108Registered on MahaRERA as “Satvam Hills B7”

What’s in the report? →

Possession date of Symphony Satvam Hills B7 (MahaRERA P52100053964): 31 December 2026, moved from 30 January 2025 (23 months later). No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100053964, and currently active.

Source: MahaRERA website — records for P52100053964, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Symphony Satvam Hills B7?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Symphony Satvam Hills B7 has moved

  1. 30 January 2025

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EA28072621894)

    Reason the builder gave MahaRERA:
    “We are applying for Post Facto Extension (i.e., extension after receiving Completion Certificate) for our Project Completion Date with MahaRERA Authority, to extend proposed date of Completion for the Project from 31-01-2025 to Revised Comp…” Read the full reason“We are applying for Post Facto Extension (i.e., extension after receiving Completion Certificate) for our Project Completion Date with MahaRERA Authority, to extend proposed date of Completion for the Project from 31-01-2025 to Revised Completion Date of 31-12-2026. We have received OC on 24-02-2026 but we need to update a few details as per the completion plan, hence this declaration.”

Source: Symphony Satvam Hills B7’s extension records on MahaRERA (P52100053964), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Symphony Satvam Hills B7

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100053964
Status
Registered and active
Builder
SYMPHONY LANDMARKS LLP
Location
Paud, Pune · 412108
Project type
Plotted
Registered on
18 Dec 2023
Completion date at registration
January 2025
Latest completion date
December 2026
Delay so far
23 months
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Symphony Satvam Hills B7, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Commencement certificate (CC), as filed on MahaRERA

Latest CC order on MahaRERA: dated 06/12/2024.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Symphony Satvam Hills B7 every 1–2 months.

Symphony Satvam Hills B7: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Synergy Properties (a group of 3 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 14 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 5 months); 8 still being built, 6 past the promised date (typically 11 months late); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Symphony Satvam Hills B7 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Symphony Satvam Hills B7: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Symphony Satvam Hills B7

What is the possession date of Symphony Satvam Hills B7?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Symphony Satvam Hills B7 in Paud, Pune is 31 December 2026 — 23 months later than 30 January 2025, the date given at registration.

The date has already moved 23 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Symphony Satvam Hills B7?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Symphony Satvam Hills B7's builder has filed on MahaRERA, the official one, is 31 December 2026, already 23 months later than the 30 January 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Symphony Satvam Hills B7 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Symphony Satvam Hills B7's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "We are applying for Post Facto Extension (i.e., extension after receiving Completion Certificate) for our Project Completion Date with MahaRERA Authority, to extend proposed date of Completion for the Project from 31-01-2025 to Revised Completion Date of 31-12-2026. We have received OC on 24-02-2026 but we need to update a few details as per the completion plan, hence this declaration.".

What is the RERA number of Symphony Satvam Hills B7?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Symphony Satvam Hills B7 in Paud, Pune is P52100053964.

Is Symphony Satvam Hills B7 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Symphony Satvam Hills B7 is registered as P52100053964 and its status is "Registered and active".

What is the current construction status of Symphony Satvam Hills B7? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Symphony Satvam Hills B7's status on MahaRERA is "Registered and active". GharKundli's full report compares construction progress with the deadline.

Does Symphony Satvam Hills B7 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Symphony Satvam Hills B7 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Symphony Satvam Hills B7 is registered on MahaRERA as P52100053964, its completion date has moved 23 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Symphony Satvam Hills B7?

Symphony Satvam Hills B7 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Symphony Satvam Hills B7?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Symphony Satvam Hills B7: gharkundli.com/tools/property-cost-calculator

Has Symphony Satvam Hills B7 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Symphony Satvam Hills B7 is still under construction, with 31 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Symphony Satvam Hills B7 a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Symphony Satvam Hills B7's planning authority on MahaRERA is Pune Metropolitan Regional Development Authority (PMRDA), not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Symphony Satvam Hills B7 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Symphony Satvam Hills B7 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Symphony Satvam Hills B7 have other wings or phases?

Yes. MahaRERA lists 5 other registrations of the same project, each with its own possession date: Satvam Hills A4 (P52100052106, possession 30 Apr 2027); SATVAM HILLS A5 (P52100052048, possession 24 Feb 2026); Satvam Hills A6 (P52100054456, possession 30 Oct 2027); Satvam Hills C4 (P52100055512, possession 30 Apr 2027); Satvam Hills C5 (PP1260002601969, possession 31 Aug 2029). Check that your agreement names the registration of your own wing.

How can I get updates if Symphony Satvam Hills B7's possession date changes?

The latest dates are on Symphony Satvam Hills B7's MahaRERA page (P52100053964). GharKundli's Kundli Watch sends a free WhatsApp update on Symphony Satvam Hills B7 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How big is the land of Symphony Satvam Hills B7?

According to GharKundli's check of MahaRERA records (updated October 2026), Symphony Satvam Hills B7 stands on 2,013 sq m of land (about 0.5 acres) and 255 sq m of recreational open space.

What is the track record of Symphony Satvam Hills B7's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Synergy Properties (a group of 3 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 14 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 5 months); 8 still being built, 6 past the promised date (typically 11 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Symphony Satvam Hills B7?

Google Maps has reviews of Symphony Satvam Hills B7 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Symphony Satvam Hills B7?

Symphony Satvam Hills B7 by SYMPHONY LANDMARKS LLP is in Paud, Pune, pincode 412108, Maharashtra, and is registered on MahaRERA as P52100053964, per GharKundli's check of MahaRERA records. Its land is filed as Gat no 316/A 316/B 316/C. GharKundli lists all 73 MahaRERA projects in Paud (412108).

When was Symphony Satvam Hills B7 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Symphony Satvam Hills B7 was registered on MahaRERA on 18 December 2023. GharKundli did not find a title report on the land on file there.

Does Symphony Satvam Hills B7 have any legal issues or court cases?

No court cases are listed for Symphony Satvam Hills B7 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Symphony Satvam Hills B7?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SYMPHONY LANDMARKS LLP, which has 1 other project registered on MahaRERA.

All projects with possession due in 2026 in Pune →

Other projects in Paud (412108)

All 73 projects in Paud (412108) →

Other projects by SYMPHONY LANDMARKS LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.