GOKULDHAM
by GIRIRAJ DEVELOPERS · Chhatrapati Sambhajinagar Cantonment, Aurangabad
Possession date of GOKULDHAM: 30 April 2027, moved from 31 December 2024 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51500030191, and currently active. Its completion date has moved from December 2024 to April 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about GOKULDHAM?
How the possession date of GOKULDHAM has moved
31 December 2024
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA16092502607)
Reason the builder gave MahaRERA:
“We have sold 11 Row House Units till date and also given possession of the units... Sale Deed First Page Index II Attached For Ref. And also possession letters also attached for ref. So request you please grant the extension till 31/12/2026…” Read the full reason
“We have sold 11 Row House Units till date and also given possession of the units... Sale Deed First Page Index II Attached For Ref. And also possession letters also attached for ref. So request you please grant the extension till 31/12/2026. This is due to technical issues we required extra... We have already executed the final individual conveyance deed in fevor of allottees and also given them the possession of the units... due to technical issue the project is delayed completion so we request please grant the extension.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: GOKULDHAM’s extension records on MahaRERA (P51500030191), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on GOKULDHAM
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51500030191
- Status
- Registered and active
- Builder
- GIRIRAJ DEVELOPERS
- Location
- Chhatrapati Sambhajinagar Cantonment, Aurangabad · 431002
- Project type
- Residential / Group Housing
- Registered on
- 5 Aug 2021
- Completion date at registration
- December 2024
- Latest completion date
- April 2027
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 32
- Sold or booked
- 34%
- Towers
- 5
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of GOKULDHAM, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ROW HOUSE NO 1 TO 6 | 100% | 100% | 100% | 100% |
| ROW HOUSE NO 7 TO 15 | 100% | 100% | 100% | 100% |
| ROW HOUSE 16 TO 23 | 100% | 100% | 100% | 100% |
| ROW HOUSE 24 TO 30 | 100% | 100% | 100% | 100% |
| ROW HOUSE 31 AND 32 | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- ROW HOUSE NO 1 TO 6: covers 2 floors
- ROW HOUSE NO 7 TO 15: covers 2 floors
- ROW HOUSE 16 TO 23: covers 2 floors
- ROW HOUSE 24 TO 30: covers 2 floors
- ROW HOUSE 31 AND 32: covers 2 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on GOKULDHAM every month.
GOKULDHAM: buildings, flats and land, as filed on MahaRERA
- Buildings: ROW HOUSE NO 1 TO 6 (2 floors, 6 units) · ROW HOUSE NO 7 TO 15 (2 floors, 9 units) · ROW HOUSE 16 TO 23 (2 floors, 8 units) · ROW HOUSE 24 TO 30 (2 floors, 7 units) · ROW HOUSE 31 AND 32 (2 floors, 2 units)
- Land: 3,840 sq m (about 0.9 acres) · sanctioned built-up 2,451 sq m · recreational space 385 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of GOKULDHAM →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
GOKULDHAM: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about GOKULDHAM
What is the possession date of GOKULDHAM?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GOKULDHAM in Chhatrapati Sambhajinagar Cantonment, Aurangabad is 30 April 2027 — 24 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for GOKULDHAM?
Builders and listing sites often quote an earlier "target" date for handover. The completion date GOKULDHAM's builder has filed on MahaRERA, the official one, is 30 April 2027, already 24 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of GOKULDHAM extended?
According to GharKundli's check of MahaRERA records (updated October 2026), GOKULDHAM's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "We have sold 11 Row House Units till date and also given possession of the units... Sale Deed First Page Index II Attached For Ref. And also possession letters also attached for ref. So request you please grant the extension till 31/12/2026. This is due to technical issues we required extra... We have already executed the final individual conveyance deed in fevor of allottees and also given them the possession of the units... due to technical issue the project is delayed completion so we request please grant the extension.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of GOKULDHAM?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GOKULDHAM in Chhatrapati Sambhajinagar Cantonment, Aurangabad is P51500030191.
Is GOKULDHAM registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GOKULDHAM is registered as P51500030191 and its status is "Registered and active".
What is the construction status of GOKULDHAM?
According to GharKundli's check of MahaRERA records (updated October 2026), GOKULDHAM's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 5 towers. GharKundli's full report compares construction progress with the deadline.
Does GOKULDHAM have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is GOKULDHAM safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), GOKULDHAM is registered on MahaRERA as P51500030191, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if GOKULDHAM's possession date changes?
The latest dates are on GOKULDHAM's MahaRERA page (P51500030191). GharKundli's Kundli Watch sends a free WhatsApp update on GOKULDHAM every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does GOKULDHAM have?
According to GharKundli's check of MahaRERA records (updated October 2026), GOKULDHAM has 5 buildings filed: ROW HOUSE NO 1 TO 6 with 2 floors and 6 units; ROW HOUSE NO 7 TO 15 with 2 floors and 9 units; ROW HOUSE 16 TO 23 with 2 floors and 8 units; ROW HOUSE 24 TO 30 with 2 floors and 7 units; ROW HOUSE 31 AND 32 with 2 floors and 2 units.
How big is the land of GOKULDHAM?
According to GharKundli's check of MahaRERA records (updated October 2026), GOKULDHAM stands on 3,840 sq m of land (about 0.9 acres), with 2,451 sq m of sanctioned built-up area and 385 sq m of recreational open space.
Where can I read reviews of GOKULDHAM?
Google Maps has reviews of GOKULDHAM written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is GOKULDHAM?
GOKULDHAM by GIRIRAJ DEVELOPERS is in Chhatrapati Sambhajinagar Cantonment, Aurangabad (pincode 431002), Maharashtra, and is registered on MahaRERA as P51500030191, per GharKundli's check of MahaRERA records.
How many homes are in GOKULDHAM?
According to GharKundli's check of MahaRERA records (updated October 2026), GOKULDHAM has 32 homes in 5 towers registered on MahaRERA, and 34% of them are sold or booked.
When was GOKULDHAM registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GOKULDHAM was registered on MahaRERA on 5 August 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on GOKULDHAM?
No court cases are listed for GOKULDHAM on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of GOKULDHAM?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GIRIRAJ DEVELOPERS, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of GOKULDHAM
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Aurangabad →
Other projects in pincode 431002
- Gaia Carnival Apartment Phase II
- BELMONT
- SHRI GOVINDAM HEIGHTS
- SAINATH VIHAR
- PMAY U PADEGAON
- SAI NAKSHATRA
- PARAM SUVARNVALLEY
- NABHRAJ TRILOK HEIGHTS MHADA
Other projects by GIRIRAJ DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.