Krushna Pride 21
by KRUSHNA PROPERTIES · Gunjalwadi Sangamner, Ahmednagar 422605
What’s in the report? →Possession date of Krushna Pride 21 (MahaRERA P52200031826): 31 December 2025, and it has already passed. It has 3,080 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52200031826. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P52200031826, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about Krushna Pride 21?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
GharKundli’s full report on Krushna Pride 21
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52200031826
- Status
- Lapsed (registration period ended)
- Builder
- KRUSHNA PROPERTIES
- Location
- Gunjalwadi Sangamner, Ahmednagar · 422605
- Project type
- Residential / Group Housing
- Registered on
- 12 Nov 2021
- Completion date at registration
- December 2025
- Homes
- 3,080
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Krushna Pride 21, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| KRUSHNA PRIDE 21 | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Krushna Pride 21 every 1–2 months.
Krushna Pride 21: buildings, flats and land, as filed on MahaRERA
- Buildings: KRUSHNA PRIDE 21 (5 floors)
- Land: 1,345 sq m (about 0.3 acres) · sanctioned built-up 1,345 sq m · recreational space 403 sq m
- Land, as filed: SURVEY NO 131/41/1/2 GUNJALWADI
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Krushna Properties (a group of 4 linked companies) has 6 projects on MahaRERA since 2020, this one included. Of the 6 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, none past the promised date yet; 2 lapsed. No complaints on MahaRERA.
Read Google reviews of Krushna Pride 21 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Krushna Pride 21: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Krushna Pride 21
What is the possession date of Krushna Pride 21?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Krushna Pride 21 in Gunjalwadi Sangamner, Ahmednagar is 31 December 2025. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Krushna Pride 21?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Krushna Pride 21's builder has filed on MahaRERA, the official one, is 31 December 2025, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Krushna Pride 21?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Krushna Pride 21 in Gunjalwadi Sangamner, Ahmednagar is P52200031826.
Is Krushna Pride 21 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Krushna Pride 21 is registered as P52200031826 and its status is "Lapsed (registration period ended)".
What is the current construction status of Krushna Pride 21? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Krushna Pride 21's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on KRUSHNA PRIDE 21 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Krushna Pride 21 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Krushna Pride 21 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Krushna Pride 21 is registered on MahaRERA as P52200031826, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Krushna Pride 21?
Krushna Pride 21 isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Krushna Pride 21?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Krushna Pride 21: gharkundli.com/tools/property-cost-calculator
Has Krushna Pride 21 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Krushna Pride 21 isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Krushna Pride 21?
According to GharKundli's check of MahaRERA records (updated November 2026), Krushna Pride 21's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Krushna Pride 21 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Krushna Pride 21 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Krushna Pride 21's possession date changes?
The latest dates are on Krushna Pride 21's MahaRERA page (P52200031826). GharKundli's Kundli Watch sends a free WhatsApp update on Krushna Pride 21 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Krushna Pride 21 have?
According to GharKundli's check of MahaRERA records (updated November 2026), Krushna Pride 21 has one building filed: KRUSHNA PRIDE 21 with 5 floors.
How big is the land of Krushna Pride 21?
According to GharKundli's check of MahaRERA records (updated November 2026), Krushna Pride 21 stands on 1,345 sq m of land (about 0.3 acres), with 1,345 sq m of sanctioned built-up area and 403 sq m of recreational open space.
What is the track record of Krushna Pride 21's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Krushna Properties (a group of 4 linked companies) has 6 projects on MahaRERA since 2020, this one included. Of the 6 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, none past the promised date yet; 2 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Krushna Pride 21?
Google Maps has reviews of Krushna Pride 21 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Krushna Pride 21?
Krushna Pride 21 by KRUSHNA PROPERTIES is in Gunjalwadi Sangamner, Ahmednagar, pincode 422605, Maharashtra, and is registered on MahaRERA as P52200031826, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO 131/41/1/2 GUNJALWADI. GharKundli lists all 21 MahaRERA projects in Sangamner (422605).
How many flats are in Krushna Pride 21?
According to GharKundli's check of MahaRERA records (updated November 2026), Krushna Pride 21 has 3,080 homes in 1 tower registered on MahaRERA.
When was Krushna Pride 21 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Krushna Pride 21 was registered on MahaRERA on 12 November 2021. GharKundli did not find a title report on the land on file there.
Does Krushna Pride 21 have any legal issues or court cases?
No court cases are listed for Krushna Pride 21 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Krushna Pride 21?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is KRUSHNA PROPERTIES, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Krushna Pride 21
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Sangamner
- Unicorn Nest II
- Prestige Park
- Chintamani Residency
- Samartha Plaza
- Sangamner Central
- Aman Plaza
- Building at CTS No 2454
- Kanchan Comfortz Sangamner Phase 2
Other projects by KRUSHNA PROPERTIES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.