Registered on MahaRERA under P51800000499. Status: Completed. Its completion date has moved from December 2018 to December 2019, 12 months later.

Source: GharKundli’s check of MahaRERA records, November 2026.

GharKundli’s full report on KABRA PRARTHNA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800000499
Status
Completed
Builder
KABRA ESTATE AND INVESTMENT CONSULTANTS
Location
JVPD Scheme, Mumbai · 400049
Project type
Residential / Group Housing
Registered on
18 Jul 2017
Completion date at registration
December 2018
Latest completion date
December 2019
Delay so far
12 months
Homes
38
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Kundli Watch

KABRA PRARTHNA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about KABRA PRARTHNA

Is KABRA PRARTHNA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), KABRA PRARTHNA is registered as P51800000499 and its status is "Completed".

Where is KABRA PRARTHNA?

KABRA PRARTHNA by KABRA ESTATE AND INVESTMENT CONSULTANTS is in JVPD Scheme, Mumbai (pincode 400049), near Juhu, Vileparle West, Andheri Railway Station, Maharashtra, and is registered on MahaRERA as P51800000499, per GharKundli's check of MahaRERA records.

When is possession of KABRA PRARTHNA due?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for KABRA PRARTHNA in JVPD Scheme, Mumbai is 31 December 2019 — 12 months later than 31 December 2018, the date given at registration.

Does KABRA PRARTHNA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

How many homes are in KABRA PRARTHNA?

According to GharKundli's check of MahaRERA records (updated November 2026), KABRA PRARTHNA has 38 homes in 1 tower registered on MahaRERA.

When was KABRA PRARTHNA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), KABRA PRARTHNA was registered on MahaRERA on 18 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on KABRA PRARTHNA?

No court cases are listed for KABRA PRARTHNA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of KABRA PRARTHNA?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is KABRA ESTATE AND INVESTMENT CONSULTANTS, which has 4 other projects registered on MahaRERA.

All projects in Juhu (400049) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.