Possession due in 2030 · Aurangabad
According to GharKundli's check of MahaRERA records, 8 housing projects in Aurangabad have a MahaRERA completion date in 2030, out of 78 Aurangabad projects GharKundli has read in detail so far.
The date is the latest completion date the builder has filed on MahaRERA, including MahaRERA’s automatic 4-month extension of August 2026 where it applies. “First promised” is the date given at registration. Completed projects are not listed. Open a project for its full MahaRERA record.
| Project | Where | Possession due (MahaRERA) | First promised | Complaints |
|---|---|---|---|---|
| OBEROI MANALI COMFORT MANALI VENTURES | Chhatrapati Sambhajinagar (MH) | 28 Feb 2030 | 31 Oct 2029 | 0 |
| ARHAM URBANIA ARHAM BUILDERS AND DEVELOPERS | Garkheda Parisar | 30 Apr 2030 | 31 Dec 2025 | 0 |
| T Three TAYAL BUSINESS PARK LLP | Mohalla Adalatroad | 30 Apr 2030 | 31 Dec 2029 | 0 |
| BELMONT VASTU AMBIKA VENTURES | Itkheda | 31 Dec 2030 | 31 Mar 2026 | 0 |
| NABHRAJ TRILOK HEIGHTS MHADA NABHRAJ BUILDERS AND DEVELOPERS PVT LTD | Shahnoorwadi | 31 Dec 2030 | same | 0 |
| PMAY U Tisgaon 227 A Unity Developers | Mauje Tisgaon | 31 Dec 2030 | 31 Dec 2025 | 0 |
| SEETA PARK LAXMAN KONDIA KALE | At Pisadevi | 31 Dec 2030 | 31 Mar 2024 | 0 |
| SHIV SRUSHTI SHIVTEJ BUILDERS & DEVELOPERS | Shendra Jahangir | 31 Dec 2030 | 31 Mar 2025 | 0 |
Other years in Aurangabad: 2026 (7) · 2027 (18) · 2028 (12) · 2029 (6) · 2031 (9)
Source: GharKundli’s check of MahaRERA records. More projects appear as GharKundli reads them.