Gaia Carnival Apartment Phase II

by Zambad Disha Pride Infrastructure LLP · Chhatrapati Sambhajinagar Cantonment, Aurangabad

Possession date of Gaia Carnival Apartment Phase II: 30 April 2029, moved from 31 December 2025 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51500032777, and currently active. Its completion date has moved from December 2025 to April 2029: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Gaia Carnival Apartment Phase II?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Gaia Carnival Apartment Phase II has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 31 December 2028

    Extended at the builder's request (MahaRERA application EA19012619493)

    Reason the builder gave MahaRERA:
    “The registered project comprises row house building structures. The delay in the project has occurred due to changes in planning, pursuant to which the Commencement Certificate (CC) was obtained from the respective authority in August 2024.…” Read the full reason“The registered project comprises row house building structures. The delay in the project has occurred due to changes in planning, pursuant to which the Commencement Certificate (CC) was obtained from the respective authority in August 2024. The said changes and approvals have been duly updated on the MahaRERA portal. Further, no bookings have been taken for the project till date. In view of the above circumstances, we hereby request an extension of the project completion timeline up to 31 December 2028.”
  3. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Gaia Carnival Apartment Phase II’s extension records on MahaRERA (P51500032777), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Gaia Carnival Apartment Phase II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51500032777
Status
Registered and active
Builder
Zambad Disha Pride Infrastructure LLP
Location
Chhatrapati Sambhajinagar Cantonment, Aurangabad · 431002
Project type
Residential / Group Housing
Registered on
29 Jan 2022
Completion date at registration
December 2025
Latest completion date
April 2029
Delay so far
36 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
12
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of Gaia Carnival Apartment Phase II, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Signature 12100%75%53%0%

Commencement certificate (CC), as filed on MahaRERA

  • Signature 12: covers 3 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Gaia Carnival Apartment Phase II every month.

Gaia Carnival Apartment Phase II: buildings, flats and land, as filed on MahaRERA

  • Buildings: Signature 12 (7 floors, 12 units)
  • Car parking: 1 covered
  • Land: 1,016 sq m (about 0.3 acres) · sanctioned built-up 1,725 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Gaia Carnival Apartment Phase II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Gaia Carnival Apartment Phase II: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Gaia Carnival Apartment Phase II

What is the possession date of Gaia Carnival Apartment Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Gaia Carnival Apartment Phase II in Chhatrapati Sambhajinagar Cantonment, Aurangabad is 30 April 2029 — 36 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Gaia Carnival Apartment Phase II?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Gaia Carnival Apartment Phase II's builder has filed on MahaRERA, the official one, is 30 April 2029, already 36 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Gaia Carnival Apartment Phase II extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Gaia Carnival Apartment Phase II's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "The registered project comprises row house building structures. The delay in the project has occurred due to changes in planning, pursuant to which the Commencement Certificate (CC) was obtained from the respective authority in August 2024. The said changes and approvals have been duly updated on the MahaRERA portal. Further, no bookings have been taken for the project till date. In view of the above circumstances, we hereby request an extension of the project completion timeline up to 31 December 2028.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Gaia Carnival Apartment Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Gaia Carnival Apartment Phase II in Chhatrapati Sambhajinagar Cantonment, Aurangabad is P51500032777.

Is Gaia Carnival Apartment Phase II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Gaia Carnival Apartment Phase II is registered as P51500032777 and its status is "Registered and active".

What is the construction status of Gaia Carnival Apartment Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), Gaia Carnival Apartment Phase II's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Signature 12 is 75% done and internal work 53%. GharKundli's full report compares construction progress with the deadline.

Does Gaia Carnival Apartment Phase II have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Gaia Carnival Apartment Phase II safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Gaia Carnival Apartment Phase II is registered on MahaRERA as P51500032777, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Gaia Carnival Apartment Phase II have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Gaia Carnival Apartment Phase I (P51500032793, possession 31 Dec 2025). Check that your agreement names the registration of your own wing.

How can I get updates if Gaia Carnival Apartment Phase II's possession date changes?

The latest dates are on Gaia Carnival Apartment Phase II's MahaRERA page (P51500032777). GharKundli's Kundli Watch sends a free WhatsApp update on Gaia Carnival Apartment Phase II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Gaia Carnival Apartment Phase II have?

According to GharKundli's check of MahaRERA records (updated October 2026), Gaia Carnival Apartment Phase II has one building filed: Signature 12 with 7 floors and 12 units.

How much parking does Gaia Carnival Apartment Phase II have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered car parking spaces for Gaia Carnival Apartment Phase II.

How big is the land of Gaia Carnival Apartment Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), Gaia Carnival Apartment Phase II stands on 1,016 sq m of land (about 0.3 acres), with 1,725 sq m of sanctioned built-up area.

Where can I read reviews of Gaia Carnival Apartment Phase II?

Google Maps has reviews of Gaia Carnival Apartment Phase II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Gaia Carnival Apartment Phase II?

Gaia Carnival Apartment Phase II by Zambad Disha Pride Infrastructure LLP is in Chhatrapati Sambhajinagar Cantonment, Aurangabad (pincode 431002), Maharashtra, and is registered on MahaRERA as P51500032777, per GharKundli's check of MahaRERA records.

How many homes are in Gaia Carnival Apartment Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), Gaia Carnival Apartment Phase II has 12 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was Gaia Carnival Apartment Phase II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Gaia Carnival Apartment Phase II was registered on MahaRERA on 29 January 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on Gaia Carnival Apartment Phase II?

No court cases are listed for Gaia Carnival Apartment Phase II on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Gaia Carnival Apartment Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Zambad Disha Pride Infrastructure LLP, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2029 in Aurangabad →

Other projects in pincode 431002

All 57 projects in Chhatrapati Sambhajinagar Cantonment (431002) →

Other projects by Zambad Disha Pride Infrastructure LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.