SWAMI VIVEKANAND PALACE
by VIVEKANAND CONSTRUCTION · Nagapur, Ahmednagar
Possession date of SWAMI VIVEKANAND PALACE: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52200033694, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SWAMI VIVEKANAND PALACE?
How the possession date of SWAMI VIVEKANAND PALACE has moved
31 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SWAMI VIVEKANAND PALACE’s extension records on MahaRERA (P52200033694), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SWAMI VIVEKANAND PALACE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52200033694
- Status
- Registered and active
- Builder
- VIVEKANAND CONSTRUCTION
- Location
- Nagapur, Ahmednagar · 414111
- Project type
- Others
- Registered on
- 2 Mar 2022
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 131
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SWAMI VIVEKANAND PALACE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SWAMI VIVEKANAND PALACE | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SWAMI VIVEKANAND PALACE every month.
SWAMI VIVEKANAND PALACE: buildings, flats and land, as filed on MahaRERA
- Buildings: SWAMI VIVEKANAND PALACE (6 floors)
- Land: 2,365 sq m (about 0.6 acres) · sanctioned built-up 7,705 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SWAMI VIVEKANAND PALACE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SWAMI VIVEKANAND PALACE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SWAMI VIVEKANAND PALACE
What is the possession date of SWAMI VIVEKANAND PALACE?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SWAMI VIVEKANAND PALACE in Nagapur, Ahmednagar is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SWAMI VIVEKANAND PALACE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SWAMI VIVEKANAND PALACE's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SWAMI VIVEKANAND PALACE?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SWAMI VIVEKANAND PALACE in Nagapur, Ahmednagar is P52200033694.
Is SWAMI VIVEKANAND PALACE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SWAMI VIVEKANAND PALACE is registered as P52200033694 and its status is "Registered and active".
What is the construction status of SWAMI VIVEKANAND PALACE?
According to GharKundli's check of MahaRERA records (updated November 2026), SWAMI VIVEKANAND PALACE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SWAMI VIVEKANAND PALACE is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does SWAMI VIVEKANAND PALACE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is SWAMI VIVEKANAND PALACE safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SWAMI VIVEKANAND PALACE is registered on MahaRERA as P52200033694, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SWAMI VIVEKANAND PALACE's possession date changes?
The latest dates are on SWAMI VIVEKANAND PALACE's MahaRERA page (P52200033694). GharKundli's Kundli Watch sends a free WhatsApp update on SWAMI VIVEKANAND PALACE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SWAMI VIVEKANAND PALACE have?
According to GharKundli's check of MahaRERA records (updated November 2026), SWAMI VIVEKANAND PALACE has one building filed: SWAMI VIVEKANAND PALACE with 6 floors.
How big is the land of SWAMI VIVEKANAND PALACE?
According to GharKundli's check of MahaRERA records (updated November 2026), SWAMI VIVEKANAND PALACE stands on 2,365 sq m of land (about 0.6 acres), with 7,705 sq m of sanctioned built-up area.
Where can I read reviews of SWAMI VIVEKANAND PALACE?
Google Maps has reviews of SWAMI VIVEKANAND PALACE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SWAMI VIVEKANAND PALACE?
SWAMI VIVEKANAND PALACE by VIVEKANAND CONSTRUCTION is in Nagapur, Ahmednagar (pincode 414111), Maharashtra, and is registered on MahaRERA as P52200033694, per GharKundli's check of MahaRERA records.
How many homes are in SWAMI VIVEKANAND PALACE?
According to GharKundli's check of MahaRERA records (updated November 2026), SWAMI VIVEKANAND PALACE has 131 homes in 1 tower registered on MahaRERA.
When was SWAMI VIVEKANAND PALACE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SWAMI VIVEKANAND PALACE was registered on MahaRERA on 2 March 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on SWAMI VIVEKANAND PALACE?
No court cases are listed for SWAMI VIVEKANAND PALACE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SWAMI VIVEKANAND PALACE?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VIVEKANAND CONSTRUCTION.
Check it yourself on MahaRERA
- How to check the possession date of SWAMI VIVEKANAND PALACE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Nagar
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.