SAI MORESHWAR DIVINE
by MAATOSHREE SHELTERS PVT LTD · Near Sai nagar station, AhmednagarAlso near Shirdi, Ambad A.S
Possession date of SAI MORESHWAR DIVINE: 31 March 2024, moved from 31 March 2021 (36 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52200009308. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (March 2024) has passed.
What do you want to know about SAI MORESHWAR DIVINE?
How the possession date of SAI MORESHWAR DIVINE has moved
31 March 2021
Completion date given when the project was registered
31 March 2024
Extended at the builder's request (MahaRERA application EXT52200011791)
Reason the builder gave MahaRERA: “DUE TO COVID”
Source: SAI MORESHWAR DIVINE’s extension records on MahaRERA (P52200009308), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SAI MORESHWAR DIVINE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the March 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52200009308
- Status
- Lapsed (registration period ended)
- Builder
- MAATOSHREE SHELTERS PVT LTD
- Location
- Near Sai nagar station, Ahmednagar · 423109
- Project type
- Residential / Group Housing
- Registered on
- 22 Aug 2017
- Completion date at registration
- March 2021
- Latest completion date
- March 2024
- Delay so far
- 36 months
- Homes
- 70
- Sold or booked
- 46%
- Towers
- 3
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of SAI MORESHWAR DIVINE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING A | 100% | 100% | 95% | 45% |
| WING B | 100% | 100% | 75% | 30% |
| WING C | 100% | 40% | 30% | 10% |
Commencement certificate (CC), as filed on MahaRERA
- WING A: covers 9 floors
- WING B: covers 9 floors
- WING C: covers 9 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI MORESHWAR DIVINE every month.
SAI MORESHWAR DIVINE: buildings, flats and land, as filed on MahaRERA
- Buildings: WING A (9 floors, 28 units) · WING B (9 floors, 28 units) · WING C (9 floors, 14 units)
- Car parking: 38 covered
- Land: 3,600 sq m (about 0.9 acres) · sanctioned built-up 4,441 sq m
- Boundaries filed include: RAILWAY BOUNDARIES
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SAI MORESHWAR DIVINE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SAI MORESHWAR DIVINE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SAI MORESHWAR DIVINE
What is the possession date of SAI MORESHWAR DIVINE?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SAI MORESHWAR DIVINE in Near Sai nagar station, Ahmednagar is 31 March 2024 — 36 months later than 31 March 2021, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for SAI MORESHWAR DIVINE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI MORESHWAR DIVINE's builder has filed on MahaRERA, the official one, is 31 March 2024, already 36 months later than the 31 March 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SAI MORESHWAR DIVINE extended?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI MORESHWAR DIVINE's builder applied to MahaRERA to extend the completion date once: to 31 March 2024, giving the reason "DUE TO COVID".
What is the RERA number of SAI MORESHWAR DIVINE?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SAI MORESHWAR DIVINE in Near Sai nagar station, Ahmednagar is P52200009308.
Is SAI MORESHWAR DIVINE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI MORESHWAR DIVINE is registered as P52200009308 and its status is "Lapsed (registration period ended)".
What is the construction status of SAI MORESHWAR DIVINE?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI MORESHWAR DIVINE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 40% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does SAI MORESHWAR DIVINE have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SAI MORESHWAR DIVINE safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI MORESHWAR DIVINE is registered on MahaRERA as P52200009308, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 36 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SAI MORESHWAR DIVINE's possession date changes?
The latest dates are on SAI MORESHWAR DIVINE's MahaRERA page (P52200009308). GharKundli's Kundli Watch sends a free WhatsApp update on SAI MORESHWAR DIVINE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SAI MORESHWAR DIVINE have?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI MORESHWAR DIVINE has 3 buildings filed: WING A with 9 floors and 28 units; WING B with 9 floors and 28 units; WING C with 9 floors and 14 units.
How much parking does SAI MORESHWAR DIVINE have?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 38 covered car parking spaces for SAI MORESHWAR DIVINE.
How big is the land of SAI MORESHWAR DIVINE?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI MORESHWAR DIVINE stands on 3,600 sq m of land (about 0.9 acres), with 4,441 sq m of sanctioned built-up area.
Where can I read reviews of SAI MORESHWAR DIVINE?
Google Maps has reviews of SAI MORESHWAR DIVINE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SAI MORESHWAR DIVINE?
SAI MORESHWAR DIVINE by MAATOSHREE SHELTERS PVT LTD is in Near Sai nagar station, Ahmednagar (pincode 423109), near Shirdi, Ambad A.S, Maharashtra, and is registered on MahaRERA as P52200009308, per GharKundli's check of MahaRERA records. Its boundaries filed there include RAILWAY BOUNDARIES.
How many homes are in SAI MORESHWAR DIVINE?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI MORESHWAR DIVINE has 70 homes in 3 towers registered on MahaRERA, and 46% of them are sold or booked.
When was SAI MORESHWAR DIVINE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI MORESHWAR DIVINE was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SAI MORESHWAR DIVINE?
No court cases are listed for SAI MORESHWAR DIVINE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SAI MORESHWAR DIVINE?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MAATOSHREE SHELTERS PVT LTD, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SAI MORESHWAR DIVINE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Rahta
- Dhadiwal Raisoni Plaza
- Madhuban
- Sandal Suites Shirdi
- SHIVAY HEIGHTS
- DIVATE RESIDENCY
- RAJMUDRA APARTMENT
- SILVEROAK GOLD COAST
- GURUPRASAD RESIDENCY
Other projects by MAATOSHREE SHELTERS PVT LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.