Skip to content
GharKundli

Vyankatesh Residancy

by Sandip Balchand Surana · Opp Jadhav Petrol Pump, Ahmednagar 414001

What’s in the report? →

Possession: Vyankatesh Residancy (MahaRERA P52200022910) is marked completed on MahaRERA. It has 39 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52200022910. Status: Completed.

Source: MahaRERA website — records for P52200022910, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Vyankatesh Residancy?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Vyankatesh Residancy

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52200022910
Status
Completed
Builder
Sandip Balchand Surana
Location
Opp Jadhav Petrol Pump, Ahmednagar · 414001
Project type
Residential / Group Housing
Registered on
1 Nov 2019
Completion date at registration
October 2024
Latest completion date
October 2024
Homes
39
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Vyankatesh Residancy, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
VYANKATESH RESIDANCY0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vyankatesh Residancy every 1–2 months.

Vyankatesh Residancy: buildings, flats and land, as filed on MahaRERA

  • Buildings: VYANKATESH RESIDANCY (6 floors)
  • Land: 1,261 sq m (about 0.3 acres) · sanctioned built-up 2,336 sq m
  • Land, as filed: 241/6 PLOT NO 2
  • Map: Get directions

The builder’s record and reviews

Sandip Balchand Surana has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 2 finished, all within the promised date. No complaints on MahaRERA.

Read Google reviews of Vyankatesh Residancy →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Vyankatesh Residancy: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Vyankatesh Residancy

What is the possession date of Vyankatesh Residancy?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Vyankatesh Residancy in Opp Jadhav Petrol Pump, Ahmednagar is 1 October 2024.

Is the builder's possession date different from the MahaRERA date for Vyankatesh Residancy?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Vyankatesh Residancy's builder has filed on MahaRERA, the official one, is 1 October 2024, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Vyankatesh Residancy?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Vyankatesh Residancy in Opp Jadhav Petrol Pump, Ahmednagar is P52200022910.

Is Vyankatesh Residancy registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Vyankatesh Residancy is registered as P52200022910 and its status is "Completed".

What is the current construction status of Vyankatesh Residancy? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Vyankatesh Residancy's status on MahaRERA is "Completed". As filed by the builder, slab work on VYANKATESH RESIDANCY is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Vyankatesh Residancy have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Vyankatesh Residancy safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Vyankatesh Residancy is registered on MahaRERA as P52200022910, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Vyankatesh Residancy?

According to GharKundli's check of MahaRERA records (updated November 2026), Vyankatesh Residancy is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Vyankatesh Residancy?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Vyankatesh Residancy: gharkundli.com/tools/property-cost-calculator

Has Vyankatesh Residancy received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Vyankatesh Residancy is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Vyankatesh Residancy completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Vyankatesh Residancy is marked completed on MahaRERA, and the completion date filed there is 1 October 2024. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Vyankatesh Residancy uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Vyankatesh Residancy was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Vyankatesh Residancy's possession date changes?

The latest dates are on Vyankatesh Residancy's MahaRERA page (P52200022910). GharKundli's Kundli Watch sends a free WhatsApp update on Vyankatesh Residancy every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Vyankatesh Residancy have?

According to GharKundli's check of MahaRERA records (updated November 2026), Vyankatesh Residancy has one building filed: VYANKATESH RESIDANCY with 6 floors.

How big is the land of Vyankatesh Residancy?

According to GharKundli's check of MahaRERA records (updated November 2026), Vyankatesh Residancy stands on 1,261 sq m of land (about 0.3 acres), with 2,336 sq m of sanctioned built-up area.

What is the track record of Vyankatesh Residancy's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Sandip Balchand Surana has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 2 finished, all within the promised date. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Vyankatesh Residancy?

Google Maps has reviews of Vyankatesh Residancy written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Vyankatesh Residancy?

Vyankatesh Residancy by Sandip Balchand Surana is in Opp Jadhav Petrol Pump, Ahmednagar, pincode 414001, Maharashtra, and is registered on MahaRERA as P52200022910, per GharKundli's check of MahaRERA records. Its land is filed as 241/6 PLOT NO 2. GharKundli lists all 63 MahaRERA projects in Ahmednagar (414001).

How many flats are in Vyankatesh Residancy?

According to GharKundli's check of MahaRERA records (updated November 2026), Vyankatesh Residancy has 39 homes in 1 tower registered on MahaRERA.

When was Vyankatesh Residancy registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Vyankatesh Residancy was registered on MahaRERA on 1 November 2019. GharKundli did not find a title report on the land on file there.

Does Vyankatesh Residancy have any legal issues or court cases?

No court cases are listed for Vyankatesh Residancy on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Vyankatesh Residancy?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Sandip Balchand Surana, which has 1 other project registered on MahaRERA.

Other projects in Nagar

All 63 projects in Ahmednagar (414001) →

Other projects by Sandip Balchand Surana

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.