SAI PRATIK NAGARI
by PRATIK DREAM HOME · Deolai, AurangabadAlso near Satara Parisar, War, Deohara
Possession date of SAI PRATIK NAGARI: 30 September 2027, moved from 30 March 2023 (50 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51500020695, and currently active. Its completion date has moved from March 2023 to September 2027: 50 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SAI PRATIK NAGARI?
How the possession date of SAI PRATIK NAGARI has moved
30 March 2023
Completion date given when the project was registered
29 March 2024
Extended at the builder's request (MahaRERA application EXT51500015445)
Reason the builder gave MahaRERA: “27 Units out of 80 Units are under construction. Customers prefer to purchase completed units instead of under construction units. After November 2022 sales inquiries are at lower side and hence there is delay in completing the project.”
31 March 2026
Extended at the builder's request (MahaRERA application EXT51500022967)
Reason the builder gave MahaRERA: “Completion Certificate not yet received and some units are under construction.”
31 May 2027
Extended at the builder's request (MahaRERA application EA01062621181)
Reason the builder gave MahaRERA:
“85% Work has been completed. Extension required to Complete balance project and Completion related Formalities. Customers prefer to purchase completed units instead of under construction units. After November 2022 sales inquiries are at low…” Read the full reason
“85% Work has been completed. Extension required to Complete balance project and Completion related Formalities. Customers prefer to purchase completed units instead of under construction units. After November 2022 sales inquiries are at lower side and hence there is delay in completing the project.”30 September 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SAI PRATIK NAGARI’s extension records on MahaRERA (P51500020695), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SAI PRATIK NAGARI
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51500020695
- Status
- Registered and active
- Builder
- PRATIK DREAM HOME
- Location
- Deolai, Aurangabad · 431005
- Project type
- Residential / Group Housing
- Registered on
- 3 May 2019
- Completion date at registration
- March 2023
- Latest completion date
- September 2027
- Delay so far
- 50 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 80
- Sold or booked
- 77%
- Towers
- 6
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SAI PRATIK NAGARI, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING B | 100% | 100% | 90% | 80% |
| BUILDING C | 100% | 100% | 90% | 80% |
| BUILDING D | 100% | 100% | 100% | 100% |
| BUILDING E | 100% | 100% | 100% | 100% |
| BUILDING F | 100% | 100% | 100% | 90% |
| BUILDING A | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING B: covers 3 floors
- BUILDING C: covers 5 floors
- BUILDING D: covers 3 floors
- BUILDING E: covers 2 floors
- BUILDING F: covers 5 floors
- BUILDING A: covers 2 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI PRATIK NAGARI every month.
SAI PRATIK NAGARI: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING B (3 floors, 20 units) · BUILDING C (5 floors, 16 units) · BUILDING D (3 floors, 20 units) · BUILDING E (2 floors, 8 units) · BUILDING F (5 floors, 8 units) · BUILDING A (2 floors, 8 units)
- Car parking: 80 covered
- Land: 6,000 sq m (about 1.5 acres) · sanctioned built-up 4,788 sq m · recreational space 600 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SAI PRATIK NAGARI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SAI PRATIK NAGARI: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SAI PRATIK NAGARI
What is the possession date of SAI PRATIK NAGARI?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAI PRATIK NAGARI in Deolai, Aurangabad is 30 September 2027 — 50 months later than 30 March 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SAI PRATIK NAGARI?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI PRATIK NAGARI's builder has filed on MahaRERA, the official one, is 30 September 2027, already 50 months later than the 30 March 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SAI PRATIK NAGARI extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI PRATIK NAGARI's builder applied to MahaRERA to extend the completion date 3 times: to 29 March 2024, giving the reason "27 Units out of 80 Units are under construction. Customers prefer to purchase completed units instead of under construction units. After November 2022 sales inquiries are at lower side and hence there is delay in completing the project."; to 31 March 2026, giving the reason "Completion Certificate not yet received and some units are under construction."; to 31 May 2027, giving the reason "85% Work has been completed. Extension required to Complete balance project and Completion related Formalities. Customers prefer to purchase completed units instead of under construction units. After November 2022 sales inquiries are at lower side and hence there is delay in completing the project.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of SAI PRATIK NAGARI?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAI PRATIK NAGARI in Deolai, Aurangabad is P51500020695.
Is SAI PRATIK NAGARI registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI PRATIK NAGARI is registered as P51500020695 and its status is "Registered and active".
What is the construction status of SAI PRATIK NAGARI?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI PRATIK NAGARI's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 6 towers. GharKundli's full report compares construction progress with the deadline.
Does SAI PRATIK NAGARI have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is SAI PRATIK NAGARI safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI PRATIK NAGARI is registered on MahaRERA as P51500020695, its completion date has moved 50 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SAI PRATIK NAGARI's possession date changes?
The latest dates are on SAI PRATIK NAGARI's MahaRERA page (P51500020695). GharKundli's Kundli Watch sends a free WhatsApp update on SAI PRATIK NAGARI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SAI PRATIK NAGARI have?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI PRATIK NAGARI has 6 buildings filed: BUILDING B with 3 floors and 20 units; BUILDING C with 5 floors and 16 units; BUILDING D with 3 floors and 20 units; BUILDING E with 2 floors and 8 units; BUILDING F with 5 floors and 8 units; BUILDING A with 2 floors and 8 units.
How much parking does SAI PRATIK NAGARI have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 80 covered car parking spaces for SAI PRATIK NAGARI.
How big is the land of SAI PRATIK NAGARI?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI PRATIK NAGARI stands on 6,000 sq m of land (about 1.5 acres), with 4,788 sq m of sanctioned built-up area and 600 sq m of recreational open space.
Where can I read reviews of SAI PRATIK NAGARI?
Google Maps has reviews of SAI PRATIK NAGARI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SAI PRATIK NAGARI?
SAI PRATIK NAGARI by PRATIK DREAM HOME is in Deolai, Aurangabad (pincode 431005), near Satara Parisar, War, Deohara, Maharashtra, and is registered on MahaRERA as P51500020695, per GharKundli's check of MahaRERA records.
How many homes are in SAI PRATIK NAGARI?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI PRATIK NAGARI has 80 homes in 6 towers registered on MahaRERA, and 77% of them are sold or booked.
When was SAI PRATIK NAGARI registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI PRATIK NAGARI was registered on MahaRERA on 3 May 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on SAI PRATIK NAGARI?
No court cases are listed for SAI PRATIK NAGARI on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SAI PRATIK NAGARI?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PRATIK DREAM HOME.
Check it yourself on MahaRERA
- How to check the possession date of SAI PRATIK NAGARI
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Aurangabad →
Other projects in Deolai
- SAI NISARG
- ARADHYA RESIDENCY
- SAIANANT TOWER
- ADINATH AANGAN PHASE 2
- ADINATH AANGAN PHASE 1
- VENKATESH RESIDENCY
- SAINEEL
- SAIKAMAL
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.