VRUNDAVAN CITY
by RAMAN BABASO KHAMKAR · Village Area, Ahmednagar
Possession date of VRUNDAVAN CITY: 31 December 2024, moved from 31 December 2019 (60 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52200018783. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2024) has passed.
What do you want to know about VRUNDAVAN CITY?
How the possession date of VRUNDAVAN CITY has moved
31 December 2019
Completion date given when the project was registered
31 December 2024
Extended at the builder's request (MahaRERA application EXT52200016600)
Reason the builder gave MahaRERA: “The Project was stopped due to shortage of funds, and Later Pandemic situation arised hence could not be started. now we want to complete the project.”
Source: VRUNDAVAN CITY’s extension records on MahaRERA (P52200018783), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on VRUNDAVAN CITY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52200018783
- Status
- Lapsed (registration period ended)
- Builder
- RAMAN BABASO KHAMKAR
- Location
- Village Area, Ahmednagar · 414403
- Project type
- Residential / Group Housing
- Registered on
- 4 Dec 2018
- Completion date at registration
- December 2019
- Latest completion date
- December 2024
- Delay so far
- 60 months
- Homes
- 6
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of VRUNDAVAN CITY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ROW HOUSE 4 | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on VRUNDAVAN CITY every month.
VRUNDAVAN CITY: buildings, flats and land, as filed on MahaRERA
- Buildings: ROW HOUSE 4 (2 floors)
- Land: 470 sq m (about 0.1 acres) · sanctioned built-up 470 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of VRUNDAVAN CITY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
VRUNDAVAN CITY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about VRUNDAVAN CITY
What is the possession date of VRUNDAVAN CITY?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for VRUNDAVAN CITY in Village Area, Ahmednagar is 31 December 2024 — 60 months later than 31 December 2019, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for VRUNDAVAN CITY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date VRUNDAVAN CITY's builder has filed on MahaRERA, the official one, is 31 December 2024, already 60 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of VRUNDAVAN CITY extended?
According to GharKundli's check of MahaRERA records (updated November 2026), VRUNDAVAN CITY's builder applied to MahaRERA to extend the completion date once: to 31 December 2024, giving the reason "The Project was stopped due to shortage of funds, and Later Pandemic situation arised hence could not be started. now we want to complete the project.".
What is the RERA number of VRUNDAVAN CITY?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of VRUNDAVAN CITY in Village Area, Ahmednagar is P52200018783.
Is VRUNDAVAN CITY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), VRUNDAVAN CITY is registered as P52200018783 and its status is "Lapsed (registration period ended)".
What is the construction status of VRUNDAVAN CITY?
According to GharKundli's check of MahaRERA records (updated November 2026), VRUNDAVAN CITY's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on ROW HOUSE 4 is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does VRUNDAVAN CITY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is VRUNDAVAN CITY safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), VRUNDAVAN CITY is registered on MahaRERA as P52200018783, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 60 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if VRUNDAVAN CITY's possession date changes?
The latest dates are on VRUNDAVAN CITY's MahaRERA page (P52200018783). GharKundli's Kundli Watch sends a free WhatsApp update on VRUNDAVAN CITY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does VRUNDAVAN CITY have?
According to GharKundli's check of MahaRERA records (updated November 2026), VRUNDAVAN CITY has one building filed: ROW HOUSE 4 with 2 floors.
How big is the land of VRUNDAVAN CITY?
According to GharKundli's check of MahaRERA records (updated November 2026), VRUNDAVAN CITY stands on 470 sq m of land (about 0.1 acres), with 470 sq m of sanctioned built-up area.
Where can I read reviews of VRUNDAVAN CITY?
Google Maps has reviews of VRUNDAVAN CITY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is VRUNDAVAN CITY?
VRUNDAVAN CITY by RAMAN BABASO KHAMKAR is in Village Area, Ahmednagar (pincode 414403), Maharashtra, and is registered on MahaRERA as P52200018783, per GharKundli's check of MahaRERA records.
How many homes are in VRUNDAVAN CITY?
According to GharKundli's check of MahaRERA records (updated November 2026), VRUNDAVAN CITY has 6 homes in 1 tower registered on MahaRERA.
When was VRUNDAVAN CITY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), VRUNDAVAN CITY was registered on MahaRERA on 4 December 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on VRUNDAVAN CITY?
No court cases are listed for VRUNDAVAN CITY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of VRUNDAVAN CITY?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is RAMAN BABASO KHAMKAR, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of VRUNDAVAN CITY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Karjat
- SAI ICON BUSINESS CENTRE
- PRABHAT CORNER
- GALAXY APARTMENT
- MOHAN NAGAR
- HARSH NAGAR
- R M Dhariwal Township Rashin Plotting
Other projects by RAMAN BABASO KHAMKAR
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.