SAI NISARG
by VIRAJ CONSTRUCTIONS · Deolai, Aurangabad
Possession date of SAI NISARG: 31 July 2027, moved from 31 March 2026 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51500034864, and currently active. Its completion date has moved from March 2026 to July 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SAI NISARG?
How the possession date of SAI NISARG has moved
31 March 2026
Completion date given when the project was registered
31 March 2027
Extended at the builder's request (MahaRERA application EA18032620264)
Reason the builder gave MahaRERA:
“The development works of the project have been progressing; however, the completion of the project has been delayed due to unforeseen delays caused by labour and contractor-related issues. As a result, certain finishing and remaining constr…” Read the full reason
“The development works of the project have been progressing; however, the completion of the project has been delayed due to unforeseen delays caused by labour and contractor-related issues. As a result, certain finishing and remaining construction works could not be completed within the initially declared timeline. Out of the total 39 Row Houses in the project, we have successfully sold 23 units to allottees, and the remaining works for completion are in progress. We are taking all necessary measures to expedite construction and ensure timely delivery of all units. In view of the above, we h…”31 July 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SAI NISARG’s extension records on MahaRERA (P51500034864), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SAI NISARG
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51500034864
- Status
- Registered and active
- Builder
- VIRAJ CONSTRUCTIONS
- Location
- Deolai, Aurangabad · 431007
- Project type
- Residential / Group Housing
- Registered on
- 28 Apr 2022
- Completion date at registration
- March 2026
- Latest completion date
- July 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 39
- Sold or booked
- 69%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SAI NISARG, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| R.H. R-01 TO R.H. R-39 / SAI NISARG | 100% | 96% | 96% | 74% |
Commencement certificate (CC), as filed on MahaRERA
- R.H. R-01 TO R.H. R-39: covers 2 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI NISARG every month.
SAI NISARG: buildings, flats and land, as filed on MahaRERA
- Buildings: R.H. R-01 TO R.H. R-39 (2 floors, 39 units)
- Land: 3,512 sq m (about 0.9 acres) · sanctioned built-up 4,213 sq m · recreational space 326 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SAI NISARG →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SAI NISARG: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SAI NISARG
What is the possession date of SAI NISARG?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAI NISARG in Deolai, Aurangabad is 31 July 2027 — 12 months later than 31 March 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SAI NISARG?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI NISARG's builder has filed on MahaRERA, the official one, is 31 July 2027, already 12 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SAI NISARG extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI NISARG's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "The development works of the project have been progressing; however, the completion of the project has been delayed due to unforeseen delays caused by labour and contractor-related issues. As a result, certain finishing and remaining construction works could not be completed within the initially declared timeline. Out of the total 39 Row Houses in the project, we have successfully sold 23 units to allottees, and the remaining works for completion are in progress. We are taking all necessary measures to expedite construction and ensure timely delivery of all units. In view of the above, we h…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of SAI NISARG?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAI NISARG in Deolai, Aurangabad is P51500034864.
Is SAI NISARG registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI NISARG is registered as P51500034864 and its status is "Registered and active".
What is the construction status of SAI NISARG?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI NISARG's status on MahaRERA is "Registered and active". As filed by the builder, slab work on R.H. R-01 TO R.H. R-39 / SAI NISARG is 96% done and internal work 96%. GharKundli's full report compares construction progress with the deadline.
Does SAI NISARG have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is SAI NISARG safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI NISARG is registered on MahaRERA as P51500034864, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SAI NISARG's possession date changes?
The latest dates are on SAI NISARG's MahaRERA page (P51500034864). GharKundli's Kundli Watch sends a free WhatsApp update on SAI NISARG every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SAI NISARG have?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI NISARG has one building filed: R.H. R-01 TO R.H. R-39 with 2 floors and 39 units.
How big is the land of SAI NISARG?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI NISARG stands on 3,512 sq m of land (about 0.9 acres), with 4,213 sq m of sanctioned built-up area and 326 sq m of recreational open space.
Where can I read reviews of SAI NISARG?
Google Maps has reviews of SAI NISARG written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SAI NISARG?
SAI NISARG by VIRAJ CONSTRUCTIONS is in Deolai, Aurangabad (pincode 431007), Maharashtra, and is registered on MahaRERA as P51500034864, per GharKundli's check of MahaRERA records.
How many homes are in SAI NISARG?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI NISARG has 39 homes in 1 tower registered on MahaRERA, and 69% of them are sold or booked.
When was SAI NISARG registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI NISARG was registered on MahaRERA on 28 April 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on SAI NISARG?
No court cases are listed for SAI NISARG on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SAI NISARG?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VIRAJ CONSTRUCTIONS.
Check it yourself on MahaRERA
- How to check the possession date of SAI NISARG
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Aurangabad →
Other projects in Deolai
- SAI PRATIK NAGARI
- ARADHYA RESIDENCY
- SAIANANT TOWER
- ADINATH AANGAN PHASE 2
- ADINATH AANGAN PHASE 1
- VENKATESH RESIDENCY
- SAINEEL
- SAIKAMAL
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.