SKY COURT

by ASPIRE CONSTRUCTIONS LLP · Sawedi, Ahmednagar

Possession date of SKY COURT: 30 April 2029, moved from 30 June 2024 (54 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52200000077, and currently active. Its completion date has moved from June 2024 to April 2029: 54 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SKY COURT?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SKY COURT has moved

  1. 30 June 2024

    Completion date given when the project was registered

  2. 31 December 2028

    Extended at the builder's request (MahaRERA application EXT52200027132)

    Reason the builder gave MahaRERA:
    “REASON FOR SEEKING EXTENSION 1) The said Project SKY COURT comprises of 3 buildings i.e. North Court, Central Court and South Court. The North Court building was completed back in April 2018 and the OC bearing No. TP-2127 for the North Cour…” Read the full reason“REASON FOR SEEKING EXTENSION 1) The said Project SKY COURT comprises of 3 buildings i.e. North Court, Central Court and South Court. The North Court building was completed back in April 2018 and the OC bearing No. TP-2127 for the North Court building was received on 17.04.2018. All flats in the North Court building were sold only after receipt of OC. Form 4 Architects completion certificate dated 18.05.2018 was also uploaded on the MahaRERA project webpage. 2) Till date no units have been booked or sold in the Central Court building and the South Court building and these two buildings have…”
  3. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SKY COURT’s extension records on MahaRERA (P52200000077), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SKY COURT

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52200000077
Status
Registered and active
Builder
ASPIRE CONSTRUCTIONS LLP
Location
Sawedi, Ahmednagar · 414003
Project type
Others
Registered on
28 Jun 2017
Completion date at registration
June 2024
Latest completion date
April 2029
Delay so far
54 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
114
Sold or booked
34%
Towers
3
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of SKY COURT, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NORTH COURT100%100%100%100%
CENTRAL COURT90%16%20%0%
SOUTH COURT100%20%25%0%

Commencement certificate (CC), as filed on MahaRERA

  • NORTH COURT: covers 8 floors
  • CENTRAL COURT: covers 13 floors
  • SOUTH COURT: covers 13 floors

Latest CC order on MahaRERA: dated 15/07/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SKY COURT every month.

SKY COURT: buildings, flats and land, as filed on MahaRERA

  • Buildings: NORTH COURT (9 floors, 44 units) · CENTRAL COURT (9 floors, 36 units) · SOUTH COURT (9 floors, 36 units)
  • Car parking: 1 covered, 7 open
  • Land: 3,960 sq m (about 1.0 acres) · sanctioned built-up 6,930 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SKY COURT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SKY COURT: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SKY COURT

What is the possession date of SKY COURT?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SKY COURT in Sawedi, Ahmednagar is 30 April 2029 — 54 months later than 30 June 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SKY COURT?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SKY COURT's builder has filed on MahaRERA, the official one, is 30 April 2029, already 54 months later than the 30 June 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SKY COURT extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SKY COURT's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "REASON FOR SEEKING EXTENSION 1) The said Project SKY COURT comprises of 3 buildings i.e. North Court, Central Court and South Court. The North Court building was completed back in April 2018 and the OC bearing No. TP-2127 for the North Court building was received on 17.04.2018. All flats in the North Court building were sold only after receipt of OC. Form 4 Architects completion certificate dated 18.05.2018 was also uploaded on the MahaRERA project webpage. 2) Till date no units have been booked or sold in the Central Court building and the South Court building and these two buildings have…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SKY COURT?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SKY COURT in Sawedi, Ahmednagar is P52200000077.

Is SKY COURT registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SKY COURT is registered as P52200000077 and its status is "Registered and active".

What is the construction status of SKY COURT?

According to GharKundli's check of MahaRERA records (updated October 2026), SKY COURT's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 16% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does SKY COURT have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SKY COURT safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SKY COURT is registered on MahaRERA as P52200000077, its completion date has moved 54 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SKY COURT's possession date changes?

The latest dates are on SKY COURT's MahaRERA page (P52200000077). GharKundli's Kundli Watch sends a free WhatsApp update on SKY COURT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SKY COURT have?

According to GharKundli's check of MahaRERA records (updated October 2026), SKY COURT has 3 buildings filed: NORTH COURT with 9 floors and 44 units; CENTRAL COURT with 9 floors and 36 units; SOUTH COURT with 9 floors and 36 units.

How much parking does SKY COURT have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered and 7 open car parking spaces for SKY COURT.

How big is the land of SKY COURT?

According to GharKundli's check of MahaRERA records (updated October 2026), SKY COURT stands on 3,960 sq m of land (about 1.0 acres), with 6,930 sq m of sanctioned built-up area.

Where can I read reviews of SKY COURT?

Google Maps has reviews of SKY COURT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SKY COURT?

SKY COURT by ASPIRE CONSTRUCTIONS LLP is in Sawedi, Ahmednagar (pincode 414003), Maharashtra, and is registered on MahaRERA as P52200000077, per GharKundli's check of MahaRERA records.

How many homes are in SKY COURT?

According to GharKundli's check of MahaRERA records (updated October 2026), SKY COURT has 114 homes in 3 towers registered on MahaRERA, and 34% of them are sold or booked.

When was SKY COURT registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SKY COURT was registered on MahaRERA on 28 June 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SKY COURT?

No court cases are listed for SKY COURT on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SKY COURT?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ASPIRE CONSTRUCTIONS LLP.

All projects with possession due in 2029 in Ahmednagar →

Other projects in Nagar

All 26 projects in Savedi (414003) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.