Skip to content
GharKundli

Durga Heights

by SANDIP PIRAJI KOTKAR · Bhushan Nagar Kedgaon, Ahmednagar 414003

What’s in the report? →

Possession: Durga Heights (MahaRERA P52200012827) is marked completed on MahaRERA. It has 19 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52200012827. Status: Completed.

Source: MahaRERA website — records for P52200012827, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Durga Heights?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Durga Heights

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2019 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52200012827
Status
Completed
Builder
SANDIP PIRAJI KOTKAR
Location
Bhushan Nagar Kedgaon, Ahmednagar · 414003
Project type
Others
Registered on
7 Sep 2017
Completion date at registration
June 2019
Homes
19
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Durga Heights, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
DURGA HEIGHTS100%100%100%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Durga Heights every 1–2 months.

Durga Heights: buildings, flats and land, as filed on MahaRERA

  • Buildings: DURGA HEIGHTS (5 floors)
  • Land: 528 sq m (about 0.1 acres) · sanctioned built-up 507 sq m
  • Land, as filed: S NO 10/6A,10/6B,10/6C,10/7/2,10/9,10/10,10/12,10/13,10/14,10/15,10/16
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Durga Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Durga Heights: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Durga Heights

What is the possession date of Durga Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Durga Heights in Bhushan Nagar Kedgaon, Ahmednagar is 30 June 2019.

Is the builder's possession date different from the MahaRERA date for Durga Heights?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Durga Heights's builder has filed on MahaRERA, the official one, is 30 June 2019, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Durga Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Durga Heights in Bhushan Nagar Kedgaon, Ahmednagar is P52200012827.

Is Durga Heights registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Durga Heights is registered as P52200012827 and its status is "Completed".

What is the current construction status of Durga Heights? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Durga Heights's status on MahaRERA is "Completed". As filed by the builder, slab work on DURGA HEIGHTS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Durga Heights have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Durga Heights safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Durga Heights is registered on MahaRERA as P52200012827, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Durga Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Durga Heights is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Durga Heights?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Durga Heights: gharkundli.com/tools/property-cost-calculator

Has Durga Heights received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Durga Heights is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Durga Heights completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Durga Heights is marked completed on MahaRERA, and the completion date filed there is 30 June 2019. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Durga Heights uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Durga Heights was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Durga Heights's possession date changes?

The latest dates are on Durga Heights's MahaRERA page (P52200012827). GharKundli's Kundli Watch sends a free WhatsApp update on Durga Heights every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Durga Heights have?

According to GharKundli's check of MahaRERA records (updated November 2026), Durga Heights has one building filed: DURGA HEIGHTS with 5 floors.

How big is the land of Durga Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Durga Heights stands on 528 sq m of land (about 0.1 acres), with 507 sq m of sanctioned built-up area.

What are the reviews of Durga Heights?

Google Maps has reviews of Durga Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Durga Heights?

Durga Heights by SANDIP PIRAJI KOTKAR is in Bhushan Nagar Kedgaon, Ahmednagar, pincode 414003, Maharashtra, and is registered on MahaRERA as P52200012827, per GharKundli's check of MahaRERA records. Its land is filed as S NO 10/6A,10/6B,10/6C,10/7/2,10/9,10/10,10/12,10/13,10/14,10/15,10/16. GharKundli lists all 85 MahaRERA projects in Savedi (414003).

How many flats are in Durga Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Durga Heights has 19 homes in 1 tower registered on MahaRERA.

When was Durga Heights registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Durga Heights was registered on MahaRERA on 7 September 2017. GharKundli did not find a title report on the land on file there.

Does Durga Heights have any legal issues or court cases?

No court cases are listed for Durga Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Durga Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SANDIP PIRAJI KOTKAR.

Other projects in Nagar

All 85 projects in Savedi (414003) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.