Skip to content
GharKundli

Marvel Gold - Phase I

by Swaroop Constructions Private Limited · Harijan Colony, Valmiki Nagar, Mumbai

Possession date of Marvel Gold - Phase I: 30 December 2021. This is the latest completion date the builder has filed on MahaRERA, and it has already passed.

Registered on MahaRERA under P51800006875. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2021) has passed.

GharKundli’s full report on Marvel Gold - Phase I

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800006875
Status
Lapsed (registration period ended)
Builder
Swaroop Constructions Private Limited
Location
Harijan Colony, Valmiki Nagar, Mumbai · 400078
Project type
Others
Registered on
16 Aug 2017
Completion date at registration
December 2021
Latest completion date
December 2021
Homes
440
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Marvel Gold - Phase I, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Petra Towers100%100%100%100%
Rehab Building100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Marvel Gold - Phase I every month.

Marvel Gold - Phase I: buildings, flats and land, as filed on MahaRERA

  • Buildings: Petra Towers (23 floors) · Rehab Building (20 floors)
  • Land: 7,647 sq m (about 1.9 acres) · sanctioned built-up 12,632 sq m · recreational space 496 sq m

Kundli Watch

Marvel Gold - Phase I: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Marvel Gold - Phase I

What is the possession date of Marvel Gold - Phase I?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Marvel Gold - Phase I in Harijan Colony, Valmiki Nagar, Mumbai is 30 December 2021. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Marvel Gold - Phase I?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Marvel Gold - Phase I's builder has filed on MahaRERA, the official one, is 30 December 2021, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Marvel Gold - Phase I?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Marvel Gold - Phase I in Harijan Colony, Valmiki Nagar, Mumbai is P51800006875.

Is Marvel Gold - Phase I registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Marvel Gold - Phase I is registered as P51800006875 and its status is "Lapsed (registration period ended)".

What is the construction status of Marvel Gold - Phase I?

According to GharKundli's check of MahaRERA records (updated November 2026), Marvel Gold - Phase I's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Marvel Gold - Phase I have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Marvel Gold - Phase I safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Marvel Gold - Phase I is registered on MahaRERA as P51800006875, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Marvel Gold - Phase I's possession date changes?

The latest dates are on Marvel Gold - Phase I's MahaRERA page (P51800006875). GharKundli's Kundli Watch sends a free WhatsApp update on Marvel Gold - Phase I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Marvel Gold - Phase I have?

According to GharKundli's check of MahaRERA records (updated November 2026), Marvel Gold - Phase I has 2 buildings filed: Petra Towers with 23 floors; Rehab Building with 20 floors.

How big is the land of Marvel Gold - Phase I?

According to GharKundli's check of MahaRERA records (updated November 2026), Marvel Gold - Phase I stands on 7,647 sq m of land (about 1.9 acres), with 12,632 sq m of sanctioned built-up area and 496 sq m of recreational open space.

Where is Marvel Gold - Phase I?

Marvel Gold - Phase I by Swaroop Constructions Private Limited is in Harijan Colony, Valmiki Nagar, Mumbai (pincode 400078), Maharashtra, and is registered on MahaRERA as P51800006875, per GharKundli's check of MahaRERA records.

How many homes are in Marvel Gold - Phase I?

According to GharKundli's check of MahaRERA records (updated November 2026), Marvel Gold - Phase I has 440 homes in 2 towers registered on MahaRERA.

When was Marvel Gold - Phase I registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Marvel Gold - Phase I was registered on MahaRERA on 16 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Marvel Gold - Phase I?

No court cases are listed for Marvel Gold - Phase I on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Marvel Gold - Phase I?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Swaroop Constructions Private Limited, which has 2 other projects registered on MahaRERA.

All projects in Bhandup West (400078) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.