Hiranya Enclave
by Rushikesh Tanaji Chavan · Sun City B/H Best Prize Mall, AurangabadAlso near Nodal Delivery Center, Chikalthana Industrial Area
Possession date of Hiranya Enclave: 30 April 2028, moved from 26 July 2022 (65 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51500018267, and currently active. Its completion date has moved from July 2022 to April 2028: 65 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Hiranya Enclave?
How the possession date of Hiranya Enclave has moved
26 July 2022
Completion date given when the project was registered
24 July 2023
Extended at the builder's request (MahaRERA application EXT51500013527)
Reason the builder gave MahaRERA: “Due to post COVID market situation there was very less booking/sale of the apartment.. Hence there was a break in construction for approximate one and half year...”
31 December 2025
Extended at the builder's request (MahaRERA application EXT51500017940)
Reason the builder gave MahaRERA: “COVID Less Booking”
31 December 2027
Extended at the builder's request (MahaRERA application EA22022619947)
Reason the builder gave MahaRERA: “Almost all work is done. Only Lift Installation is remaining. Booking done is very less hence extension is required for sale, Society formation and obtaining occupancy certificate.”
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Hiranya Enclave’s extension records on MahaRERA (P51500018267), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Hiranya Enclave
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51500018267
- Status
- Registered and active
- Builder
- Rushikesh Tanaji Chavan
- Location
- Sun City B/H Best Prize Mall, Aurangabad · 431005
- Project type
- Residential / Group Housing
- Registered on
- 22 Oct 2018
- Completion date at registration
- July 2022
- Latest completion date
- April 2028
- Delay so far
- 65 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 36
- Sold or booked
- 11%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Hiranya Enclave, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Hiranya Enclave | 100% | 100% | 100% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Hiranya Enclave: covers 0 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Hiranya Enclave every month.
Hiranya Enclave: buildings, flats and land, as filed on MahaRERA
- Buildings: Hiranya Enclave (6 floors, 37 units)
- Car parking: 1 covered, 12 open
- Land: 1,031 sq m (about 0.3 acres) · sanctioned built-up 784 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Hiranya Enclave →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Hiranya Enclave: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Hiranya Enclave
What is the possession date of Hiranya Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Hiranya Enclave in Sun City B/H Best Prize Mall, Aurangabad is 30 April 2028 — 65 months later than 26 July 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Hiranya Enclave?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Hiranya Enclave's builder has filed on MahaRERA, the official one, is 30 April 2028, already 65 months later than the 26 July 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Hiranya Enclave extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Hiranya Enclave's builder applied to MahaRERA to extend the completion date 3 times: to 24 July 2023, giving the reason "Due to post COVID market situation there was very less booking/sale of the apartment.. Hence there was a break in construction for approximate one and half year..."; to 31 December 2025, giving the reason "COVID Less Booking"; to 31 December 2027, giving the reason "Almost all work is done. Only Lift Installation is remaining. Booking done is very less hence extension is required for sale, Society formation and obtaining occupancy certificate.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Hiranya Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Hiranya Enclave in Sun City B/H Best Prize Mall, Aurangabad is P51500018267.
Is Hiranya Enclave registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Hiranya Enclave is registered as P51500018267 and its status is "Registered and active".
What is the construction status of Hiranya Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), Hiranya Enclave's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Hiranya Enclave is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Hiranya Enclave have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Hiranya Enclave safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Hiranya Enclave is registered on MahaRERA as P51500018267, its completion date has moved 65 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Hiranya Enclave's possession date changes?
The latest dates are on Hiranya Enclave's MahaRERA page (P51500018267). GharKundli's Kundli Watch sends a free WhatsApp update on Hiranya Enclave every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Hiranya Enclave have?
According to GharKundli's check of MahaRERA records (updated October 2026), Hiranya Enclave has one building filed: Hiranya Enclave with 6 floors and 37 units.
How much parking does Hiranya Enclave have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered and 12 open car parking spaces for Hiranya Enclave.
How big is the land of Hiranya Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), Hiranya Enclave stands on 1,031 sq m of land (about 0.3 acres), with 784 sq m of sanctioned built-up area.
Where can I read reviews of Hiranya Enclave?
Google Maps has reviews of Hiranya Enclave written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Hiranya Enclave?
Hiranya Enclave by Rushikesh Tanaji Chavan is in Sun City B/H Best Prize Mall, Aurangabad (pincode 431005), near Nodal Delivery Center, Chikalthana Industrial Area, Maharashtra, and is registered on MahaRERA as P51500018267, per GharKundli's check of MahaRERA records.
How many homes are in Hiranya Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), Hiranya Enclave has 36 homes in 1 tower registered on MahaRERA, and 11% of them are sold or booked.
When was Hiranya Enclave registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Hiranya Enclave was registered on MahaRERA on 22 October 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on Hiranya Enclave?
No court cases are listed for Hiranya Enclave on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Hiranya Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Rushikesh Tanaji Chavan.
Check it yourself on MahaRERA
- How to check the possession date of Hiranya Enclave
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Aurangabad →
Other projects in Aurangabad
- NABHRAJ TRILOK HEIGHTS MHADA
- PARAM SUVARNVASTU
- KHINVANSARA AURA
- BUSINESS TRIANGLE
- Siddhi Ellora Business Park
- PRASSANA HIGH CLASS CITY PHASE - I
- HORIZON
- Gaia Carnival Apartment Phase II
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.