Possession due in 2027 · Aurangabad
According to GharKundli's check of MahaRERA records, 18 housing projects in Aurangabad have a MahaRERA completion date in 2027, out of 78 Aurangabad projects GharKundli has read in detail so far.
The date is the latest completion date the builder has filed on MahaRERA, including MahaRERA’s automatic 4-month extension of August 2026 where it applies. “First promised” is the date given at registration. Completed projects are not listed. Open a project for its full MahaRERA record.
| Project | Where | Possession due (MahaRERA) | First promised | Complaints |
|---|---|---|---|---|
| SHRIRAM RESIDENCY UNIQUE BUILDCON | Bhavsingpura | 31 Mar 2027 | 15 Dec 2025 | 0 |
| SERENE TOWERS Narayani Realty | Shahanoorwadi | 29 Apr 2027 | 31 Dec 2025 | 1 |
| Amrut Sai Gold Star AMRUT SAI GOLD STAR | Kranti Chowk | 30 Apr 2027 | 30 Mar 2025 | 0 |
| GOKULDHAM GIRIRAJ DEVELOPERS | Chhatrapati Sambhajinagar Cantonment | 30 Apr 2027 | 31 Dec 2024 | 0 |
| RAJ ADITYA RAHUL BASWANT NANDGAWALI | Itkheda | 30 Apr 2027 | 24 Feb 2025 | 0 |
| SUNRISE VILLE AMAR BABASAHEB JADHAV | Waluj | 30 Apr 2027 | 30 Sep 2020 | 0 |
| UNITY PARK BAHETI LANDMARK | Near Mahada | 31 May 2027 | 30 Dec 2024 | 0 |
| Aakash Ganga Phase II Aakash Ganga Developers | Mouje-Nakshtrawadi | 21 Jun 2027 | 1 Oct 2025 | 0 |
| ATHARVA PARK PHASE - I SHIVSAI CONTRACTORS | Chhatrapati Sambhajinagar (MH) | 31 Jul 2027 | 31 Mar 2026 | 0 |
| Nandan Vatika Wing B Nandan Constructions | Osmanpura | 31 Jul 2027 | 31 Dec 2025 | 0 |
| SAI NISARG VIRAJ CONSTRUCTIONS | Deolai | 31 Jul 2027 | 31 Mar 2026 | 0 |
| SHRI GOVINDAM HEIGHTS SHREE VYANKATESHA INFRA | Satara Devlai | 31 Jul 2027 | 31 Mar 2026 | 1 |
| Kalyani Park Phase II Bharat Janardhan Kale | Pisadevi | 1 Aug 2027 | 1 Apr 2026 | 0 |
| Siddhi Ellora Business Park Advika Construction | Golwadi, Nagar-IV | 31 Aug 2027 | 26 Aug 2026 | 0 |
| SAI PRATIK NAGARI PRATIK DREAM HOME | Deolai | 30 Sep 2027 | 30 Mar 2023 | 0 |
| ELEMENTS ARIA PADMANABH BUILDERS | Shahnoorwadi | 31 Dec 2027 | 31 Dec 2025 | 0 |
| MANGALA HOMES NAHATA AND NIRMAL VENTURES LLP | Mouje Tisgaon, Chh Sambhajinagar | 31 Dec 2027 | same | 0 |
| Swastik Towers Hari Om Developers | Pisadevi, Aurangabad | 31 Dec 2027 | 27 Aug 2025 | 1 |
Other years in Aurangabad: 2026 (7) · 2028 (12) · 2029 (6) · 2030 (8) · 2031 (9)
Source: GharKundli’s check of MahaRERA records. More projects appear as GharKundli reads them.