by AMRUT SAI GOLD STAR · Kranti Chowk, AurangabadAlso near War, Deohara, Kaler

Possession date of Amrut Sai Gold Star: 30 April 2027, moved from 30 March 2025 (25 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51500020039, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Amrut Sai Gold Star?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Amrut Sai Gold Star has moved

  1. 30 March 2025

    Completion date given when the project was registered

  2. 31 March 2026

    Extended at the builder's request (MahaRERA application EXT51500028123)

    Reason the builder gave MahaRERA:
    “We are requesting an extension for our project in MahaRERA due to the incorporation of two additional buildings, Wing A-6 and C-1, into the current development plan. The addition of these buildings requires extra time for planning, approval…” Read the full reason“We are requesting an extension for our project in MahaRERA due to the incorporation of two additional buildings, Wing A-6 and C-1, into the current development plan. The addition of these buildings requires extra time for planning, approvals, and construction, which is the main reason for requesting an extension to the project timeline.”
  3. 30 April 2027

    Extended at the builder's request (MahaRERA application EA28052621135)

    Reason the builder gave MahaRERA:
    “Additional time is required for obtaining the Occupancy Certificate from the Municipal Authority, for which the application has already been duly submitted (inward). Further, time is also required for execution of agreements with the allott…” Read the full reason“Additional time is required for obtaining the Occupancy Certificate from the Municipal Authority, for which the application has already been duly submitted (inward). Further, time is also required for execution of agreements with the allottees/prospective purchasers and completion of related formalities. Hence, extension of the RERA registration is requested.”

Source: Amrut Sai Gold Star’s extension records on MahaRERA (P51500020039), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Amrut Sai Gold Star

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51500020039
Status
Registered and active
Builder
AMRUT SAI GOLD STAR
Location
Kranti Chowk, Aurangabad · 431005
Project type
Residential / Group Housing
Registered on
19 Mar 2019
Completion date at registration
March 2025
Latest completion date
April 2027
Delay so far
25 months
Homes
156
Sold or booked
89%
Towers
9
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Amrut Sai Gold Star, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing A-1100%100%100%100%
Wing A-2100%100%100%100%
Wing A-3100%100%100%100%
Wing A-4100%100%100%100%
Wing A-5100%100%100%100%
Wing B-1100%100%100%100%
Wing B-2100%100%100%100%
Wing A-6100%100%100%100%
Wing C-1100%0%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Wing A-1: covers 5 floors
  • Wing A-2: covers 5 floors
  • Wing A-3: covers 5 floors
  • Wing A-4: covers 5 floors
  • Wing A-5: covers 5 floors
  • Wing B-1: covers 5 floors
  • Wing B-2: covers 4 floors
  • Wing A-6: covers 5 floors
  • Wing C-1: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Amrut Sai Gold Star every month.

Amrut Sai Gold Star: buildings, flats and land, as filed on MahaRERA

  • Buildings: Wing A-1 (5 floors, 16 units) · Wing A-2 (5 floors, 16 units) · Wing A-3 (5 floors, 16 units) · Wing A-4 (5 floors, 16 units) · Wing A-5 (5 floors, 16 units) · Wing B-1 (5 floors, 16 units) · Wing B-2 (4 floors, 16 units) · Wing A-6 (5 floors, 16 units) · and 1 more
  • Car parking: 39 covered
  • Land: 7,144 sq m (about 1.8 acres) · sanctioned built-up 6,364 sq m · recreational space 714 sq m

The builder’s record and reviews

Amrut SAI Gold Star has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 7 months late). No complaints on MahaRERA.

Read Google reviews of Amrut Sai Gold Star →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Amrut Sai Gold Star: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Amrut Sai Gold Star

What is the possession date of Amrut Sai Gold Star?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Amrut Sai Gold Star in Kranti Chowk, Aurangabad is 30 April 2027 — 25 months later than 30 March 2025, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Amrut Sai Gold Star?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Amrut Sai Gold Star's builder has filed on MahaRERA, the official one, is 30 April 2027, already 25 months later than the 30 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Amrut Sai Gold Star extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Amrut Sai Gold Star's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2026, giving the reason "We are requesting an extension for our project in MahaRERA due to the incorporation of two additional buildings, Wing A-6 and C-1, into the current development plan. The addition of these buildings requires extra time for planning, approvals, and construction, which is the main reason for requesting an extension to the project timeline."; to 30 April 2027, giving the reason "Additional time is required for obtaining the Occupancy Certificate from the Municipal Authority, for which the application has already been duly submitted (inward). Further, time is also required for execution of agreements with the allottees/prospective purchasers and completion of related formalities. Hence, extension of the RERA registration is requested.".

What is the RERA number of Amrut Sai Gold Star?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Amrut Sai Gold Star in Kranti Chowk, Aurangabad is P51500020039.

Is Amrut Sai Gold Star registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Amrut Sai Gold Star is registered as P51500020039 and its status is "Registered and active".

What is the construction status of Amrut Sai Gold Star?

According to GharKundli's check of MahaRERA records (updated October 2026), Amrut Sai Gold Star's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 9 towers. GharKundli's full report compares construction progress with the deadline.

Does Amrut Sai Gold Star have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Amrut Sai Gold Star safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Amrut Sai Gold Star is registered on MahaRERA as P51500020039, its completion date has moved 25 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Amrut Sai Gold Star's possession date changes?

The latest dates are on Amrut Sai Gold Star's MahaRERA page (P51500020039). GharKundli's Kundli Watch sends a free WhatsApp update on Amrut Sai Gold Star every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Amrut Sai Gold Star have?

According to GharKundli's check of MahaRERA records (updated October 2026), Amrut Sai Gold Star has 9 buildings filed: Wing A-1 with 5 floors and 16 units; Wing A-2 with 5 floors and 16 units; Wing A-3 with 5 floors and 16 units; Wing A-4 with 5 floors and 16 units; Wing A-5 with 5 floors and 16 units; Wing B-1 with 5 floors and 16 units; and 3 more.

How much parking does Amrut Sai Gold Star have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 39 covered car parking spaces for Amrut Sai Gold Star.

How big is the land of Amrut Sai Gold Star?

According to GharKundli's check of MahaRERA records (updated October 2026), Amrut Sai Gold Star stands on 7,144 sq m of land (about 1.8 acres), with 6,364 sq m of sanctioned built-up area and 714 sq m of recreational open space.

What is the track record of Amrut Sai Gold Star's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Amrut SAI Gold Star has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 7 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Amrut Sai Gold Star?

Google Maps has reviews of Amrut Sai Gold Star written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Amrut Sai Gold Star?

Amrut Sai Gold Star by AMRUT SAI GOLD STAR is in Kranti Chowk, Aurangabad (pincode 431005), near War, Deohara, Kaler, Maharashtra, and is registered on MahaRERA as P51500020039, per GharKundli's check of MahaRERA records.

How many homes are in Amrut Sai Gold Star?

According to GharKundli's check of MahaRERA records (updated October 2026), Amrut Sai Gold Star has 156 homes in 9 towers registered on MahaRERA, and 89% of them are sold or booked.

When was Amrut Sai Gold Star registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Amrut Sai Gold Star was registered on MahaRERA on 19 March 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on Amrut Sai Gold Star?

No court cases are listed for Amrut Sai Gold Star on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Amrut Sai Gold Star?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AMRUT SAI GOLD STAR, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Aurangabad →

Other projects in pincode 431005

All 107 projects in Kranti Chowk (431005) →

Other projects by AMRUT SAI GOLD STAR

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.