SHIV SRUSHTI
by SHIVTEJ BUILDERS & DEVELOPERS · Shendra Jahangir, Aurangabad
Possession date of SHIV SRUSHTI: 31 December 2030, moved from 31 March 2025 (69 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51500030274, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SHIV SRUSHTI?
How the possession date of SHIV SRUSHTI has moved
31 March 2025
Completion date given when the project was registered
31 December 2030
Extended at the builder's request (MahaRERA application EA25082502435)
Reason the builder gave MahaRERA:
“To, The Maharashtra Real Estate Regulatory Authority (MahaRERA) Mumbai Subject: Application for Project Extension under Section 7(3) of RERA Reference: RERA Project Registration Number – P51500030274 Respected Sir, We, the partners of M/s S…” Read the full reason
“To, The Maharashtra Real Estate Regulatory Authority (MahaRERA) Mumbai Subject: Application for Project Extension under Section 7(3) of RERA Reference: RERA Project Registration Number – P51500030274 Respected Sir, We, the partners of M/s Shivtej Builders & Developers, hereby submit our request for an extension of the project under Section 7(3) of RERA. Due to unforeseen circumstances, we have been unable to complete the project within the stipulated timeframe. Our project comprises four phases, with each phase consisting of six row houses, totaling 24 row houses. As of now, Phase A is 90%…”
Source: SHIV SRUSHTI’s extension records on MahaRERA (P51500030274), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHIV SRUSHTI
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51500030274
- Status
- Registered and active
- Builder
- SHIVTEJ BUILDERS & DEVELOPERS
- Location
- Shendra Jahangir, Aurangabad · 431007
- Project type
- Residential / Group Housing
- Registered on
- 15 Aug 2021
- Completion date at registration
- March 2025
- Latest completion date
- December 2030
- Delay so far
- 69 months
- Homes
- 24
- Sold or booked
- 8%
- Towers
- 4
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SHIV SRUSHTI, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Block A | 100% | 100% | 100% | 20% |
| Block B | 100% | 100% | 100% | 20% |
| Block C | 100% | 100% | 100% | 20% |
| Block D | 100% | 100% | 100% | 20% |
Commencement certificate (CC), as filed on MahaRERA
- Block A: covers 3 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHIV SRUSHTI every month.
SHIV SRUSHTI: buildings, flats and land, as filed on MahaRERA
- Buildings: Block A (3 floors, 6 units) · Block B (3 floors, 6 units) · Block C (3 floors, 6 units) · Block D (3 floors, 6 units)
- Land: 4,701 sq m (about 1.2 acres) · sanctioned built-up 2,096 sq m · recreational space 2,798 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SHIV SRUSHTI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHIV SRUSHTI: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHIV SRUSHTI
What is the possession date of SHIV SRUSHTI?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHIV SRUSHTI in Shendra Jahangir, Aurangabad is 31 December 2030 — 69 months later than 31 March 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SHIV SRUSHTI?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHIV SRUSHTI's builder has filed on MahaRERA, the official one, is 31 December 2030, already 69 months later than the 31 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SHIV SRUSHTI extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIV SRUSHTI's builder applied to MahaRERA to extend the completion date once: to 31 December 2030, giving the reason "To, The Maharashtra Real Estate Regulatory Authority (MahaRERA) Mumbai Subject: Application for Project Extension under Section 7(3) of RERA Reference: RERA Project Registration Number – P51500030274 Respected Sir, We, the partners of M/s Shivtej Builders & Developers, hereby submit our request for an extension of the project under Section 7(3) of RERA. Due to unforeseen circumstances, we have been unable to complete the project within the stipulated timeframe. Our project comprises four phases, with each phase consisting of six row houses, totaling 24 row houses. As of now, Phase A is 90%…".
What is the RERA number of SHIV SRUSHTI?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHIV SRUSHTI in Shendra Jahangir, Aurangabad is P51500030274.
Is SHIV SRUSHTI registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIV SRUSHTI is registered as P51500030274 and its status is "Registered and active".
What is the construction status of SHIV SRUSHTI?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIV SRUSHTI's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does SHIV SRUSHTI have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is SHIV SRUSHTI safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIV SRUSHTI is registered on MahaRERA as P51500030274, its completion date has moved 69 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHIV SRUSHTI's possession date changes?
The latest dates are on SHIV SRUSHTI's MahaRERA page (P51500030274). GharKundli's Kundli Watch sends a free WhatsApp update on SHIV SRUSHTI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHIV SRUSHTI have?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIV SRUSHTI has 4 buildings filed: Block A with 3 floors and 6 units; Block B with 3 floors and 6 units; Block C with 3 floors and 6 units; Block D with 3 floors and 6 units.
How big is the land of SHIV SRUSHTI?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIV SRUSHTI stands on 4,701 sq m of land (about 1.2 acres), with 2,096 sq m of sanctioned built-up area and 2,798 sq m of recreational open space.
Where can I read reviews of SHIV SRUSHTI?
Google Maps has reviews of SHIV SRUSHTI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHIV SRUSHTI?
SHIV SRUSHTI by SHIVTEJ BUILDERS & DEVELOPERS is in Shendra Jahangir, Aurangabad (pincode 431007), Maharashtra, and is registered on MahaRERA as P51500030274, per GharKundli's check of MahaRERA records.
How many homes are in SHIV SRUSHTI?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIV SRUSHTI has 24 homes in 4 towers registered on MahaRERA, and 8% of them are sold or booked.
When was SHIV SRUSHTI registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIV SRUSHTI was registered on MahaRERA on 15 August 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on SHIV SRUSHTI?
No court cases are listed for SHIV SRUSHTI on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SHIV SRUSHTI?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHIVTEJ BUILDERS & DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of SHIV SRUSHTI
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Aurangabad →
Other projects in Aurangabad
- Shree Radhe Kunj
- NABHRAJ TRILOK HEIGHTS MHADA
- PARAM SUVARNVASTU
- KHINVANSARA AURA
- BUSINESS TRIANGLE
- Siddhi Ellora Business Park
- PRASSANA HIGH CLASS CITY PHASE - I
- HORIZON
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.