Aakash Ganga Phase II
by Aakash Ganga Developers · Mouje-Nakshtrawadi, Aurangabad
Possession date of Aakash Ganga Phase II: 21 June 2027, moved from 1 October 2025 (16 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51500054973, and currently active. Its completion date has moved from October 2025 to June 2027: 16 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Aakash Ganga Phase II?
How the possession date of Aakash Ganga Phase II has moved
1 October 2025
Completion date given when the project was registered
21 February 2027
Extended at the builder's request (MahaRERA application EA08092502533)
Reason the builder gave MahaRERA:
“We have encountered unforeseen delays in the completion of the project, primarily due to a difference between the demand we had initially anticipated during the registration process and the actual market response observed after commencement…” Read the full reason
“We have encountered unforeseen delays in the completion of the project, primarily due to a difference between the demand we had initially anticipated during the registration process and the actual market response observed after commencement. At the time of registration, the original project timeline was based on our comprehensive assessment of expected demand. However, as the project progressed, it became clear that the market response was not aligned with our initial projections. This variance in demand has led to several adjustments in our construction schedule, resulting in a revised and…”21 June 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Aakash Ganga Phase II’s extension records on MahaRERA (P51500054973), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Aakash Ganga Phase II
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Aakash Ganga Phase IP51500045306 · possession 30 Apr 2027
- MahaRERA registration
- P51500054973
- Status
- Registered and active
- Builder
- Aakash Ganga Developers
- Location
- Mouje-Nakshtrawadi, Aurangabad · 431005
- Project type
- Residential / Group Housing
- Registered on
- 21 Feb 2024
- Completion date at registration
- October 2025
- Latest completion date
- June 2027
- Delay so far
- 16 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 12
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Aakash Ganga Phase II, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Block - C / Block - C | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Block - C: covers 2 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aakash Ganga Phase II every month.
Aakash Ganga Phase II: buildings, flats and land, as filed on MahaRERA
- Buildings: Block - C (2 floors, 12 units)
- Land: 3,712 sq m (about 0.9 acres) · sanctioned built-up 930 sq m
The builder’s record and reviews
Aakash Ganga Developers (a group of 4 linked companies) has 6 projects on MahaRERA since 2019, this one included. Of the 6 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 19 months); 4 still being built, 2 past the promised date (typically 14 months late). No complaints on MahaRERA.
Read Google reviews of Aakash Ganga Phase II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Aakash Ganga Phase II: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Aakash Ganga Phase II
What is the possession date of Aakash Ganga Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Aakash Ganga Phase II in Mouje-Nakshtrawadi, Aurangabad is 21 June 2027 — 16 months later than 1 October 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Aakash Ganga Phase II?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Aakash Ganga Phase II's builder has filed on MahaRERA, the official one, is 21 June 2027, already 16 months later than the 1 October 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Aakash Ganga Phase II extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Ganga Phase II's builder applied to MahaRERA to extend the completion date once: to 21 February 2027, giving the reason "We have encountered unforeseen delays in the completion of the project, primarily due to a difference between the demand we had initially anticipated during the registration process and the actual market response observed after commencement. At the time of registration, the original project timeline was based on our comprehensive assessment of expected demand. However, as the project progressed, it became clear that the market response was not aligned with our initial projections. This variance in demand has led to several adjustments in our construction schedule, resulting in a revised and…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Aakash Ganga Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Aakash Ganga Phase II in Mouje-Nakshtrawadi, Aurangabad is P51500054973.
Is Aakash Ganga Phase II registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Ganga Phase II is registered as P51500054973 and its status is "Registered and active".
What is the construction status of Aakash Ganga Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Ganga Phase II's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Block - C / Block - C is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Aakash Ganga Phase II have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Aakash Ganga Phase II safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Ganga Phase II is registered on MahaRERA as P51500054973, its completion date has moved 16 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Aakash Ganga Phase II have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Aakash Ganga Phase I (P51500045306, possession 30 Apr 2027). Check that your agreement names the registration of your own wing.
How can I get updates if Aakash Ganga Phase II's possession date changes?
The latest dates are on Aakash Ganga Phase II's MahaRERA page (P51500054973). GharKundli's Kundli Watch sends a free WhatsApp update on Aakash Ganga Phase II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Aakash Ganga Phase II have?
According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Ganga Phase II has one building filed: Block - C with 2 floors and 12 units.
How big is the land of Aakash Ganga Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Ganga Phase II stands on 3,712 sq m of land (about 0.9 acres), with 930 sq m of sanctioned built-up area.
What is the track record of Aakash Ganga Phase II's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Ganga Developers (a group of 4 linked companies) has 6 projects on MahaRERA since 2019, this one included. Of the 6 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 19 months); 4 still being built, 2 past the promised date (typically 14 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Aakash Ganga Phase II?
Google Maps has reviews of Aakash Ganga Phase II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Aakash Ganga Phase II?
Aakash Ganga Phase II by Aakash Ganga Developers is in Mouje-Nakshtrawadi, Aurangabad (pincode 431005), Maharashtra, and is registered on MahaRERA as P51500054973, per GharKundli's check of MahaRERA records.
How many homes are in Aakash Ganga Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Ganga Phase II has 12 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was Aakash Ganga Phase II registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Ganga Phase II was registered on MahaRERA on 21 February 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on Aakash Ganga Phase II?
No court cases are listed for Aakash Ganga Phase II on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Aakash Ganga Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Aakash Ganga Developers, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Aakash Ganga Phase II
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Aurangabad →
Other projects in Aurangabad
- NABHRAJ TRILOK HEIGHTS MHADA
- PARAM SUVARNVASTU
- KHINVANSARA AURA
- BUSINESS TRIANGLE
- Siddhi Ellora Business Park
- PRASSANA HIGH CLASS CITY PHASE - I
- HORIZON
- Gaia Carnival Apartment Phase II
Other projects by Aakash Ganga Developers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.